Majority
Opinion
I. Introduction
Plaintiff, Capitol Steel Fabricators, Inc. (Capitol), a subcontractor, appeals from a judgment entered against it in favor of defendants Mega Construction Co., Inc. (Mega), the general contractor, and Fidelity and Deposit Company of Maryland (Fidelity), the surety, on a complaint arising out of a public works contract. The primary issue presented by this appeal is whether the trial court properly determined a “pay when paid” clause was enforceable
H. Background
The complaint was filed on June 23, 1992, and named as defendants Mega, Fidelity, and the Long Beach Unified School District (the district). Plaintiff asserted causes of action for breach of contract, public works stop notice, and statutory payment bond. The district was merely a stakeholder and has since been dismissed from the action. The complaint alleged, prior to November 5, 1990, Mega and the district entered into the prime contract for the construction of the project known as the New Avalon School Gymnasium on Catalina Island. On November 5, 1990, Capitol and Mega entered into a written subcontract which was subsequently modified. Under the terms of the subcontract, Capitol was to supply Mega with structural steel fabrication, erection labor services, and equipment and material for the project. Mega obtained a bond to secure payment for laborers, material suppliers, and other persons from Fidelity. The prime contract was between the district and Mega. Capitol claimed it performed all terms of the subcontract as modified by the parties. However, Capitol argued Mega failed to pay the amount due under the subcontract. Capitol alleged it had been damaged in the amount of $33,716.50 plus interest from January 27, 1992, and attorney’s fees. Plaintiff served a stop notice on May 21, 1992. Defendants answered the complaint. Mega asserted among other defenses backcharges and offsets for allegedly defective workmanship.
The dispute proceeded to trial on April 14, 1995. The parties agreed to have the matter tried on certain stipulated facts subject to briefing and oral argument. The parties stipulated to the following facts. The subcontract was entered into on November 5, 1990. Capitol performed work on the project and was in the class of beneficiaries under the payment bond issued pursuant
1 Because the issue is not briefed nor pertinent to the present case, we do not address the question of the effect of the Wm. R. Clarke Corp. decision when a public entity is a party to the litigation.
On January 18,1993, Mega filed a claim under Government Code section 900 et seq. with the district for $652,011.39 plus interests and costs. The claim was also for work which Mega, the general contractor, contended it or its subcontractors had performed on the project. On May 28, 1993, Mega filed a complaint against the district which was settled in February 1995. On March 1,1995, Mega, the general contractor, paid $33,716.50 to Capitol, the subcontractor. This was in exchange for Capitol’s execution and delivery to Mega of a release of the stop notice. The payment was made without prejudice to claims by Capitol, the subcontractor, that there were additional monies due to it which Mega, the general contractor, denied and disputed. As of the date of the “Stipulation of Facts” in the present case, April 28, 1995, the district had not paid Mega the amount due under the settlement agreement. The parties further stipulated that the prevailing party would be entitled to recover reasonable attorney’s fees and costs.
Capitol argued it was entitled to unpaid interest and attorney’s fees totaling $25,343.89. This was because the March 1, 1995, payment of $33,716.50 was allocated to satisfy accrued interest of $9,274.21 and attorney’s fees and costs of $16,069.18, leaving an $8,373.11 balance for allocation to principal. The interest was due on the amount which Capitol recovered as liquidated damages, $33,716.50, from the date they became due pursuant to section 3287. This was because, when Mega paid Capitol the entire contract retention amount and abandoned the claims for an offset, such constituted an admission of the lack of merit in the backcharges. Capitol also contended its claims were capable of being made certain with reliance only on documents that existed as of January 27, 1992. Capitol further asserted it was entitled to recover on the bond pursuant to section 3226 because the only conditions for recovery on the payment bond are that the claimant is one of the class identified in section 3110 and is unpaid.
Mega contended it was not required to pay the additional amount because there are three “pay when paid” clauses in the contract between the parties.
2 All further statutory references are to the Civil Code unless otherwise indicated.
Capitol countered the “pay when paid” clause was unenforceable because such provisions are null and void under section 3262, subdivision (a) which
3 It is not clear from the rider whether the clause should read “placed in position as condition precedent and for which payment” or “placed in position and as condition precedent.”
Mega also asserted the entire payment of $33,716.50 must be allocated to principal. Mega further argued Capitol waived all right to claim interest by accepting the whole principal amount pursuant to section 3290. Also, Mega argued Capitol waived all rights to recover for alleged extra work by executing a conditional waiver and release upon receiving a progress payment on April 10, 1992, which covered the period when the alleged extra work was completed. Capitol billed Mega for the last work on January 27, 1992. The waiver and release provided it covered “progress payments] for labor, services, equipment or material furnished to [Mega] through January 31, 1992 only and [did] not cover any retention or items furnished after said date.” Capitol argued its conditional release was not a waiver of all its extra work claims. Also, Capitol contended Mega should be equitably estopped to assert the release was a waiver.
