Majority
The plaintiff, a corporation, was the owner of a tract of land; entered into a contract, allegedly with all of the defendants, viz., Carrico Construction Co., a corporation, George Lee Carrico, Lloyd Frimmersdorf, and Lloyd Frimmersdorf & Associates, dba Carrico Construction Co., a California corporation, for the subdivision and improvement thereof; and brought this action to recover damages for a failure to perform. The contract, which is dated December 7, 1960, recites that it is entered into between the plaintiff, as owner, and “Lloyd Frimmersdorf & Associates dba Carrico Construction Co., a California corporation" as “Contractor"; on behalf of the plaintiff is signed by its corporate officers; and, apparently on behalf of the “Contractor" is signed:
“Lloyd Frimmersdorf & Associates
“By(s) Lloyd Frimmersdorf."
The court found, among other things, that (1) all of the defendants entered into the contract; (2) that the defendant “Carrico Construction Co., a corporation, was a party to the written contract dated December 7, 1960 entered into on its behalf by its President, Lloyd Frimmersdorf”; (3) that all of the defendants failed to perform any of the terms required of them under the contract, and although, with the exception of the defendant George Lee Carrico, they went through the motions of commencing performance, they did not actually perform, and conferred no benefits upon the plaintiff; (4) that pursuant to the terms of the contract the plaintiff paid the defendants the sum of $1,100; (5) that the reasonable cost of obtaining performance, by another contractor, of the work agreed to be performed by the defendants would exceed the contract price by $6,500; and (6) that the defendant Lloyd Frimmersdorf was the alter ego of the “defendants Carrico Construction Co., a California corporation and Lloyd Frimmersdorf & Associates dba Carrico Construction Co., a California corporation, Avhich are solely owned, controlled and dominated by said” defendant, and it would be unjust to the plaintiff “if said corporate entities were to be recognized by this court.” Judgment in the sum of $7,600 was entered in favor of the plaintiff against all of the defendants except George Lee Carrico. All of the defendants, except Carrico, have appealed.
Among other contentions, the defendants claim that the subject contract lacks mutuality; that the promises of the plaintiff were unenforcible because only the construction corporation held a contractor’s license; that the respective promises of the parties to the contract, therefore, did not impose mutual obligations; and consequently, there was a want of consideration for the defendants’ promises. This contention is premised on the rule that in a contract where the consideration therefor consists of mutual promises, and the promise of one party is not enforeible, the obligations imposed thereby are not mutual, and a want of consideration exists. (Mattei v. Hopper, 51 Cal.2d 119 , 122 [ 330 P.2d 625 ];)
In a general way, the defendants urge the illegality of the subject contract; allege in their answer that only the construction company was a licensed contractor; and assert the illegality of a construction contract in which a licensed contractor joins with one or more nonlicensed contractors to do construction work for another. The trial court found that all four of the defendants jointly agreed to do the construction work specified in the subject contract. The undisputed evidence establishes that only the construction company had a contractor’s license. Under these circumstances, the contract was unenforcible by the contractor, and was of the type declared by the courts to be illegal. (Bus. & Prof. Code, §§ 7028, 7028.5, 7029, 7031; Lewis & Queen v. N. M. Ball Sons, 48 Cal.2d 141 , 149 [ 308 P.2d 713 ]; Loving & Evans v. Blick, 33 Cal.2d 603 , 607 [ 204 P.2d 23 ].) In response to the charge of illegality, the plaintiff relies upon the principle of law permitting a party to such a contract not in pari delicto with the contractor to maintain an action against the latter; directs attention to the rule that a member of the class for whose protection the contractors' licensing laws were enacted generally is not in pari delicto with the contractor; and contends that, because it is a member of this class, the illegality of the instant contract did not foreclose the instant action, citing Lewis & Queen v. N. M. Ball Sons, supra, 48 Cal.2d 141 , 153. (See also Carter v. Seaboard Finance Co., 33 Cal.2d 564 , 574 [ 203 P.2d 758 ].) The uncontradicted evidence in the ease at bar brings it within the rule applied in Dias v. Houston, 154 Cal.App.2d 279 , 281
In the trial court, as disclosed by the joint pretrial statement and the pretrial order, the defense of the defendant construction company was that it did not execute the subject contract and was not a party thereto. The defense of the defendant Lloyd Frimmersdorf, “an individual, or as doing business under a fictitious name” was that he had been prevented from performing the contract by the plaintiff, and that no damages resulted from the “Defendants” not completing the contract.
The contentions now made by the appealing defendants, other than as heretofore noted, fall within the two general defenses categorically outlined in their pretrial statement.
At this juncture it should be noticed that nowhere in the record is the status of the defendant sued under the name of “Lloyd Frimmersdorf & Associates dba Carrico Construction Co., a California corporation,” alleged, discussed, or found, except as appears from the foregoing pretrial statement.
The answer of the defendant “Lloyd Frimmersdorf and Lloyd Frimmersdorf & Associates, doing business as Carrico Construction Company, a California corporation,” alleges that “these answering defendants” entered into the subject contract. Our determination of the issues on appeal must take into consideration the foregoing admission.
