Majority
The defendant Midwood Construction Company, Inc., a corporation, has appealed from a judgment in favor of the plaintiff Gollaher for damages for breach of contract.
The plaintiff, doing business under the name of Gollaher Construction Company, and the defendant entered into an agreement which was dated February 25, 1957. That agreement was embodied in a printed form, with appropriate typewritten insertions in the spaces provided therefor, and in a typewritten page added thereto. In that page it was provided in part as follows:
“Gollaher Construction Company hereinafter known as the subcontractor agrees to supply all carpentry labor and equipment necessary to completely frame the four models for Tract No. 22848 in Northridge, with the following provisions: This contract covers all rough carpentry labor making house ready for plaster and stucco. . . .
7. If it is decided by Midwood Construction Company to award to the Subcontractor Tract No. 22848 consisting of approximately 277 units, Subcontractor hereby agrees to accept this tract at the above mentioned unit prices [$765 per unit] and this agreement with the understanding also that the production schedule will by [be] 10 units a day in sequence, or as called for by Contractor.”
The present action arose out of the refusal of the defendant to permit the plaintiff to do the rough carpentry on units other than the four models. The findings of fact of the trial
1 As will be hereinafter noted, after February 25, 1957, the defendant determined to build 261 houses in Tract No. 22848 rather than 277 units as previously contemplated.
Placing its reliance on the parol evidence rule, the defendant primarily contends that there was no contract with respect to 261 units upon which a recovery by the plaintiff could be based. Succinctly stated, the question presented is whether there is any support in the record for that part of the findings of fact, emphasized above, that after the execution of the agreement of February 25, 1957, “both orally and by numerous acts and by writings, the defendant did exercise its decision to award to plaintiff” the work on the houses other than the four models.
Under paragraph 7 of the typewritten page of the agreement, the defendant was given the privilege or option of having the plaintiff do the framing work on approximately 277 units in Tract Number 22848 for $765 per unit. It is obvious that the defendant could exercise that right only by words spoken or acts done on its behalf after the execution of the contract of February 25, 1957. Evidence of such words or acts was not received for the purpose of varying the terms of the contract or changing the rights of the parties for which provision was made therein, but rather for the purpose of showing the exercise by the defendant of its privilege or option in harmony with the terms of the agreement;
We turn then to the question of the sufficiency of the evidence to sustain the findings that the defendant did in fact exercise its privilege or option under the provisions of paragraph 7 and did thereafter breach its obligation, so assumed, that the plaintiff should be allowed to do the designated work and be paid $765 per unit therefor. “In considering this question, we must follow the rule that we are ‘bound by the decision of the trial court if there is any substantial evidence ’ to support the finding and must accept ‘the full force of the evidence adduced, together with every inference favorable to the prevailing party that may be drawn therefrom, and excluding all evidence in conflict therewith. ’ ” (Talizin v. Oak Creek Biding Club, 176 Cal.App.2d 429 , at p. 434 [ 1 Cal.Rptr. 514 ]; see also Estate of Nidever, 181 Cal.App.2d 367 , 370 [ 5 Cal.Rptr. 343 ].)
With respect to the change in the number of units to be built, Jerome Snyder, president of the defendant Mid-wood Construction Company, Inc., testified in part as follows: “The City notified me on January 17th [1957] that I could develop 277 lots of which 261 were one size and 16 were another size. It was at a later date that we decided that we were not going to build houses on 16 of the lots because they were larger lots. . . . Well, the later date was a business decision that we made and it might have been March or April of ’57.” The four models were constructed “approximately a half to three-quarters of a mile north of the tract.”
2 As clearly stated in Estate of Gaines, 15 Cal.2d 255 , at pages 264-265 [ 100 P.2d 1055 ] : "The parol evidence rule, as is now universally recognized, is not a rule of evidence but is one of substantive law. It does not exclude evidence for any of the reasons ordinarily requiring exclusion, based on the probative value of such evidence or the policy of its admission. The rule as applied to contracts is simply that as a matter of substantive law, a certain act, the act of embodying the complete terms of an agreement in a writing (the ‘integration’), becomes the contract of the parties. The point then is, not how the agreement is to be proved, because as a matter of law the writing is the agreement. Extrinsic evidence is excluded because it cannot serve to prove what the agreement was, this being determined as a matter of law to be the writing itself. The rule comes into operation when there is a single and final memorial of the understanding of the parties. When that takes place, prior and contemporaneous negotiations, oral or written, are excluded; or, as it is sometimes said, the written memorial supersedes these prior or contemporaneous negotiations. [Citations.]”