Both sides asserted they were entitled to attorney’s fees and costs as the prevailing party. Capitol argued it was the prevailing party because it obtained greater relief under the contract given that Mega paid the entire amount due under the contract. According to Capitol, if the payment by the district “was truly a ‘condition precedent’ to [Mega’s] obligation to pay, [Mega] would not yet have paid anything.” Defendants countered they were the prevailing parties because the owner never paid Mega, therefore the payment never became due under the “pay when paid” clause of the subcontract.
The trial court found for Mega and Fidelity and entered judgment. The court made an award of attorney’s fees and costs to defendants. In its statement of decision, the trial court determined the “pay when paid” clause was enforceable. As a result, the trial judge concluded Mega had no duty to pay Capitol until the district paid the general contractor. The court concluded
A. Standard of Review
The interpretation of a written instrument is a judicial function which is exercised according to general canons of interpretation so that the purposes of the instrument are to be given effect. (Parsons v. Bristol Development Co. (1965) 62 Cal.2d 861 , 865 [ 44 Cal.Rptr. 767 , 402 P.2d 839 ], citing §§ 1635-1661 and Code Civ. Proc., §§ 1856-1866.) The Supreme Court has held: “The fundamental goal of contractual interpretation is to give effect to the mutual intention of the parties. (Civ. Code, § 1636.) If contractual language is clear and explicit, it governs. (Civ. Code, § 1638.)” (Bank of the West v. Superior Court (1992) 2 Cal.4th 1254 , 1264 [ 10 Cal.Rptr.2d 538 , 833 P.2d 545 ].) If the contract terms are ambiguous, the appellate court is bound by the findings of fact made on evidence which was introduced to aid in its interpretation. (Pierpont Inn, Inc. v. State of California (1969) 70 Cal.2d 282 , 294 [ 74 Cal.Rptr. 521 , 449 P.2d 737 ], disapproved on another point in Los Angeles County Metropolitan Transportation Authority v. Continental Development Corp. (1997) 16 Cal.4th 694 , 698-699 [ 66 Cal.Rptr.2d 630 , 941 P.2d 809 ]; cf. Parsons v. Bristol Development Co., supra, 62 Cal.2d at p. 865.) Where the interpretation of the contract does not turn on credibility of extrinsic evidence, the appellate review is de novo. (Estate of Dodge (1971) 6 Cal.3d 311 , 318 [ 98 Cal.Rptr. 801 , 491 P.2d 385 ]; see Keane v. Smith (1971) 4 Cal.3d 932 , 939 [ 95 Cal.Rptr. 197 , 485 P.2d 261 ].) Contracts are construed as a whole. (Nish Noroian Farms v. Agricultural Labor Relations Bd. (1984) 35 Cal.3d 726 , 735 [ 201 Cal.Rptr. 1 , 677 P.2d 1170 ]; Adkins v. Lear, Inc. (1967) 67 Cal.2d 882 , 905 [ 64 Cal.Rptr. 545 , 435 P.2d 321 ];
4 Because we conclude the present dispute is governed by Wm. R. Clarke Corp. v. Safeco Ins. Co., supra, 15 Cal.4th at pages 888-897, we do not address the trial judge’s conclusion that section 3262 only applies to prime contracts between a contractor and an owner.
