Majority
Plaintiffs appeal from portions of an adverse judgment entered in an action for declaratory relief brought against a contractor, the surety on his performance bond and certain materialmen and subcontractors who are lien claimants.[1]
Plaintiffs Fred and Nell Culbertson own improved real property in Oakland. On August 12, 1958, they entered into a written “Builder’s Contract” with Cizek under the terms of which Cizek agreed to construct thereon three stores with two apartments above them and to convert an existing beauty shop into two apartments “as Per Plans and Specifications” and to furnish all necessary labor and materials in connection therewith for the sum of $27,500 which plaintiffs agreed to pay. The above contract contained provisions governing alterations, additions and omissions.[2] In compliance with the
1 Prineipal defendants below and sole respondents herein are Prank Cizek, hereafter called Cizek, the contractor, and United Pacific Insurance Company, hereafter called United, the surety on his bond. Cizek as principal and United as surety executed and delivered a so-called ‘‘ contract bond ’ ’ in favor of plaintiffs as owners and the Bank of America National Trust & Savings Association, hereafter called the Bank, as mortgagee. We will generally refer to the other defendants as "lien claimants. ’ ’
2 Paragraph eight thereof provided: “Should the Owner at any time during the progress of the work request in writing any alterations or deviations in, additions to, or omissions from this contract or the plan or specifications, he shall be at liberty to do so, and the same shall in no way affect or make void this contract; but the amount thereof shall be added to or deducted from the amount of the contract price aforesaid, *459 as the ease may he, by a fair and reasonable valuation. And this contract shall be held to be completed when the work is finished in accordance with the original plans, as amended by such changes, whatever may be the nature or extent thereof. ’ ’ Paragraph nine provided: "The rule of practice to be observed in the fulfillment of the last foregoing paragraph (eighth) shall be that the character and valuation of any or all changes, omissions, or extra work shall be agreed upon and fixed in writing, signed by the Owner and the Contractor, prior to execution. ’ ’ Paragraph ten provided in part that any dispute between the parties as to the valuation of extra work, work done or work omitted would be subject to arbitration. This provision was expressly waived by the parties at trial.
Cizek began work about September 3, 1958, and abandoned the job about March 24, 1959. During these seven months plaintiffs requested many additions to the original plans and specifications and made arrangements with Cizek for deviations therefrom. Nevertheless the valuation of these changes and extra work was never agreed upon in writing by the parties as specified by the contract. (See footnote 2, ante.) By March 27, 1959, four progress payments of $5,500 each had been made to Cizek by the Bank. However Cizek owed substantial sums of money to his subcontractors and materialmen who during May and June 1959 filed claims of lien against plaintiffs’ property.
On July 16, 1959, plaintiffs commenced the instant action against Cizek, United and a number of the above lien claimants, alleging the existence of a controversy among all the parties to the action as to their legal rights and duties under the contract and the bond. The core of the dispute as alleged in the complaint is this: Plaintiffs claimed that they owed Cizek $5,500; Cizek claimed that they owed him $19,857.14 of which $15,739.14 was for extras; plaintiffs claimed that the $19,857.14 was for work and materials called for by the contract ; United claimed it was not required by its bond to pay the lien claimants and complete the construction work; and plaintiffs claimed a credit for work not completed by Cizek
Cizek filed an answer admitting that he had executed the builder’s contract but alleging that it had been abandoned by the parties as the result of the numerous alterations and deviations from the plans and specifications. In addition, he filed a cross-complaint seeking recovery of the above sum of $19,857.14 and the foreclosure of his contractor’s lien theretofore filed for such amount. The theory of both the answer and the cross-complaint is that the written contract had been abandoned and therefore did not define the rights of the parties; that the total claims against the property amounted to $43,257.14 which included a reasonable overhead and profit for Cizek in the sum of $2,448.52; and that plaintiff having paid Cizek $23,400, the balance of $19,857.14 was due. As we point out infra, this concept of the reasonable value of the work and materials is echoed in the court’s findings, despite the fact that the court found that the written contract was not abandoned.