A document entitled “Addenda to contract dated February 25, 1957” was signed by Mr. Levine; the plaintiff received it in Mr. Levine’s office on April 25, 1957. It was typed by an employee of the defendant. A copy thereof is set forth in the
Mr. Gollaher also testified to a conversation, which occurred “ [approximately April, 1957,” in which Mr. Knott told him that the defendant required that he obtain a performance bond with respect to the 261 units; Mr. Knott recommended a company in Santa Ana and the plaintiff communicated with that company.
On May 7, 1957, the plaintiff received a telegram from the defendant. In that telegram it was said: “In Accordance With Item 7 Addenda to Our Contract on Models for Tract 22848 You Are Hereby Notified of Midwoods Decision Not to Award Contract for Tract 22848 Consisting of Approximately 277 Units to Gallaher [sic] Construction Co.” The next day Mr. Gollaher had a brief conversation with Max Levine in which he expressed his opinion as to the manner in which he had been treated after he had expended time and money 1 ‘ on the preparation of work for the tract. ’ ’
The defendant argues that no agreement with respect to 261 units could properly be found to have been in existence because of certain printed language in the agreement of February 25, 1957. That printed wording (with a typewritten insertion noted by the use of italics) is in part as follows: “Sub-contractor agrees to furnish all materials, labor, equipment, transportation, and to do and perform all
3 "Addenda to Contract Dated February 25,1957 “Draw schedule for Northridge Tract consisting of 261 units will be payable as follows: “20% when sub floors are complete “30% when ceiling joist installed “30% when roof is sheathed “20% after 2nd inspection “Except that there shall be deducted from said payments a sum equal to .05% of same, which .05% shall be withheld until the expiration of the lien period. “April 25,1957 “S/ Midwood Const. “S/ Max Levine ’ ’
The evidence which has been related was clearly sufficient to sustain the determination of the trial court that the defendant exercised its privilege or option expressed in paragraph 7 of the typewritten page of the agreement of February 25, 1957. It thereby bound itself to pay to Mr.
The defendant complains that it cannot be determined from the findings of fact how the trial court arrived at the figure of $703.80 per unit as “the cost to plaintiff.” But the trial court was not required to set forth its computations showing by what method the amount of damages awarded was determined. (Employees' Participating Assn. v. Pine, 91 Cal.App.2d 299 , 303 [ 204 P.2d 965 ].) The pertinent inquiry is whether there was substantial support in the evidence for the finding as to damages.
Where one party to a contract who has agreed to perform certain work in the construction of a building or buildings is, without fault on his part, prevented from doing so by the other party, the primary measure of damages is the amount of his loss, which may consist of his reasonable outlay of expenditures toward performance as well as the profits which he would have made by performance. (O'Connell v. Main & Tenth Streets Hotel Co., 90 Cal. 515 , 520 [ 27 P. 373 ]; Connell v. Higgins, 170 Cal. 541 , 549 [ 150 P. 769 ]; see also Navarro v. Jeffries, 181 Cal.App.2d 454 , 460 [ 5 Cal.Rptr. 435 ]; 9 Cal.Jur.2d, Building Contracts, § 23; Restatement, Contracts, § 346, comment g.) The evidence directed to the determination of such damages in the present case will be summarized.
