Majority
By its complaint the city of Vernon sought to quiet title to certain real and personal property described as constituting the Vernon electric system and to recover possession thereof, together with damages, from the Southern California Edison Company. The defendant, hereinafter called Edison, filed its answer and, in addition, a cross-complaint under which it sought a declaratory judgment as to the rights and duties of the parties under their agreement with respect to the property involved.
The nature of the controversy can be made apparent by a résumé of the facts found and the legal conclusions of the trial court with respect thereto. Such summary is as follows:
1 The importance of this date in the light of the agreement of February 23, 1937, between Vernon and Edison will hereinafter be noted.
2 In section 31 of the agreement it is stated: “This agreement shall not be effective until it has been approved by the Railroad Commission of the State of California. ’ ’ In the decision of the Eailroad Commission of May 10, 1937, it was said in part: “The agreement contains a condition subsequent which provides that the City of Vernon can terminate said agreement at any time when the Edison Company in the City of Vernon charges rates higher than its rates on other portions of the Edison System within Los Angeles County, or higher than the rates of the Department of Water and Power of the City of Los Angeles for similar service. In the event of the termination of the agreement because of the breach of this condition, the Edison Company will receive no compensation for the properties it is now transferring to the City of Vernon. If the agreement is not renewed by the City of Vernon at the end of a 10-year period, the Edison Company, is entitled to reimbursement for its expenditures on account of properties transferred to the City less accrued depreciation on such properties. . . . Thus, while the City transfers possession of its plant to the Edison Company, it does so only upon condition that its rate policy be maintained. ’ ’ The order of the commission was as follows: “It Is Hereby Ordered that Southern California Edison Company Ltd. be, and it is hereby authorized to execute and carry into effect an agreement similar in terms to the agreement filed in this proceeding as Exhibit A, provided nothing contained in such agreement nor in this decision shall by the Edison Company, its successors or assigns or by any one else, be held to limit the Commission’s authority from ordering and directing said Southern California Edison Company Ltd., its successors or assigns, from charging in said City of Vernon rates for electric service which are higher or lower than the rates provided for in Sgid agreement, ’ ’
(a) the reasonable cost of the material, equipment and structures' constructed or installed by Edison in combining the Vernon electric system and the Edison electric system;
(b) the reasonable cost of Edison’s electric system which Edison granted, transferred, assigned and set over to Vernon in 1937; and
(e) the reasonable cost of all alterations, extensions, additions and improvements made or installed by Edison ' during its possession under the lease;
deducting in'each case certain costs and, also, accrued depreciation upon the items mentioned in (a), (b) and (c), set forth above, according to the formula set forth in section 13. 18. Vernon has never tendered or paid to Edison any sums under such terms of section 13 of the agreement. 19. “The provision of said Section 13 which purports to relieve Vernon of the obligation to compensate Edison for the leasehold property granted, transferred, assigned and set over to Vernon by Edison by
3 It is to be further noted that the trial court determined that even if Edison’s possession after December 19, 1957, was wrongful, “as to *386 which the Court finds and concludes to the contrary,” the amount of damages measured by the reasonable value of the use and occupation of the leasehold property from that date to the date of judgment would be in the same amount because the amount would be calculated in the same manner as above.
The judgment was, in part, that Vernon is the owner of the property involved and, upon payment to Edison of the sum of $3,540,758.91, is entitled to possession of the property, free and clear of all claims of Edison, but that Edison is entitled to retain possession until such sum is paid. In addition, judgment was given in favor of Vernon for $398,963.16. Such amount was determined as follows:
‘ ‘An amount equal to the net unpaid rentals as reserved in the said lease, computed for the period December 19, 1957 to the present time .............................$188,379.71
4 The judgment was entered on June 8, 1959.
5 Section 27 of the agreement of February 23, 1937, is as follows: “Edison agrees that in the event any suit or proceedings are brought to enforce or interpret any of the terms and conditions of this agreement it will, in the event any judgment in favor of Vernon is entered in such suit or proceedings, pay to Vernon a reasonable attorneys’ fee to be fixed by the court in said action or proceeding.”
“5-%% of $187,000 per month for the period
December 19,1957 to the present time... .$175,519.70
“Reasonable value of services rendered by
attorneys for Vernon..................$ 35,063.75
Total........$398,963.16”
Vernon appeals from the judgment insofar as it is thereby required to pay Edison the sum of $3,540,758.91 before obtaining possession and having its title quieted to the property involved and insofar as it provides for a money judgment for only $398,963.16, except that Vernon raises no issue as to the sum of $35,063.75 awarded to it as attorneys’ fees. Edison appeals from the judgment insofar as it relates to the termination of Edison’s rights to continue to operate the Vernon system under the agreement and insofar as it orders judgment for any amount in excess of unpaid net rentals reserved in the agreement.