United filed a separate answer denying all liability to plaintiffs and asserting, inter alia, that the alteration and modification of the builder’s contract by plaintiffs and Cizek without United’s consent had released the surety from any obligations under the performance bond.[3]
The trial court made copious and detailed findings of fact. So far as is here pertinent the court found: that the “Builder’s Contract” was a valid contract under which the parties thereto intended that there would be changes and additions to work for which a reasonable amount would be paid in addition to the contract price; that after the commencement of the work, some changes, additions and alterations of the
3 A separate action brought by San Francisco Glass Company, defendant lien claimant herein, was ordered consolidated with the instant action for the purposes of trial. Tancready Inc., defendant lien claimant herein, having also filed a separate action, stipulated that it would be bound by the court’s judgment in the instant action. All other lien claimants joined as defendants by plaintiffs filed answers, cross-complaints, and counterclaims. The pretrial conference order stated that the claims of several of the lien claimants had been stipulated to as due and owing. Those claims not disposd of by the stipulation were decided in favor of the claimants, and have since been satisfied by plaintiffs. The validity of the allowance of these claims is not in issue on this appeal, the sole parties and the sole rights to be determined being those of the plaintiffs, Culbertson, and the defendants and cross-complainants Cizek and United.
The court further found: that the unpaid bills of four of the defendant lien claimants amounted to $11,029.54; that the total cost of the work was $42,668.45[4] ; that the reasonable cost of the work was $38,168.45[5] ; and that plaintiffs “should be entitled to a credit or offset from the said total cost of construction in the sum of $4,500.00.” The last “finding” as well as several other related “findings” on which we shall comment are actually conclusions of law. The court found that “it would be inequitable” for either Cizek or plaintiffs to pay the full amount of the $11,029.54 due lien claimants but that $1,359.40[6] thereof should be paid by Cizek and the balance of $9,670.14 ($11,029.54 less $1,359.40) should be paid by plaintiffs.
The court concluded[7] that all of the defendant lien claimants were entitled to a judgment of foreclosure against plaintiffs’ property and a money judgment against Cizek and
4 The finding discloses that this figure is obtained by taking the total of the amount paid Cizek by plaintiffs, the amounts paid subcontractors, materialmen and laborers by plaintiffs, the amount paid such persons by Cizek over what he received from plaintiffs, and the unpaid bills of the four defendant lien claimants in the sum of §11,029.54.
5 The findings do not disclose how the court arrived at the sum of §38,168.45. Remarkably the precise difference between the “total cost” and “reasonable cost” figures is the round figure of $4,500.
6 In related findings this figure is arrived at thus: Cizek paid out $26,540 to various subcontractors, materialmen and laborers (cf. footnote 4, ante) but, receiving only $23,400 from plaintiffs, was found to have “sustained a loss” of $3,140.60. Finding that Cizek “should equitably be liable for the same amount as the credit” of $4,500 allowed plaintiffs, the court then determined Cizek’s additional obligation to be $1,359.40 (§4,500 less $3,140.60).
7 For convenience of treatment we have set forth in substance the court’s conclusions on these matters both as they appear among the findings of fact and as they are set forth under “conclusions of law.” We properly do this since a conclusion of law does not lose its characteristic as such by being placed among the findings of fact. (Estate of Blake (1910) 157 Cal. 448 , 456 [ 108 P. 287 ], overruled on other *462 grounds in Estate of Stanford (1957) 49 Cal.2d 120 , 129 [ 315 P.2d 681 ] ; Lenchner v. Chase (1950) 98 Cal.App.2d 794 , 802 [ 220 P.2d 921 ]; Jon-Mar Co. v. City of Anaheim (1962) 201 Cal.App.2d 832 , 840 [ 20 Cal.Rptr. 350 ].)
We are presented here with two basic questions: First, did the trial court make a proper determination of the rights and duties of plaintiffs and Cizek in the light of the written contract entered into by such parties 1 Secondly, did the court make a proper determination of United's liability in the light of the contract bond furnished by it as surety ?