The plaintiff testified as to his estimate of the costs per unit which would be incurred in doing the work; the total of such costs so estimated was $572.93 per unit. In preparation for the work, he expended the sum of $314.24. Clinton R. Perkins, called as an expert witness on behalf of the plaintiff, expressed an opinion that the actual cost of the work per unit “would run $563.25.” Trent Meredith testified as an expert witness for the defendant; he stated that the custom in Southern California is to add 10 per cent of the cost as anticipated profit; he further testified as follows: “ Q. Bv Mr. Bglash: Referring to bidding on the framing of tracts, the size of the Midwood Tract, 261 houses, would that be the usual percentage, the customary percentage? . . . The Witness: The usual or customary percentage, if the subcontractor wanted the job, I would say, would be between 5 and 6 per cent.” Carl G. Attman, who was called as an expert witness
The weight to be given to the testimony of the various witnesses on the subject of damages and the inferences to be drawn from such evidence were matters within the province of the trial court. It was not necessary that the court’s determination of the cost per unit coincide with a specific figure expressed by a witness in the course of his testimony. (Cf. Employees’ Participating Assn. v. Pine, supra, 91 Cal.App.2d 299 , 303; Stone v. Farnell, 239 E.2d 750, 757.) A review of the evidence shows that the finding of the trial court as to the amount of the plaintiff’s damages was amply justified. This court is not at liberty to interfere with such determination.
Finally, the appellant contends that the trial court erred in failing to make a finding upon the subject of mitigation of damages. In the opening brief of the defendant, it is said: “It was on May 7, 1957, that Midwood sent Gollaher the telegram advising him that he was not awarded the tract. Mr. Gollaher and his entire crew and organization were then released to engage in any work or enterprise that they might desire. The evidence is that Plaintiff did not submit any bids on any work during this period although there was work upon which he could have submitted bids. The result was that during this period he did not work at all.” Attention is called to a part of the plaintiff’s testimony in his deposition which was as follows: “Q. Can you tell me in your opinion how much of your time would have been required to have
In Olds v. Mapes-Reeves Const. Co., 177 Mass. 41 [ 58 N.E. 478 ], an action was brought by subcontractors against the general contractor for breach of a contract under which the plaintiffs were to furnish and set up all the marble work in a building. The court said (58 N.E., at page 479): “But there is this difference between the case of one who is discharged while under a contract to render personal services and a case like the present. In the former case the person discharged, whose personal services come back to him, is bound to dispose of them in a reasonable way, so as to make the damages to the other party not unreasonably large, while, in a case like the present, one deprived of his contract is under no obligation to enter into new contracts with a view to make profits for the other party. In a contract of the kind before the court, personal services are not necessarily included. The labor or supervision may be personally performed by the contractor, or may be furnished through agents or employes. . . . Their agreement was not to render personal services, but only to
4 "It is a general rule that it is the duty of an employee who has been wrongfully discharged before his term of service has expired, to seek other employment, and thus diminish the damages sustained by him.’ ” (Smetherham v. Laundry Workers' Union, 44 Cal.App.2d 131 , at p. 139 [ 111 P.2d 948 ].)
The judgment is affirmed.
Shinn, P. J., and Vallée, J., concurred.
Appellant’s petition for a hearing by the Supreme Court was denied October 11, 1961.
Cases cited
- Talizin v. Oak Creek Riding Club 176 Cal.App.2d 429 p. 645
- Williams v. Binkley 181 Cal.App.2d 367 at 370 p. 645
- Lawrence Block Co. v. Palston 123 Cal.App.2d 300 at 311 p. 648
- Body-Steffner Co. v. Flotill Products, Inc. 63 Cal.App.2d 555 at 561 p. 648
- Burns v. Peters 5 Cal.2d 619 at 623 p. 648
- Continental Casualty Co. v. Phoenix Construction Co. 46 Cal.2d 423 at 431 p. 648
- Monson v. Fischer 118 Cal.App. 503 at 513 p. 648
- Employees' Participating Ass'n v. Pine 91 Cal.App.2d 299 at 303 p. 649, p. 650
- O'Connell v. Main & Tenth Streets Hotel Co. 90 Cal. 515 at 520 p. 649
- Connell v. Higgins 170 Cal. 541 at 549 p. 649
- Navarro v. Jeffries 181 Cal.App.2d 454 at 460 p. 649
- Payne v. Pathe Studios, Inc. 6 Cal.App.2d 136 at 142 p. 651