It is Edison’s contention that the trial court erred in holding that the provisions of section 5(c) as to the termination of the leasehold are valid and enforceable. It is asserted that the condition subsequent therein embodied constitutes an attempt by Vernon to regulate the rates to be charged by a public utility in that it is predicated entirely upon the maintenance of rates by Edison at a specified level. It is true, of course, that the sole authority to determine and regulate the rates of a public utility for service furnished by it rests in the Public Utilities Commission (formerly designated as the Railroad Commission). (Cal. Const., art. XII, § 23; Pub. Util. Code, §§ 454, 728, 729; see Pacific Tel. & Tel. Co. v. City of Los Angeles, 44 Cal.2d 272 , 280 [ 282 P.2d 36 ].) But a municipality may engage in the business of supplying persons within its territory with electricity from electric works constructed and operated by it, as Vernon formerly did, without subjecting itself to the jurisdiction of the Public Utilities Commission as to its rates for service. (City of Pasadena v. Railroad Com., 183 Cal. 526 [ 192 P. 25 , 10 A.L.R. 1425 ]; see Polk v. City of Los Angeles, 26 Cal.2d 519 , 539-540 [ 159 P.2d 931 ].) In its action as to the approval of the agreement of February 23, 1937, the Railroad Commission’s jurisdiction existed only by virtue of the fact that there were involved properties of Edison and an agreement on Edison’s part with respect to the supplying of electricity. (Water Users & Tax
In the light of the applicable law, we turn to the language of section 5 of the agreement which Edison asserts to be invalid and unenforceable. That language is: “Said lease is made on the following conditions subsequent, upon the happening of any one of which, at the option of Vernon, to be exercised by service of written notice upon Edison within the period of thirty (30) days thereafter, the leasehold term herein granted shall cease, and Vernon shall be entitled to repossess the leased property. ...(c) If Edison shall, . . . establish, or at any time for a period longer than fifteen (15) days maintain or continue in effect . . . within the present corporate limits of Vernon, any electric rates or charges for service that are higher than any rates or charges for service for the same or similar service on the system of the Department of Water and Power of the City of Los Angeles, . . .” It is clear that the provision embodies solely a condition subsequent and involves no covenant or promise on the part of Edison to maintain rates. (See Knight v. Black, 19 Cal.App. 518 , 522 [ 126 P. 512 ]; 3 Williston on Contracts [rev. ed.], §§ 665, 670, 671.) Such a covenant, if one had been made, would, of course, not be enforceable in the face of an order of the Public Utilities Commission that Edison increase its rates in Vernon (see Sutter Butte Canal Co. v. Railroad Com., 202 Cal. 179 , 187 [ 259 P. 937 ] (aff'd, 279 U.S. 125 [ 49 S.Ct. 325 , 73 L.Ed. 637 ]); Law v. Railroad Com., 184 Cal. 737 , 739 [ 195 P. 423 , 14 A.L.R. 249 ]; Limoneira Co. v. Railroad Com., 174 Cal. 232 , 238 [ 162 P. 1033 ]), but there still remains the question of the validity and enforceability of the condition subsequent.
It is obvious from the record in this case that at all times since 1933 it has been the purpose of Vernon to assure users of electricity within its highly industrialized area that the rates therefor would not be higher than those of the Depart
6 In the preamble of the agreement of February 23, 1937, such purpose is expressed as follows: “That, Whereas, Vernon owns and operates within its corporate limits an electric generating plant and an interconnected electric transmission and distribution system for the purpose of supplying said City and its inhabitants with light, heat and power, and has established and is continuously maintaining a policy of fixing rates and charges for such service so that they shall be at least as low as rates and charges covering the same or similar service in effect on the electric system of the Department of Water and Power of the City of Los Angeles, or any part thereof, or on the electrical system of Edison within the County of Los Angeles, or any part thereof, including any incorporated territory within said County; and . . . “Whereas, Edison desires to lease from Vernon and upon the terms and conditions hereinafter stated, including the continued maintenance of the policy of Vernon hereinabove referred to of fixing rates and charges for service, Vernon is willing to lease to Edison, the present properties of Vernon herein described, together with the material, equipment and structures to be constructed and/or installed by Edison as hereinafter provided and the properties of Edison granted, transferred, assigned and set over to Vernon pursuant to the terms hereof: ...”