Before we reach the merits of the first question, some preliminary matters require our attention. An action brought under section 1060 of the Code of Civil Procedure for declaratory relief is an equitable proceeding and the powers of a court thus invoked are as broad and as extensive as those exercised by such court in any ordinary suit in equity. (Adams v. Cook (1940) 15 Cal.2d 352 , 362 [ 101 P.2d 484 ] ; City of Los Angeles v. City of Glendale (1943) 23 Cal.2d 68 , 81 [ 142 P.2d 289 ] ; Rolapp v. Federal Building & Loan Assn. (1936) 11 Cal.App.2d 337 , 342 [ 53 P.2d 974 ] ; Ho Gate Wah v. Fong Wan (1953) 118 Cal.App.2d 159 , 165 [ 257 P.2d 674 ].) While the court in a declaratory relief action may properly determine questions as to rights and duties arising out of an existing contract (Foster v. Masters Pontiac Co. (1958) 158 Cal.App.2d 481 , 486 [ 322 P.2d 592 ]; see 15 Cal.Jur.2d, Declaratory Relief, § 71, pp. 225-230), it may not make a new contract for the parties or, in lieu of construing an existing contract, incorporate new obligations into it. (Lyon v. Goss (1942) 19 Cal.2d 659 , 673-674 [ 123 P.2d 11 ].) Its duty is to provide for a determination
8 As we discuss infra, the court’s denial of recovery to Cizek rests on findings that he was not a duly licensed contractor and that the work done by him was of the type described as general contracting which required a license.
With these principles in mind we turn to the findings. As stated above the court found that the builder’s contract was valid and in effect. The contract therefore defined the rights and duties of the parties and among other things determined the amount to which Cizek was entitled for the construction work. The basic price was $27,500. Under the provisions of the contract (see footnote 2, ante) the amount of alterations, additions or omissions to or from the contract, plans or specifications “shall be added to or deducted from the amount of the contract price aforesaid, as the case may be. bv a fair and reasonable valuation. ’ ’
Our inquiry then narrows to whether or not the trial court determined plaintiffs’ liability for the construction work in accordance with the terms of the contract. Prom our examination of the findings and conclusions, we are convinced that it did not. Essentially, the court based its determination of plaintiffs’ liability on the total cost of the work ($42,668.45). It made a $4,500 adjustment of this figure,[9]
9 The conclusion of law, placed among the findings, that plaintiffs are entitled to such §4,500 as a credit or offset, does not disclose how the *464 court arrived at the adjustment or just exactly what it represents. The record discloses that at the time of the announcement of its decision, the court stated to counsel that it would make an allowance of 10 per cent of the total cost in favor of plaintiffs. The resulting figure of $4,290.21 (based on a total cost of $42,902.15) appears to approximate the final allowance of $4,500.
The court made no finding as to the reasonable value of the extras or as to the reasonable value (net plus or minus) of all changes and deviations. This was a material issue raised by the pleadings[10] and set forth by the pretrial conference order as remaining in dispute.[11] Instead the court made a finding as to the reasonable value of the total cost of construction. This finding was immaterial and necessarily inadequate as a finding of the reasonable value of extras. It is settled that “findings are required on all material issues raised by the pleadings and evidence, unless they are waived, and if the court renders judgment without making findings on all material issues, the ease must be reversed.” (James v. Haley (1931) 212 Cal. 142 , 147 [ 297 P. 920 ]; see also De Burgh v. De Burgh (1952) 39 Cal.2d 858 , 873 [ 250 P.2d 598 ] ; Edgar v. Hitch (1956) 46 Cal.2d 309 , 312 [ 294 P.2d 3 ]; Bertone v. City & County of San Francisco (1952)
10 See summary of allegations of complaint, supra.
11 The court adopted plaintiffs’ pretrial statement as part of its pretrial conference order. Such statement contains the following: "Issues : The issues raised by the pleadings are the rights and duties of the plaintiffs under their contract with Oizek, the liability of United Pacific Insurance Company under its performance bond, and whether or not, or the extent to which the lien claims of the subcontractors constitute work under the general contract, or extras, for which the plaintiffs are liable. ’ ’
United argues that the effect of the findings of the trial court is that plaintiffs “will wind up” paying the contract price of $27,500 plus $15,168.45 for changes, additions and extras[12] and that the findings considered as a whole cover all material issues.
