Majority
Opinion
Real party in interest Magma Energy, Inc. (hereafter Magma) applied to respondent Lake County Planning Commission (hereafter Planning Commission) for a use permit to drill three exploratory geothermal wells in an area on the slope of Mt. Konocti in Lake County. The Planning Commission ordered that a full environmental impact report (EIR) be prepared prior to approval of the permit. Magma filed an EIR, analyzing only the effects of the exploratory drilling. No consideration was given to the impact of a geothermal production unit in the event the exploratory wells were successful. The Planning Commission certified the EIR as being in compliance with the California Environmental Quality Act (hereafter CEQA), but denied Magma the use permit under section 78.2 of the Lake County Zoning Ordinance.
Magma appealed to respondent Lake County Board of Supervisors (hereafter Board of Supervisors) which overturned the Planning Commission decision and ordered that the Planning Commission issue a use permit for two of the exploratory wells. Appellant Lake County Energy Council filed in the superior court a petition for writ of mandate, seeking to set aside the certification of the EIR by the Planning Commission and
The point in controversy is clear: Appellant asserts that in connection with an application for exploratory geothermal drilling, an EIR which is prepared must assess the effects of commercial development in the event that geothermal resources are encountered; Magma and respondents contend that such an EIR need only extend to the exploratory drilling for which the application is sought.
We commence our analysis by reference to the guidelines issued, by the Secretary of Resources for implementation of CEQA. (Cal. Admin. Code, tit. 14.) Section 15069 of these guidelines provides: “Where individual projects are, or a phased project is, to be undertaken and where the total undertaking comprises a project with significant environmental effect, the responsible agency or Lead Agency must prepare a single EIR for the ultimate project. Where an individual project is a necessary precedent for action on a larger project, or commits the Responsible Agency to a larger project, with significant environmental effect, an EIR must address itself to the scope of the larger project, subject to the limitation of Section 15066 of these Guidelines. Where one project is one of several similar projects of a public agency, but is not deemed a part of a larger undertaking or a larger project, the agency may prepare one EIR for all projects, or one for each project, but should in either case comment upon the combined effect.” (Italics added.)
Since exploratory drilling is no doubt a “necessary precedent” to the larger project of commercial development, the guidelines seem to require that the EIR address itself to the scope of the “larger project.” However, since the scope of the larger project is unknown until the initial project (exploratory wells) is completed, and the initial project, as will be shown below, does not “commit the Responsible Agency” to the larger project, it is arguable that an EIR need not encompass the contingency of commercial development.
The controversy is sharpened by California cases interpreting CEQA. While it is clear that tíre requirements of CEQA “cannot be avoided by chopping up proposed projects into bite-size pieces” which, when taken individually, may have no significant adverse effect on the environment (Plan for Arcadia, Inc. v. City Council of Arcadia (1974) 42 Cal.App.3d 712 , 726 [ 117 Cal.Rptr. 96 ]), it is also true that where future
In No Oil, Inc. v. City of Los Angeles (1974) 13 Cal.3d 68 , 77, footnote 5 [ 118 Cal.Rptr. 34 , 529 P.2d 66 ], the dilemma presented by these cases was recognized. The Supreme Court, although it did not (and needed not to) decide the issue, aptly and succinctly described the issues as follows: “Plaintiffs contend that the trial court erred in limiting the scope of the ‘project’ at issue to the drilling of two test wells; they maintain that the scope of inquiry should include the environmental effects of commercial production and exploitation of the oil resources of the Pacific Palisades. They point out that the drilling of the test wells would be a useless waste of money unless commercial production can follow. Thus information on the environmental impact of commercial production is relevant to the council’s decision to approve the test wells; if that data proved that commercial production would be harmful, the council might well decide to