Majority
Opinion
In January 1989, Residents for Adequate Water and respondents Michael E. Sweeney and Oliver L. Sause obtained a writ of mandate halting the connection of new residential water service by appellant Redwood Valley County Water District. In July 1993, the district unsuccessfully moved to dissolve the writ of mandate and to set aside the subsequent judgment. (Code Civ. Proc., § 473.) The district appeals the order denying its motion to set aside the judgment,[1] contending that the trial court lacked jurisdiction to issue the writ of mandate because (1) it misinterpreted and misapplied the Safe Drinking Water Act and its implementing regulations, and (2) those seeking the writ did not exhaust their administrative remedies. We affirm the order denying the motion to set aside the judgment.
I. Facts
In February 1988, Residents for Adequate Water and respondents Michael
1 The district filed a timely notice of appeal. (See Cal. Rules of Court, rule 2(a).)
In January 1989, the trial court issued a judgment and a peremptory writ in accordance with the petition. In its statement of decision, the trial court found that the district did not possess a water source capacity sufficient to supply the needs of its users under maximum demand conditions as required by law, but that the district continued to permit new service connections to be added to its water system. Thus, the court imposed an immediate moratorium on new service connections by the district.
The district appealed this judgment.[2] Its motion for stay of judgment pending appeal was denied in February 1989. In September 1989, the appeal was dismissed pursuant to a stipulation of both sides seeking a dismissal with prejudice.
In January 1990, the district moved to modify the writ of mandate, without success. In July 1993, the district moved to dissolve the writ of mandate and to set aside the judgment. (Code Civ. Proc., § 473.) The district alleged two grounds in support of its motion—that there had been a significant change in the district water supply and that the underlying judgment was void. In November 1993, this motion was denied.[3]
2 The State Department of Health Services was also compelled to act under this peremptory writ of mandate, but does not challenge the writ on appeal. The district’s brief challenges the portion of the writ of mandate directed to the department as well as that part directed to itself, but as the department has not perfected an appeal, we do not determine those issues.
3 The district also argued that changed circumstances warranted the modification of the judgment. The trial court declined to consider the merits of this motion on the ground that the district had unclean hands in that it failed to counter evidence that it had authorized new water connections in violation of that judgment. The district does not appeal from this aspect of the trial court’s November 1993 order. In February 1994, the district again moved to modify the judgment and writ of mandate. The trial court denied this motion in June 1994, finding that the district continued to act in violation of the judgment and finding that there was then no change of circumstances sufficient to warrant modification.
II. Appealability
III. Statutory Authority
The district first contends that the trial court lacked subject matter jurisdiction over this action. In essence, the district argues that the trial court misinterpreted and misapplied the Safe Drinking Water Act and its implementing regulations. (See Health & Saf. Code, §§ 4010-4039.6; Cal. Code
4 Michael E. Sweeney filed a respondent’s brief on his own behalf, in which Oliver L. Sause concurs by letter. Residents did not file a brief. For convenience, all respondents will be referred to as “Sweeney.”
5 The 1989 appeal was dismissed before the date on which the district was to file an opening brief.
On appeal, the district argues the statutes that the trial court relied on to issue its writ of mandate do not compel the district to refrain from authorizing new water connections. It urges us to find that the writ operates to compel the district to exercise its discretion, not to perform a legal duty. A writ of mandate may issue only to compel the performance of an act which the law specially enjoins, as a duty resulting from an office, trust or station. (Code Civ. Proc., § 1085; Gilbert v. State of California (1990) 218 Cal.App.3d 234 , 241 [ 266 Cal.Rptr. 891 ]; Sullivan v. State Bd. of Control (1985) 176 Cal.App.3d 1059 , 1062-1063 [ 225 Cal.Rptr. 454 ]; see 8 Witkin, Cal. Procedure (3d ed. 1985) Extraordinary Writs, § 65, pp. 702-704.) Mandate will lie if the district has a clear, present and usually ministerial duty and Sweeney has a clear, present and beneficial right of performance of that duty. However, Sweeney may not invoke mandamus to control the district’s discretion. A court may—in appropriate circumstances—compel an agency to exercise its discretion, but cannot compel an agency with discretionary power to act in any particular manner. A court may not substitute its discretion for that properly vested in an administrative agency. (See Gilbert v. State of California, supra, at p. 241.)
The district contends that it does not have a mandatory duty to halt new service connections. We disagree. The Safe Drinking Water Act provides that the operator of a public water system is charged with a mandatory duty to provide a reliable and adequate supply of pure, wholesome and potable water. (§ 4017, subd. (c).) No operator of a public water system shall modify its authorized distribution system unless the operator first submits an application to the Department of Health Services and receives an amended permit as provided in the Safe Drinking Water Act authorizing the modification. (§ 4016, subd. (a).) The California Waterworks Standards—the administrative regulations promulgated pursuant to the Safe Drinking Water
6 A11 statutory references are to the Health and Safety Code unless otherwise indicated.
IV. Exhaustion
The district also contends that the underlying judgment is void—that the trial court lacked subject matter jurisdiction over this action because the original petitioners did not exhaust their administrative remedies. When an administrative remedy has been provided by statute, this remedy must be exhausted before the courts will act. (Abelleira v. District Court of Appeal (1941) 17 Cal.2d 280 , 292 [ 109 P.2d 942 , 132 A.L.R. 715 ]; Karlin v. Zalta (1984) 154 Cal.App.3d 953 , 979 [ 201 Cal.Rptr. 379 ].) Exhaustion of administrative remedies is a jurisdictional requirement. (Browning-Ferris Industries v. City Council (1986) 181 Cal.App.3d 852 , 859 [ 226 Cal.Rptr. 575 ]; see 3 Witkin, Cal. Procedure, supra, Actions, § 234, pp. 264-266.)
However, the district does not contend that Sweeney failed to exhaust any administrative remedy to seek the mandated action from the district. Instead, it urges us to find a lack of trial court jurisdiction because Sweeney did not petition the Water Resources Control Board to determine whether the Mendocino County Russian River Flood Control and Water Conservation and Improvement District violated a permit by selling water to the district.
The order denying the motion to set aside the judgment is affirmed. The district shall pay all Sweeney’s costs on appeal, in an amount to be determined by the trial court.
Perley, J., concurred. Poché, Acting P. J., concurred in the judgment.
Cases cited
- Brockman v. Brockman 194 Cal.App.3d 1035 at 1041 p. 1805
- County of Ventura v. Tillett 133 Cal.App.3d 105 at 110 p. 1805
- Gilbert v. State 218 Cal.App.3d 234 at 241 p. 1806
- Sullivan v. State Board of Control 176 Cal.App.3d 1059 at 1062-1063 p. 1806
- Abelleira v. District Court of Appeal 17 Cal.2d 280 at 292 p. 1807
- Karlin v. Zalta 154 Cal.App.3d 953 at 979 p. 1807
- Browning-Ferris Industries v. City Council 181 Cal.App.3d 852 at 859 p. 1807
- County of Alpine v. County of Tuolumne 49 Cal.2d 787 at 798 p. 1808