The general tenor of this argument is that although the court made no express findings as to the reasonable value of the changes and deviations, the amount due from plaintiffs on the contract and the amounts due for changes and deviations, all of these facts can be reasonably implied from the findings which the court did make. As the court said in Richter v. Walker (1951) 36 Cal.2d 634 , 640 [ 226 P.2d 593 ] : “ [W]hile full findings are required upon all material issues a judgment will not be set aside on appeal because of a failure to make an express finding upon an issue if a finding thereon, consistent with the judgment, results by necessary implication from the express findings which are made.” (See also Greenberg v. Hastie (1962) 202 Cal.App.2d 159 , 173 [ 20 Cal.Rptr. 747 ].)
However the above rule set forth in Richter, supra, is not operative where the appealing party made a written request in the trial court for a specific finding on the issue in controversy. (Code Civ. Proc., § 634; City of National City v. California Water & Telphone Co. (1962) 204 Cal.App.2d 540 , 545 [ 22 Cal.Rptr. 560 ]; Ruppert v. Jackson (1963) 212 Cal.App.2d 678 , 682-683 [ 28 Cal.Rptr. 467 ].) In the instant case, plaintiffs filed detailed objections to the findings of fact and conclusions of law prepared by counsel for Cizek[13] in
12 TJnited states in its brief: "The effect of the findings of the trial court is that appellants will wind up paying the contract price of $37,500.00 plus $15,168.45 for changes, additions and extras (which is the difference between the total actual cost of $42,668.45 and the contract price of $27,500.00), less $4,500.00 for omissions, deletions and inferior workmanship, or a total of $38,168.45 (the reasonable cost or value of the improvements after all allowances are considered), for an improvement that actually cost $42,668.45. The $4,500.00 loss will be absorbed by respondent Cizek.”
13 Plaintiffs ’ motion to augment the record on appeal by including therein findings of fact and conclusions of law submitted by them on July 27, 1961, and objections filed February 22, 1962, to findings of fact and conclusions of law submitted by Cizek on February 19, 1962, after the court’s announcement on January 18, 1962, of its intended decision, was submitted at the time of the argument of this cause on its merits. We have granted plaintiffs ’ motion.
We turn to examine the court’s determination of United's liability under the contract bond. We will thereafter discuss the relationship of this issue to other issues before us and to our disposition of the appeal.
The bond is executed by Cizek as principal and United as surety in the sum of $27,500 and runs in favor of plaintiffs and the Bank. It refers to the builder’s contract between plaintiffs and Cizek “a copy of which is or may be hereto annexed” and provides in substance that the condition of the bond is that Cizek shall faithfully perform the work contracted for and shall pay or cause to be paid in full, the
14 Plaintiffs requested that the court find: that the contract price was 627,500; the extras ordered by plaintiffs were $3,764.10; the total contract price and extras were $31,264.16; the work not furnished by Cizek was $2,644.29; the work improperly done involved costs of repair in the sum of $1,019; and that the work called for in the contract but paid for by plaintiffs totalled $1,186,
The bond thus incorporated by reference the builder’s contract “and thereby all of the provisions of the contract became provisions of the bond as a performance bond. ’ ’ (C.O. Sparks, Inc. v. Pacific Coast Paving Co. (1958) 159 Cal.App.2d 513 , 517 [ 324 P.2d 293 ] ; W. P. Fuller & Co. v. Alturas School Dist. (1915) 28 Cal.App. 609 , 612-613 [ 153 P. 743 ] ; Sunset Lumber Co. v. Smith (1928) 91 Cal.App. 746 , 751 [ 267 P. 738 ].) “A bond which is given for the faithful performance of a contract, to which it refers, binds the surety for labor performed and materials furnished thereunder as completely as though the surety were a party to the contract. [Citations.]” (Pacific States Elec. Co. v. United States Fidelity & Guar. Co. (1930) 109 Cal.App. 691 , 693-694 [ 293 P. 812 ]; C.O. Sparks, Inc. v. Pacific Coast Paving Co., supra.) The court found that neither the contract nor the bond was filed in the office of the county recorder. Failure to file the contract did not render the contract wholly void but had the effect of making the owners’ property liable to the lien claimants for the full reasonable value of the labor done or material furnished rather than limiting such liability to the amount due from the owners to the contractor. (Code Civ. Proc., § 1185.1; Bird v. American Surety Co. (1917) 175 Cal. 625 , 629 [ 166 P. 1009 ], decided under former Code Civ. Proc., § 1183. )[15] Likewise, failure to so file the bond did not render the bond void or add to the burden of the surety. The bond itself does not provide that filing with the recorder is a prerequisite to its validity, United does not here so contend, and in any event, the bond is valid as a common-law bond for the benefit of all persons named therein as beneficiaries. (Hammond Lumber Co. v. Willis (1915) 171 Cal. 565 , 568 [ 153 P. 947 ];
15 The lien of a general contractor would of course be limited to the agreed contract price. (Code Civ. Proc., § 1185.1, subd. (a).)