disapprove the test drilling. Under these circumstances, plaintiffs observe that a narrow definition of ‘project’ which bars inquiiy into the environmental effects of commercial production defeats the objectives of the act. [H] Defendants protest, however, that the geologic information obtained from the test wells is essential to the preparation of an accurate EIR on the impact of commercial production. As the court pointed out in Scientists' Inst. for Pub. Info., Inc. v. Atomic Energy Com'n (1973) 481 F.2d 1079 [ 156 App.D.C. 395 ], an impact statement prepared before reliable information is available would ‘tend toward uninformative generalities’ (481 F.2d at p. 1093), but one delayed until after key decisions have been made could not assure that such decisions reflected environmental consideration. ‘Thus we are pulled in two directions. Statements must be written late enough in the development process to contain meaningful information, but they must be written early enough so that whatever information is contained can practically serve as an input into the decision making process.’ (481 F.2d at p. 1094.) [H] The issue thus narrows to the question whether the city, before drilling of the test wells, has sufficient reliable data to permit preparation of a meaningful and accurate report on the impact of commercial production. Unfortunately the parties have not briefed this question thoroughly, and the record contains little evidence pertinent to its resolution. Since we are persuaded by plaintiffs’ other contentions to reverse the judgment against them, we need not and do not decide whether the trial court erred in limiting the scope of inquiry to exclude consideration of commercial production.” (No Oil, Inc., supra, at p. 77.)
We note further that approval of the exploratory wells in no manner commits the Board of Supervisors to approval of general commercial development. In its findings pursuant to the granting of the use permit, the board states: “6. This use permit is for two (2) exploratory wells and the Board of Supervisors reaffirms that the granting of this use permit neither establishes precedent for geothermal field development in the immediate area, .nor includes commitment to single resource exploitation.” This case is thus clearly distinguishable from Environmental Defense Fund, Inc. v. Coastside County Water Dist. (1972) 27 Cal.App.3d 695 [ 104 Cal.Rptr. 197 ], where construction of the first phase of a project in effect committed the developer to a larger plan. (Id., at pp. 706-707.) Here, to the contrary, the administrative agencies involved have determined, and the subject EIR itself states, that if geothermal sources are eventually discovered, a very comprehensive EIR would be required prior to commercial development. Until such a source is discovered, this activity cannot be viewed as a “phased project.”
Finally, we take cognizance of the fact that before any facilities for geothermal production are constructed, the state energy commission must evaluate and certify such facilities. (Pub. Resources Code, § 25500; 58 Ops.Cal.Atty.Gen. 729.) Section 25500 provides that the issuance of such a certificate shall be required in lieu of any permit, certificate or similar document required by any state, local or regional entity.
The Supreme Court has indicated in No Oil, Inc. that an EIR dealing with exploratory drilling must discuss the impact of the commercial development which may result therefrom only where “meaningful inquiry” into the consequences of such development can be made. (13 Cal.3d at p. 77, fn. 5.) As appellant has not demonstrated that such meaningful inquiry can be made at this point in time, we conclude that the Planning Commission did not abuse its discretion in certifying an EIR which confined itself to the environmental impact of that for which the use permit was sought, i.e., the drilling of exploratory wells.
The judgment is affirmed.
Rattigan, Acting P. J., and Christian, J., concurred.
A petition for a rehearing was denied July 19, 1977.
Footnotes
- * Retired judge of the superior court sitting under assignment by the Acting Chairman of the Judicial Council.
Cases cited
- Plan for Arcadia, Inc. v. City Council of Arcadia 42 Cal.App.3d 712 at 726 p. 854
- Topanga Beach Renters Ass'n v. Department of General Services 58 Cal.App.3d 188 at 196 p. 855
- No Oil, Inc. v. City of Los Angeles 13 Cal.3d 68 at 77 p. 855
- Environmental Defense Fund, Inc. v. Coastside County Water District 27 Cal.App.3d 695 p. 856
- Hixon v. County of Los Angeles 38 Cal.App.3d 370 at 378-379 p. 857