Majority
The San Bernardino County Flood Control District (Flood Control District) seeks a writ of prohibition to restrain respondent superior court from exercising jurisdiction over an eminent domain action brought by the East San Bernardino County Water District (Water District) to condemn a “non-exclusive easement” in the beds and banks of certain watercourses and flood control channels which are presently owned by the Flood Control District and appropriated to flood control purposes. In the court below the Flood Control District, by demurrer and motions for summary judgment and for dismissal unsuccessfully challenged the power of the Water District to maintain the action.
The events giving rise to the controversy between the two public agencies may be summarized as follows:
The Flood Control District was created by the Legislature in 1939 with boundaries coterminous with the boundaries of the County of San Bernardino. (Stats. 1939, ch. 73.) It is the fee owner of, or has easements for flood control purposes over, the beds and banks of certain watercourses and flood control channels located in and near the easterly portion of the City of San Bernardino. Over the years, through three federally financed flood control projects, the district has caused extensive protective work to be constructed in and along the streams and channels. In 1961, pursuant to the district’s
• In January 1967, at a public hearing on the proposed project conducted by the Corps of Engineers in San Bernardino, Water District objected to that feature of the proposed project calling for concrete lining of watercourses and channels on the ground that it would prevent percolation of waters into the underground basin.
Water District is a county water district organized in 1954 under the provisions of division 12 of the Water Code, and its boundaries embrace the easterly portion of the City of San Bernardino. In May 1967 Water District filed an eminent domain action against Flood Control District and others to condemn 1 ‘ a nonexclusive easement for the use of the bed and banks” of certain named watercourses and flood control channels, including Warm Creek and its tributaries, “for the spreading, sinking, controlling and storing” the waters of the streams and channels for the beneficial use of the district and its inhabitants, exclusive, however, of the right to enlarge the watercourses and channels. It is conceded that the action was precipitated by Flood Control District’s'proposed project.
Both in the court below, and in this court, the parties have filed declarations which, in addition to the facts heretofore recited, state the following:
The. flood control engineer states: that extensive residential and commercial developments coupled with recent watershed burns necessitate construction of the proposed Upper Warm Creek project; that the Army Corps of Engineers recom
The manager of the Water District and its consulting engineer state that the district embraces approximately 6,500 acres of the easterly portion of the City of San Bernardino, that it provides water for municipal and domestic purposes to approximately 34,000 inhabitants, that the district is largly dependent upon the ground water basin for its source of water supply and in order to maintain that supply acquires and percolates surface waters from various sources, that concrete lining of the channels and watercourses as proposed by Flood Control District would prevent percolation and result in an estimated average annual ground water loss to the basin from which the district derives its water supply of 2,320 acre feet, that it is both practical and feasible to line the sides of the streams and channels for flood protection but to leave the bottom open to permit continued replenishment of the underground basin by percolation, and that such a design would fulfill flood control and conservation purposes at the same time, and that such uses of the watercourses and channels are compatible and may be enjoyed in common.
Flood Control District contends that Water District is without legislative authority to condemn the interest sought and that, under the guise of an eminent domain action, Water District is attempting to dictate the design of flood control projects. On the other hand, Water District contends that it is merely seeking to impose a 11 non-exclusive easement” for the use of beds and banks of the streams and channels for water conservation purposes, that it is empowered to maintain the action if the use for which it seeks to take the property is compatible with flood control uses, and that the trial court has jurisdiction to resolve the factual issue of compatibility. The trial court concluded that Water District’s right to maintain its action turned on the question of compatibility of uses and that that was a factual issue to be resolved after a full scale trial.
The authority of the Water District to maintain its action turns upon the proper application of certain basic principles of the law of eminent domain. First, although the power of eminent domain is inherent in government, neither the state, its political subdivisions, municipalities, or public districts may exercise the power in the absence of legislative authorization, granted either expressly or by necessary implication. (City of Beaumont v. Beaumont Irr. Dist., 63 Cal.2d 291 , 293 [ 46 Cal.Rptr. 465 , 405 P.2d 377 ]; County of Marin v. Superior Court, supra, 53 Cal.2d 633 , 636; People v. Superior Court, 10 Cal.2d 288 , 295-296 [ 73 P.2d 1221 ].) Second, property already appropriated to a public use ordinarily may not be taken (a) unless it is “for a more necessary public use,”[1] or (b) unless, and only under certain limited circumstances, the public use for which the property is sought is one which is
1 Code of Civil Procedure, sections 1240, subdivision 3, and 1241, subdivision 3; see State ex rel. State Public Works Board v. City of Los Angeles, 256 Cal.App.2d 930 , 933 [ 64 Cal.Rptr. 476 ]; People v. City of Los Angeles, 179 Cal.App.2d 558 , 564 [ 4 Cal.Rptr. 531 ].)
Although it is so alleged in the complaint, Water District does not seriously contend that the purpose for which it is seeking “a non-exclusive easement” in the beds and banks of the watercourses and channels is “for a more necessary public use ’ ’ than that to which they are presently devoted.