Prom the foregoing we reach the following conclusions : First, it was the obligation of Cizek and United to pay the lien claimants in full. Secondly, upon not being paid, the lien claimants were entitled to two remedies: (a) to proceed against plaintiffs’ property for the full amount of their liens (the contract and bond not having been filed) and (b) to proceed to obtain a separate personal judgment in such mechanics’ lien action against Cizek and United as the persons personally liable for their respective debts notwithstanding the lien. The right to foreclose the lien is not the exclusive remedy; the two remedies are cumulative and may be pursued simultaneously so long as any money collected on the personal judgment is credited on the amount of the lien. (Code Civ. Proc., § 1200; Faucett v. Riveroll (1928) 203 Cal. 438 , 440 [ 264 P. 1098 ] ; Dodd v. Mattox, supra, 72 Cal.App. 705 , 709; Wm. J. Bettingen Lumber Co. v. Kerrin (1929) 99 Cal.App. 686 , 689-690 [ 279 P. 163 ]; Withington v. Shay (1941) 47 Cal.App.2d 68 , 77 [ 117 P.2d 415 , 119 P.2d 1 ]; Adolph v. Municipal Court (1960) 181 Cal.App.2d 198 , 200 [ 5 Cal.Rptr. 212 ].)[16]
The trial court however, while rendering a personal judgment in favor of the lien claimants and against both Cizek and United for the full amount of the unpaid claims and also rendering a judgment of foreclosure against plaintiffs’ property, further directed that the judgment in favor of the lien claimants be satisfied first from a foreclosure of plaintiffs’ property and only if it were not thereby fully satisfied, then to proceed further against Cizek and United.[17] We have concluded that the court erred in issuing the above directive. Since the remedies of the lien claimants were
16 Under Code Civ. Proc., § 1200, lien claimants are also entitled to maintain a separate action to obtain such personal judgment. (Homestead Savings & Loan Assn. v. Superior Court (1961) 195 Cal.App.2d 697 , 701 [ 16 Cal.Rptr. 121 ].)
17 Paragraph 7 of the judgment in pertinent part provides: "... and said defendants are directed to proceed in execution, first against the said real property by such foreclosure proceedings and to receive therefrom, a total not to exceed $9,670.14, plus the interest thereon. ’ ’ Paragraph 9 thereof provides: "That should said real property fail to produce the sum as above set forth upon foreclosure sale, then said defendant lien claimants shall recover said deficiency from defendants Prank Cizek and United Pacific Insurance Company.” The above portions of the judgment conformed to the conclusions of law.
This brings us to defendant United’s contention that plaintiffs have not been prejudiced by the errors on which they rely because the trial court committed error in finding: (1) that the alterations, additions and modifications of and to the written contract, plans and specifications were not material and substantial; (2) that the written contract had not been abandoned and United was liable on its contract bond; and (3) that Cizek was not at all times material to the case a duly licensed general contractor. It is to be noted that neither Cizek nor United has appealed from the judgment or any part thereof. Paying lip service to the general rule that a respondent who does not appeal cannot attack error, United nevertheless invokes section 956 of the Code of Civil Procedure.[18] We find no merit in United’s argument.