Any conclusion other than that reached by the trial court would mean that while Vernon’s objective could no longer be achieved, Edison would still retain the use of Vernon’s property for the remainder of the 10-year period. In Law v. Railroad Com., supra, 184 Cal. 737 , the contract to which the public utility succeeded was one under which steam and electricity were to be furnished at certain rates for a period of 20 years for the purposes of heating, power, and illumination in a building in the city of San Francisco. The party contracting to furnish such steam and electricity was granted the right, under the agreement, to use parts of the building and premises, including certain improvements, free of charge. Thereafter the Railroad Commission made an order which, in effect, abrogated the provisions of the contract as to rates. The Supreme Court said, at pages 741-742: “If the order attempted to change the rate paid by petitioner and, at the same time, give the power company the right to continue to use the agencies and appliances of petitioner under the contract, then it would, indeed, exceed the jurisdiction of the commission by depriving petitioner of his property without compensation and due process of law. This, however, is not the effect of the order, which simply does what the law permits, namely, fixes the rates to be paid by the consumer, and, therefore, nullifies the compensation fixed by the contract. It follows, of course, in view of the change effected by the order in such an important part of the contract, that petitioner will have the right under the law to rescind the contract, and prevent further use of his property by the former company, except for compensation properly determined.”
Vernon attacks the determination of the trial court that the provisions of sections 5 and 13 of the agreement which purport to allow Vernon to repossess the leasehold property without payment of compensation constitute an unlawful penalty and cannot be enforced in law or equity. It is to be noted that section 13 provides in substance for the payment by Vernon to Edison of the costs to Edison of the property embodied by Edison in the system, subject to certain deductions, such payment to be made “at the end of the leasehold period therein fixed, ... or at the end of any additional leasehold term resulting from the exercise of the option pro
“(a) If Edison shall fail to make when due any of the payments hereinabove provided, and such failure shall continue for a period of ten (10) days after written notice of such failure shall have been served on Edison by Vernon.
“ (b) If Edison shall . . . establish, or at any time maintain or continue in effect . . . within the present corporate limits of Vernon, any electric rates or charges for service which shall be higher than any rates or charges for service . . . for the same or similar service in effect concurrently on any other portion of the system of Edison . . . within the County of Los Angeles, or any part thereof . . .
“ (d) If Edison shall fail to promptly observe and perform any other term, condition, covenant or agreement herein provided to be kept, observed or performed by Edison, and any such failure shall continue for a period of forty-five (45) days after written notice thereof has been served by Vernon upon Edison.”
It is to be noted that aside from the situation defined in section 5(b), which is of the same nature as section 5(c), the grounds of termination relate to matters over which Edison itself has control. The provisions of (b) and (c) relate to matters as to which the action of Edison is subordinate to the authority and order of the Public Utilities Commission. The effect of a provision for the loss of payment it would otherwise receive[7] upon the termination of the agreement, if such termination results from the event described in section 5(e), is to bring pressure to bear upon Edison to cause it to refrain from performing its duties as a public utility to the extent that such performance is affected by its operations
7 It is to be noted that, under section 5, upon the happening of a contingency therein specified and the exercise of its option by Vernon, it is provided that “the leasehold term herein granted shall cease.’ ’ We interpret such cessation to mean that thereby there is brought into being “the end of any additional leasehold term” as such language is used in section 13, if, insofar as section 5 (c) is concerned, no force or effect is to be given to that portion of section 13 which is as follows: “and provided the lease shall not have been sooner terminated in accordance with the provisions of Section 5 hereof. ’ ’
8 In its opinion of October 15, 1957, the Public Utilities Commission said in part: “The Commission has carefully considered the positions taken by the applicant and the City of Vernon. We find as a fact “(a) That the rates charged by applicant to its customers located in the City of Vernon are depressed far below a reasonable level. “(b) That said rates produce an unreasonable and inadequate return to applicant which results in either applicant or its other customers subsidizing the customers of applicant in Vernon. “(c) That there are industries served by applicant which are in competition with industries in Vernon, the former of which industries are required to pay substantially higher rates than similar industries in Vernon; thus creating unreasonable and unlawful prejudice to and discrimination against industries located outside of Vernon and unreasonable and unlawful preference to and discrimination in favor of industries located in Vernon. Furthermore, these depressed rates charged by applicant in the City of Vernon constitute prejudice to and discrimination against customers of applicant outside of but similarly situated and comparable to customers in Vernon, contrary to the public interest. ‘ ‘ (d) That said rates charged by applicant to customers in Vernon constitute an unreasonable and unlawful burden upon the other customers of applicant and, also, upon applicant. ‘ ‘ (e) That for applicant to continue to charge these depressed rates would have a direct tendency to disable applicant in the full performance of its public duty. “(f) That said rates and the unreasonable and unlawful burden which they create are contrary to the public interest and such burden should be removed in order that the public interest be protected.”