The San Bernardino County Flood Control District was created by the Legislature to provide flood control protection and to conserve storm and flood waters for beneficial use within the district.[4] It is authorized to exercise the power of
2 Code of Civil Procedure, section 1240, subdivisions 3 and 6; Reclamation Dist. No. 551 v. Superior Court, 151 Cal. 263 [ 90 P. 545 ]; City of Pasadena v. Stimson, 91 Cal. 238 [ 27 P. 604 ]; Los Angeles v. Los Angeles Pac. Co., 31 Cal.App. 100 [ 159 P. 992 ]; see City of Oakland v. Schenck, 197 Cal. 456 [ 241 P. 545 ].)
4 Section 2 of the San Bernardino County Flood Control Act, (Act), Statutes 1939, chapter 73, provides in part: “The objects and purposes of this act are to provide for the control of the flood and storm waters of said district and the flood and storm waters of streams that have their source outside of said district, but which streams and the flood waters thereof flow into said district, and to conserve such waters for beneficial and useful purposes by spreading, storing, retaining and causing to percolate into the soil within said district, or without such district, such waters, or to save or conserve in any manner all or any of such waters and protect from such flood or storm waters, the watercourses, watersheds, public highways, life and property in said district, and to prevent waste of water or diminution of the water supply in, or exportation of *520 water from said district, and to obtain, retain and reclaim drainage, storm, flood and other waters for beneficial nsn in said district. ’ ’
By granting the Flood Control District comprehensive powers over the control and conservation of storm and flood waters, including the power to condemn property already appropriated by a public district or public corporation “to control flood waters or to conserve such flood or storm waters,” the Legislature has by implication determined that the uses proposed by Flood Control District in the instant case are to be considered a more necessary public use than that proposed by Water District. This legislative determination is binding on the courts. (See State ex rel. State Public Works Board v. City of Los Angeles, 256 Cal.App.2d 930 , 933-934 [ 64 Cal.Rptr. 476 ]; Barry v. Department of Public Works, 199 Cal.App.2d 359 , 363 [ 18 Cal.Rptr. 637 ].)
Even in the absence of such clear legislative intent, Water District’s proposed use could not be held to be a more necessary public use. The construction of improvements in and along channels and watercourses for the protection of lives "and property is of primary concern to the State.[7] In another context, it has been observed that “ [t]he construction of improvements along a stream for purposes of flood control is no less essential to the public health and safety than the grading of streets. ...” (O’Hara v. Los Angeles County Flood
5 Seetion 2, subdivision 8, of the Act.
6 Section 2, subdivision 9, of the Act.
7 Section 12578 of the Water Code provides: “It is hereby declared that the people of the State have a primary interest in the control and conservation of flood waters, prevention of damage by flood waters, the washing away of river and stream banks by floods, and in the determination of the manner in which flood waters shall be controlled for the protection of life and property and the control, storage, and use of the State’s water resources in the general public interest. ’ ’
Water District bases its right to maintain its eminent domain action to acquire “non-exclusive easement” in the beds and banks of the streams and channels primarily on the ground that it is one which can be exercised without interfering with their use for flood control purposes. It contends that the right of one public agency, by eminent domain, to impose a public servitude on an existing public servitude when the uses are compatible is recognized both by judicially established principles and by statute.
The most familiar instances of common use involve crossings, intersections of rights-of-way, or the maintenance of utility transmission facilities in highway rights-of-way. Manifestly in such situations the imposition of the second servitude would not impair the enjoyment of the existing easement. The general principle has been stated as follows: “A particular public easement may be imposed upon land already subject to a different public easement without express legislative authority if the exercise of the second easement will not interfere with the exercise of the first, or if the amount of land taken is not enough to impair the use of the remainder for the original purpose. [Footnote omitted.] This rule has been extended so as to justify the imposition of an easement without express legislative authority upon land already devoted to a different public use, even to the detriment of the prior use, when such detriment is trivial and the two easements can be exercised at the same time without serious conflict, and the expense of laying out the second work over private land would be wholly disproportionate to the injury to the earlier undertaking from the encroachment upon its location. . . (1 Nichols, Eminent Domain [rev.3d ed. 1964], § 2.2[8], pp. 237-238.)
In this state, subdivisions 3 and 6 of section 1240 of the
There are very few decisions in this state involving the common use provisions of subdivisions 3 or 6 of section 1240 and those that have considered those provisions are not helpful in resolving the issue here presented. None involved a situation comparable to that presented in the case under review. It has been held that the statute authorized the taking of an easement for the installation and maintenance of a sewer line in a highway right-of-way. (City of Pasadena v. Stimson, 91 Cal. 238 , 255 [ 27 P. 604 ].) In Reclamation Dist. No. 551 v. Superior Court, 151 Cal. 263 [ 90 P. 545 ], a railroad company sought to condemn a longitudinal use of the top of a reclamation district levee for a railroad right of way. The court
9 Subdivision 1 of section 1247 provides: "The court shall have power: 1. To regulate and determine the place and manner of making connections .ánd crossings, or of enjoying the common use mentioned in subdivision 6 of Section 1240; ...” -Section 1247a provides: "The court shall also have power to regulate and determine the place and manner of removing or relocating structures or improvements, or of enjoying the common use mentioned in subdivision ‘3 of Section 1240.”