18 Code Civ. Proc., § 956, provides: "Upon an appeal from a judgment the court may review the verdict or decision, and any intermediate ruling, proceeding, order or decision which involves the merits or necessarily affects the judgment, or which substantially affects the rights of a party. The court may also on such appeal review any order on motion for a new trial. The respondent, or party in whose favor the judgment was given, may, without appealing from such judgment, request the court to and it may review any of the foregoing matters for the purpose of determining whether or not the appellant was prejudiced by the error *470 or errors upon which he relies for reversal or modification of the judgment from which the appeal is talcen. Tlie provisions of this section do not authorize the court to review any decision or order from which an appeal might have been taken.” (Italics added.) The portion in italics, was added to the section in 1957.
As to the third finding complained of, the court found that Cizek was not duly licensed, that this was not known to any of the parties, except Cizek, until the commencement of the instant action, that the work done by Cizek was general contracting, thus requiring that he be duly licensed as a general contractor. It will be recalled that Cizek had filed his own lien against plaintiffs’ property and by cross-complaint sought not only recovery of $19,857.1.4 from plaintiffs but also foreclosure of his lien. The court concluded that Cizek should recover nothing from plaintiffs and entered judgment accordingly. Neither Cizek nor TTnited appealed from the judgment. Thus the foregoing matters pertaining to
Finally United contends that if the judgment is reversed at all, it should be reversed in its entirety. While recognizing the rule that a judgment becomes final as against a nonappealing party despite its reversal on the appeal of other parties, United cites Blache v. Blache (1951) 37 Cal.2d 531 , 538 [ 233 P.2d 547 ] for the proposition that “this rule is not applied where portions of a judgment adverse to a nonappealing party are so interwoven with the whole that appeal from a part affects the other parts; in such a situation the appellate court can reverse the entire judgment if it is necessary to do justice. ’ ’
The applicable rules are fully set forth in the leading ease of American Enterprise, Inc. v. Van Winkle (1952) 39 Cal.2d 210 , 216-217 [ 246 P.2d 935 ] : “The well recognized rule is that there may be an appeal from a part of a judgment only if that part is severable. [Citations.] Where portions of a judgment are truly severable, the appellate court is without jurisdiction to consider the parts from which no appeal has been taken. [Citations.] And the appellate court will consider the portion before it independently of the other parts- [Citations.] Modification or reversal of the portion of the judgment from which the appeal has been taken has no effect upon the other portions. [Citations.]
“The test of whether a portion of a judgment appealed from is so interwoven with its other provisions as to preclude an independent examination of the part challenged by the appellant is whether the matters or issues embraced therein are the same as, or interdependent upon, the matters or
We proceed to apply the above rules to the judgment in the instant case. Plaintiffs have appealed only “from the provisions of sections numbered 1, 7, 8, 9, 10, 11, 12, 13 and 15 of the Judgment . . . .” Paragraph (i.e., section) 1 provides that plaintiffs recover nothing from Cizek. Paragraphs 7 through 13 deal with the foreclosure of the mechanics ’ liens, the directions that resort first be had to plaintiffs’ property, the resort secondarily to Cizek and United, and the application of the proceeds of any foreclosure sale, all of which we have discussed supra. (See also footnote 17, ante.) Paragraph 15 provides for United’s right of recovery against plaintiffs and Cizek.[20] In toto the foregoing provisions encompass the area of controversy discussed by us above.
The remaining portions of the judgment not appealed from are paragraphs 2, 3, 4, 5, 6 and 14. Paragraph 2, already mentioned, provides that Cizek recover nothing from plaintiffs. Under normal circumstances, the provisions of paragraph 2 would appear to be closely interwoven with those of paragraph 1 (that plaintiffs recover nothing from Cizek) since whether either party may recover from the other depends upon a determination of their rights and liabilities according to the terms of the builder’s contract entered into between them and found by the court to be valid and not abandoned. However paragraph 2 of the judgment as well as