The defendant construction company contends that it did not execute the contract and, therefore, is not liable thereunder. In support of this position it applies the theory of lack of mutuality, viz., the contract not having been executed by it could not be enforced by it, and, therefore, should not be enforced against it. Regardless of the theory thus expressed, the issue for determination is whether the evidence supports the finding of the court that the construction company executed the contract. The recital therein identifying the “Contractor” as “Lloyd Frimmersdorf & Associates dba Carrico Construction Co., a California Corporation,” was ambiguous in that it could refer to an association of people doing business under a fictitious corporate name, or to people acting for and through an actually existent corporation, or to both an association of people under the name of Lloyd Frimmersdorf & Associates and a corporation named Carrico Construction Co. Because of this ambiguity,
In view of the foregoing determination and the admission in the answer of the defendants Lloyd Frimmersdorf and Lloyd Frimmersdorf & Associates, the finding that all of the defendants executed the subject contract must be sustained.
All of the appealing defendants attack the finding that Frimmersdorf was the alter ego of the defendant construction company. As pointed out by them, this finding does not purport to establish that the construction company was the alter ego of Frimmersdorf. Our attention is not directed to the materiality of the questioned finding and for this reason we need give it no further consideration.
The appealing defendants further claim that they were prevented from completing the contract and, therefore, are not chargeable with any breach thereof. This contention cen
The finding on the issue of damages is attacked upon the ground that it is not sustained by the evidence. The argument in support of this contention goes to the weight of the evidence rather than its sufficiency. By the contract the plaintiff agreed to pay the defendants $21,000 for the work to be performed by the latter. The plaintiff’s president testified that the reasonable cost of performing this work at the time of trial was $27,500. There was evidence in refutation of this testimony. However, the determination of the conflict thus produced was a function committed exclusively to the trial court. (Shields v. Shields, 200 Cal.App.2d 99 , 102 [ 19 Cal.Rptr. 129 ].)[1] The measure of damages applied by the court on account of the defendants’ failure to perform was the difference between the aforesaid amounts, viz., the contract price and the price of completing the work the defendants had agreed to perform. This was proper. (Wallace v. Ah Sam, 71 Cal. 197 , 201 [ 12 P. 46 , 60 Am.Rep. 534 ]; Allen v. Gardner, 126 Cal.App.2d 335 , 342 [ 272 P.2d 99 ].) Although' the defendants inferentially contend to the contrary, the plaintiff was entitled to recover damages from them for their breach of the contract even though it had not
1 There was evidence that the plaintiff had received bids for the work in question, made at the time the contract was executed, that were lower in amount than the contract price. However, this evidence, which was produced by interrogatories propounded to the plaintiff, at the most produced a conflict and contrary to the defendants’ contention, the court was not required to accept it as determinative of the issue at hand.
The defendants also contend that the court erred in accepting the stated contract price of $21,000 as the true contract price, because there was no evidence establishing the value of the lot to be given in part payment. No authority is cited in support of this position. The parties to the contract agreed that the consideration payable to the defendants was $21,000, and the court was entitled to accept this agreement as a premise for its award. The fact that the parties further agreed that payment of a part of this amount should be in kind rather than in money did not require rejection of their agreement that the consideration to be paid was in the amount agreed upon by them. The further fact that a part of the contract price was to be paid in installments, upon the sales of lots, was not a factor minimizing the damage sustained by the plaintiff because of the defendants’ breach.
The additional contention of the defendants that the findings do not set forth the terms of the contract is frivolously technical and wholly without merit.
The judgment is affirmed.
Griffin, P. J., and Brown (Gerald), J., concurred.
Cases cited
- Mattei v. Hopper 51 Cal.2d 119 at 122 p. 67
- Lawrence Block Co. v. Palston 123 Cal.App.2d 300 at 308 p. 68
- Shortell v. Evans-Ferguson Corp. 98 Cal.App. 650 at 659-660 p. 68
- Hamlin v. Barnhart 26 Cal.App. 632 at 633 p. 68
- Black Light Corp. v. Ultra-Violet Products, Inc. 195 Cal.App.2d 473 at 478 p. 68
- Arrow Flying Service, Inc. v. Universal Flyers Ground School 99 Cal.App.2d 49 at 51 p. 68
- Kruce v. Parlier Winery 208 Cal. 723 at 725 p. 68
- Pastene v. Pardini 135 Cal. 431 at 433 p. 68
- Lewis & Queen v. N. M. Ball Sons 48 Cal.2d 141 at 149, at 153 p. 68
- Loving & Evans v. Blick 33 Cal.2d 603 at 607 p. 68
- Carter v. Seaboard Finance Co. 33 Cal.2d 564 at 574 p. 68
- Dias v. Houston 154 Cal.App.2d 279 at 281 p. 68
- Vitagraph, Inc. v. Liberty Theatres Co. 197 Cal. 694 at 696 p. 70
- Minton v. Mitchell 89 Cal.App. 361 at 370 p. 70
- Richter v. Walker 36 Cal.2d 634 at 640 p. 70
- Main Street & Agricultural Park Railroad v. Los Angeles Traction Co. 129 Cal. 301 at 305 p. 71
- Marinovich v. Kilburn 153 Cal. 638 at 642 p. 71
- Bailey v. Breetwor 206 Cal.App.2d 287 at 291-292 p. 71
- Shields v. Shields 200 Cal.App.2d 99 at 102 p. 72
- Wallace v. Ah Sam 71 Cal. 197 at 201 p. 72
- Allen v. Gardner 126 Cal.App.2d 335 at 342 p. 72
- County of Los Angeles v. Margulis 6 Cal.App.2d 57 at 60 p. 73