Even though Edison did not withhold possession wrongfully as long as Vernon failed to pay the sum due Edison under section 13 of the agreement, it is obvious that the manner of compensating Vernon for the use of its property which governed while the agreement was in full force and effect can no longer be fairly applied under the changed circumstances which resulted in substantially greater revenue to Edison.[9] To permit Edison to use Vernon’s property in the interim without awarding to Vernon the reasonable value of the use and occupation thereof would result in the unjust enrichment of Edison. As said in Major-Blakeney Corp. v. Jenkins, 121 Cal.App.2d 325 , at pages 339-340 [ 263 P.2d 655 ]: “It is fundamental, of course, that the gravamen of a quasi-eontraetual action grounded on unjust enrichment is the equitable principle that a person should not be allowed to enrich himself at the expense of another. (Lazzarevich v. Lazzarevich, 88 Cal.App.2d 708 [ 200 P.2d 49 ]; Miller v. Schloss, 218 N.Y. 400 [ 113 N.E. 337 ]; 17 C.J.S., Contracts, pp. 322-325; Woodward, The Law of Quasi Contracts, p. 9.) It presupposes the acceptance and retention of a benefit by one party with full appreciation of the facts, under circumstances making it inequitable for the benefit to be retained without payment of the reasonable value thereof. (17 C.J.S., Contracts, pp. 332 et seq.) ” The manner in which the trial court made its determination of such reasonable
9 One of the conclusions of law in the present case is: “Equity and good conscience require that Edison pay Vernon the reasonable value of the use and occupation of the leasehold property from and after December 19, 1957 to and including the date of judgment herein.”
The provision embodied in section 27 with respect to attorneys’ fees is one whereby Edison agrees to pay to Vernon reasonable attorneys’ fees to be fixed by the court in the event any judgment is entered in favor of Vernon in “any suit or proceedings” brought to enforce or interpret any of the terms and conditions of the agreement. The present judgment was rendered in an action which falls within the meaning of section 27; the judgment is in favor of Vernon even though the principal relief it sought is granted upon the condition that it pay a substantial sum of money to Edison. (Cf. Exchange Nat. Bank v. Ransom, 52 Cal.App.2d 544 , 546 [ 126 P.2d 620 ].) The award of attorneys’ fees was, accordingly, proper. (See Tibbets v. Robb, 158 Cal.App.2d 330 , 342 [ 322 P.2d 585 ]; Gregers v. Peterson Ice Cream Co., Inc., 158 Cal.App.2d 746 , 755 [ 323 P.2d 572 ].) No contention is made that the amount awarded is unreasonable.
The judgment is affirmed. Each party shall bear its own costs on this appeal.
Vallée, J., concurred.
Shinn, P. J., did not participate.
Cases cited
- Pacific Telephone & Telegraph Co. v. City of Los Angeles 44 Cal.2d 272 at 280 p. 387
- City of Pasadena v. Railroad Commission 183 Cal. 526 p. 387
- Polk v. City of Los Angeles 26 Cal.2d 519 at 539-540 p. 387
- Water Users & Taxpayers Ass'n v. Railroad Commission 188 Cal. 437 at 442-444 p. 388
- Pinney & Boyle Co. v. Los Angeles Gas & Electric Corp. 168 Cal. 12 at 18 p. 388
- Knight v. Black 19 Cal.App. 518 at 522 p. 388
- Sutter Butte Canal Co. v. Railroad Commision 202 Cal. 179 at 187 p. 388
- Sutter Butte Canal Co. v. Railroad Commission 279 U.S. 125 p. 388
- Law v. Railroad Commission 184 Cal. 737 at 739 p. 388, p. 390
- Limoneira Co. v. Railroad Commission 174 Cal. 232 at 238 p. 388
- Gibbs v. Consolidated Gas Co. of Baltimore 130 U.S. 396 at 410 p. 392
- Ebbert v. Mercantile Trust Co. 213 Cal. 496 p. 392
- Gavina v. Smith 25 Cal.2d 501 at 505 p. 393
- Gardner v. Samuels 116 Cal. 84 at 88-89 p. 393
- Major-Blakeney Corp. v. Jenkins 121 Cal.App.2d 325 p. 393
- Lazzarevich v. Lazzarevich 88 Cal.App.2d 708 p. 393
- Miller v. Schloss 218 N.Y. 400 p. 393
- City of San Diego v. Southern California Telephone Corp. 42 Cal.2d 110 p. 394
- County of Los Angeles v. Southern Counties Gas Co. 42 Cal.2d 129 p. 394
- Exchange National Bank of Tulsa v. Ransom 52 Cal.App.2d 544 at 546 p. 394
- Tibbets v. Robb 158 Cal.App.2d 330 at 342 p. 394
- Gregers v. Peterson Ice Cream Co. 158 Cal.App.2d 746 at 755 p. 394