19 American cites a number of authorities including Blache.
20 Paragraph 15 provides: “That said defendant United Pacific Insurance Company shall have a right of recovery for any sums it pays to the defendant lien claimants hereinabove named and said right of recovery shall be against the plaintiffs for all sums in excess of $1,359.40 and interest thereon and costs of suit, and shall be against defendant Prank Cizek for all sums it pays to the said defendant lien claimants pursuant to the orders contained herein for their recovery. ' ’
21 In Steinwinter, for example, plaintiffs who were unlicensed contractors sued the owners who cross-complained for damages for breach because of allegedly defective work. The contractors answered the cross complaint by a general denial and an affirmative defense of money due them under the contract. The trial court granted defendants’ motion for summary judgment on the complaint based on Bus. & Prof. Code, § 7031. After a trial on the issues raised by the cross-complaint, the trial court concluded that the owners were entitled to recover thereon the sum of $4,136.65 but found there was a balance due the contractors of $4,751.09 and allowed the contractors an equitable offset in that amount against the recovery allowed the owners. However the court further ruled that since the offset exceeded the owners’ recovery, no monetary judgment could be rendered and gave the owners judgment for their costs.
Paragraphs 3 through 6 of the judgment grant recovery to the various lien claimants against Cizek and United. Clearly these parts of the judgment are not so interwoven with the parts appealed from as to preclude an independent review of the latter. A redetermination of the obligations between plaintiffs and Cizek does not affect the obligations of Cizek and United to these third-party lien claimants. Indeed on this appeal the parties appear to agree that such latter obligation exists in the amount set forth in the judgment. (See also footnote 3, ante.) In the same way, paragraph 14 allowing United attorneys’ fees and costs against Cizek is not affected by those parts of the judgment appealed from.
We conclude therefore, contrary to United’s contention, that we need not reverse the judgment in its entirety. The judgment nevertheless must be reversed as to those portions appealed from because the findings of fact relating thereto are inadequate, because findings on material issues relating thereto have not been made, and because the court did not correctly determine the rights and obligations of the parties before us according to the contract and bond. On remand, the trial court should determine, inter alia, the following: the amount, if any, due Cizek from plaintiffs based on the contract price of $27,500 and allowing for the addition and deduction, as the case may be, of any alterations or deviations in, additions to, or omissions from the contract, plans or specifications; and the amount, if any, due plaintiffs from Cizek for any unworkmanlike performance or other breach of contract on Cizek’s part. As explained supra, the court should allow Cizek an equitable offset for the amount, if any, due him from plaintiffs against any amounts found to be due plaintiffs from him but only to the extent of such latter amounts and not in excess thereof.
As we have explained, those portions of the judgment granting recovery to the lien claimants should permit them to pursue their remedies provided by law without any restrictions thereon. In the event of a judgment in favor of plaintiffs, such judgment in the light of the contract and bond must be given against both Cizek and United.
Except for the reception of evidence on the matter of liens paid after judgment, we find nothing in the record which impels us to order a new trial. The case was fully tried and, with the exception noted, there is no necessity to take further evidence. Under the circumstance it is appropriate to remand the cause -with directions to the trial court to make adequate findings on all issues involved, based on the evidence now before it, and in conformity with the views herein expressed; to draw proper conclusions of law therefrom; and to enter judgment accordingly. (4 Cal.Jur.2d, Appeal and Error, § 670, pp. 561-562.)
It is ordered, therefore, that the judgment be reversed as to those portions thereof appealed from and that the cause be remanded with directions to the trial court to set aside such portions of the judgment and those findings of fact and conclusions of law pertinent thereto; to receive evidence, if any, on the limited issue of liens paid after judgment; and thereupon, having reexamined and redetermined all issues relating to the portions of the judgment appealed from in conformity with the views herein expressed (but without redetermining those issues relating to the portions of the judgment not appealed from), to make and file findings of fact thereon based upon the evidence now before it; to draw proper eon
The judgment is reversed as to those portions thereof appealed from and the cause is remanded to the trial court to proceed with the disposition thereof under the directions and in conformity with the views herein expressed. Appellants shall recover costs on appeal.