The resolution of the question whether a proposed new use may co-exist with the continuance of an existing use requires a consideration, not only of the existing physical use being made of the property, but such use thereof as may be reasonably necessary for the purpose to which it is appropriated. (11 McQuillin, Municipal Corporations (3d ed. rev.) p. 430; cf. East Bay Municipal Utility Dist. v. Lodi, 120 Cal.App. 740 , 750 [ 8 P.2d 532 ].) The question is whether “the exercise of the second easement will not interfere with the exercise of the first.” [Italics supplied.] (1 Nichols, Eminent Domain, supra, p. 237.)
In the ease under review Water District seeks the use of the beds and banks of the channels and watercourses “for the spreading, sinking, controlling and storing” waters of those channels and streams whereas the Flood Control District, pursuant to the statutory authority vested in it and in the exercise of its rights in the channel beds and banks, in cooperation with the United States Army Corps of Engineers, has investigated the need for additional flood control protection in the area and has designed and proposes to construct a system which includes the concrete lining of watercourses and channels. The use sought to be made of the beds and banks by Water District is manifestly in direct conflict with the use proposed by and authorized to be made by Flood Control District.
While reasonable minds might differ respecting the compatibility of the uses sought to be imposed on existing uses under the circumstances presented in Reclamation Dist. v. Superior Court, supra, 151 Cal. 263 , and Los Angeles v. Los Angeles Pac. Co., supra, 31 Cal.App. 100 , in the case under review the admitted facts reveal the use sought to be imposed to be patently so directly in conflict with the continuance of the existing use that the two must be held to be inconsistent as a matter of law.[10]
10 We assume for the purpose of the present opinion that, apart from the issue of compatibility of uses, the property sought to be taken and *524 the use sought to be made by the Water District qualify for common use under subdivisions 3 or 6 of section 1240 of the Code of Civil Procedure. However, there is a question whether property appropriated to a public use by a public corporation may be taken for a common use under subdivision 3, and it is doubtful whether the rights sought to be taken by the Water District constitute a “right-of-way” within the meaning of- subdivision 6. The common use provision of subdivision 3 refers to property appropriated to a public use by “any individual, firm or private corporation,” and subdivision 6 relates to imposition of a “right-of-way” servitude on existing “rights-of-way.” In view of our conclusion that the proposed use by the Water District is inconsistent with flood control uses as a matter of law, we find it unnecessary to express any , opinion on the foregoing questions.
In County of Marin v. Superior Court, supra, 53 Cal.2d 633 , a municipal water district sought to condemn for a reservoir site county roads which were a part of a federal aid secondary highway system constructed with federal funds. Upon discovering that its project would inundate the roads, the water district offered to relocate them, but being unable to reach an agreement with the county over the terms of the relocation and reconstruction of the roads, it filed eminent
In the present case, by filing the eminent domain action, Water District, in essence, is attempting to enjoin Flood Control District from constructing the proposed flood control project and to have the superior court redesign it. The rationale of the additional ground of the holding in County of Marin v. Superior Court, supra, 53 Cal.2d 633 , is apposite. It provides a further reason for the issuance of a writ of prohibition in the present case.
We conclude that the Water District is not authorized to maintain the action in eminent domain. It is ordered that a peremptory writ of prohibition issue enjoining respondent court from taking any further proceedings against petitioner,
McCabe, P. J., and Fogg, J. pro tem.,[11] concurred.
The petition of the real party in interest for a hearing by the Supreme Court was denied April 23, 1969. Mosk, J., was of the opinion that the petition should be granted.
* Assigned by the Chairman of the Judicial Council.
Cases cited
- Harden v. Superior Court 44 Cal.2d 630 at 637 p. 518
- County of Marin v. Superior Court 53 Cal.2d 633 at 636, at 642 p. 518, p. 524, p. 525
- Northwestern Pacific Railroad v. Superior Court 34 Cal.2d 454 at 458-459 p. 518
- Corona Unified Hospital District v. Superior Court 61 Cal.2d 846 at 850-852 p. 518
- City of Beaumont v. Beaumont Irrigation District 63 Cal.2d 291 at 293, at 297 p. 518, p. 521
- State ex rel. State Public Works Board v. City of Los Angeles 256 Cal.App.2d 930 at 933-934 p. 520
- Barry v. Department of Public Works 199 Cal.App.2d 359 at 363 p. 520
- O'Hara v. Los Angeles County Flood Control District 19 Cal.2d 61 at 63 p. 521
- City of Pasadena v. Stimson 91 Cal. 238 at 255 p. 522
- Reclamation Dist. No. 551 v. Superior Court of Sacramento 151 Cal. 263 p. 522, p. 523
- City of Los Angeles v. Los Angeles Pacific Co. 31 Cal.App. 100 p. 523
- East Bay Municipal Utility District v. City of Lodi 120 Cal.App. 740 at 750 p. 523