Bray, P. J., and Molinari, J., concurred
Cases cited
- Adams v. Cook 15 Cal.2d 352 at 362 p. 462
- City of Los Angeles v. City of Glendale 23 Cal.2d 68 at 81 p. 462
- Rolapp v. Federal Building & Loan Ass'n 11 Cal.App.2d 337 at 342 p. 462
- Ho Gate Wah v. Fong Wan 118 Cal.App.2d 159 at 165 p. 462
- Foster v. Masters Pontiac Co. 158 Cal.App.2d 481 at 486 p. 462
- Lyon v. Goss 19 Cal.2d 659 at 673-674 p. 462
- Putnam v. Putnam 51 Cal.App.2d 696 at 699 p. 463
- Flynn v. Flynn 103 Cal.App.2d 91 at 96 p. 463
- Taliaferro v. Taliaferro 125 Cal.App.2d 419 at 427 p. 463
- Floyd v. Davis 98 Cal. 591 at 601 p. 463
- Boyce v. Fisk 110 Cal. 107 at 112 p. 463
- James v. Haley 212 Cal. 142 at 147 p. 464
- De Burgh v. De Burgh 39 Cal.2d 858 at 873 p. 464
- Edgar v. Hitch 46 Cal.2d 309 at 312 p. 464
- Bertone v. City & County of San Francisco 111 Cal.App.2d 579 at 586 p. 465
- Keroff v. Snyder 208 Cal.App.2d 429 at 432 p. 465
- Richter v. Walker 36 Cal.2d 634 at 640 p. 465
- Greenberg v. Hastie 202 Cal.App.2d 159 at 173 p. 465
- City of National City v. California Water & Telephone Co. 204 Cal.App.2d 540 at 545 p. 465
- Ruppert v. Jackson 212 Cal.App.2d 678 at 682-683 p. 465
- Calloway v. Downie 195 Cal.App.2d 348 at 352-353 p. 466
- C. O. Sparks, Inc. v. Pacific Coast Paving Co. 159 Cal.App.2d 513 at 517 p. 467
- W. P. Fuller & Co. v. Alturas School District 28 Cal.App. 609 at 612-613 p. 467
- Sunset Lumber Co. v. Smith 91 Cal.App. 746 at 751 p. 467
- Pacific States Electric Co. v. United States Fidelity & Guaranty Co. 109 Cal.App. 691 at 693-694 p. 467
- Bird v. American Surety Co. of New York 175 Cal. 625 at 629 p. 467
- Hammond Lumber Co. v. Willis 171 Cal. 565 at 568 p. 467
- Dodd v. Maddox 72 Cal.App. 705 at 709 p. 468
- Faucett v. Riveroll 203 Cal. 438 at 440 p. 468
- Wm. J. Bettingen Lumber Co. v. Kerrin 99 Cal.App. 686 at 689-690 p. 468
- Withington v. Shay 47 Cal.App.2d 68 at 77 p. 468
- Adolph v. Municipal Court 181 Cal.App.2d 198 at 200 p. 468
- Crawford v. Southern Pacific Co. 3 Cal.2d 427 at 429 p. 470
- Central Manufacturing District, Inc. v. Board of Supervisors 176 Cal.App.2d 850 at 857 p. 471
- Blache v. Blache 37 Cal.2d 531 at 538 p. 471
- American Enterprise, Inc. v. Van Winkle 39 Cal.2d 210 at 216-217, at 217, at 219 p. 471, p. 474, p. 475
- Loving & Evans v. Blick 33 Cal.2d 603 at 609 p. 473
- Grant v. Weatherholt 123 Cal.App.2d 34 at 41-42 p. 473
- Bierman v. Hagstrom Construction Co. 176 Cal.App.2d 771 at 775-777 p. 473
- Gore v. Witt 149 Cal.App.2d 681 at 686 p. 473
- Marshall v. Von Zumwalt 120 Cal.App.2d 807 at 809-810 p. 473
- Steinwinter v. Maxwell 183 Cal.App.2d 34 at 38 p. 473
- Lewis & Queen v. N. M. Ball Sons 48 Cal.2d 141 at 150 p. 474
- Blum v. City & County of San Francisco 200 Cal.App.2d 639 at 648 p. 474
- Stone v. Serimian 198 Cal. 520 at 523-524 p. 475