B. The Subcontract Contained a “Pay When Paid" Clause
We agree with the trial judge that the subcontract deferred payment to Capitol, the subcontractor, until Mega, the general contractor, was paid. Further, if Mega, the general contractor, were never paid, then no payments would ever be due to Capitol, the subcontractor and material supplier. Capitol’s reliance on the substantial body of decisional and other authority relating to “pay when paid” clauses is unpersuasive. No doubt, there is a significant body of decisional authority which holds that unless there is a clear expression to the contrary, a “pay when paid” clause merely fixes a time for compensation. This body of law only permits payment to be delayed for a reasonable time after the completion of the work under the subcontract. (See Byler v. Great American Insurance Company (10th Cir. 1968) 395 F.2d 273 , 276-277; Dancy v. William J. Howard, Inc. (7th Cir. 1961) 297 F.2d 686 , 688-689; Trinity Universal Insurance Company v. Smithwick (8th Cir. 1955) 222 F.2d 16 , 22-23; F.W. Sims, Inc., v. Federal Ins. Co. (E.D.N.Y. 1992) 788 F.Supp. 149 , 150-151; Statesville Roofing & Heating Co., Inc. v. Duncan (W.D.N.C. 1988) 702 F.Supp. 118 , 119-122; Aesco Steel, Inc. v. J.A. Jones Const. Co. (E.D.La. 1985) 621 F.Supp. 1576 , 1578-1580; Havens Steel Co. v. Randolph Engineering Co. (W.D.Mo. 1985) 613 F.Supp. 514 , 539; Seal Tite Corp. v. Ehret, Inc. (D.N.J. 1984) 589 F.Supp. 701 ,703-705; Moore v. Continental Casualty Company (W.D.Okla. 1973) 366 F.Supp. 954 , 955-956; Pioneer Roofing Co. v. Mardian Constr. Co. (1986) 152 Ariz. 455 [ 733 P.2d 652 , 666-667]; Yamanishi v. Bleily & Collishaw, Inc. (1972) 29 Cal.App.3d 457 , 462-463 [ 105 Cal.Rptr. 580 ]; DEC Elec., Inc. v. Raphael Const. Corp. (Fla. 1990) 558 So.2d 427 , 428-429; Grady v. S. E. Gustafson Construction Company (1960) 251 Iowa 1242 [ 103 N.W.2d 737 , 738-739]; Southern St. Masonry v. J.A. Jones Const. (La. 1987) 507 So.2d 198 , 199-206; Atlantic States Construction Co. v. Drummond & Co. (1968) 251 Md. 77 [ 246 A.2d 251 , 252-255]; Bayer & Mingolla v. A. J. Orlando Contracting (1978) 6 Mass.App. 1 [ 370 N.E.2d 1381 , 1382-1383]; Mrozik Const. v. Lovering Associates (Minn.Ct.App. 1990) 461 N.W.2d 49 , 51-52; American Drilling v. City of Springfield (Mo.Ct.App. 1981) 614 S.W.2d 266 , 273; D. K. Meyer Corp. v. Bevco, Inc. (1980) 206 Neb. 318 [ 292 N.W.2d 773 , 775-777]; Action Interiors v. Component Assembly (1988) 144 A.D.2d 606 [ 535 N.Y.S.2d 55 , 56]; Howard-Green Elec. Co. v. Chaney & James Const. Co. (1971) 12 N.C.App. 63 [ 182 S.E.2d 601 , 603-604]; Power & Pollution Svcs. v. Suburban Piping (1991) 74 Ohio App.3d 89 [ 598 N.E.2d 69 , 70-71]; Mignot v. Parkhill (1964) 237 Or. 450 [ 391 P.2d 755 , 759-761]; United Plate
However, the present case involves a subcontract which unambiguously defers payment until there has been the transfer of moneys from the district to the general contractor, Mega. Further, if Mega, the general contractor, was not paid by the district, Capitol, the subcontractor, would never receive payment for work and materials. The first reference to deferred payment referred to: monthly payments; 90 percent of the total due under the terms of the contract; a condition precedent; and a requirement that payment be made to Mega by the district. (See p. 1054, ante.) This is not the only reference in the subcontract to deferred payment. The subcontract also explicitly states that payment of the 10 percent retention would be deferred until final payment by the owner. (See p. 1054, ante.) Finally, the extras provision of the subcontract also delays payment until the district has paid Mega. (See p. 1054, ante.) The subcontract refers on three occasions to the delay of payment until Mega has been paid by the district in terms of: the contract amount; the 10 percent retention; and extras. Taken as a whole (Nish Noroian Farms v. Agricultural Labor Relations Bd., supra, 35 Cal.3d at p. 735; Adkins v. Lear, Inc., supra, 67 Cal.2d at p. 905), those references require payment by the district to Mega before Capitol can be compensated for its services and materials. If Mega, the general contractor, were never paid, Capitol would be uncompensated. The authority set forth in the immediately preceding paragraph is therefore distinguishable and not controlling.
C. The “Pay When Paid” Clause Is Unenforceable
The primary issue in this case is then whether the “pay when paid” clause is enforceable. In Wm. R. Clarke Corp. v. Safeco Ins. Co., supra, 15 Cal.4th at page 886, the Supreme Court determined that a “pay if paid” provision in a construction subcontract was unenforceable as a violation of public policy. The Supreme Court stated: “We conclude that pay if paid provisions like the one at issue here are contrary to the public policy of this state and therefore unenforceable because they effect an impermissible indirect waiver or forfeiture of the subcontractors’ constitutionally protected mechanic’s lien rights in the event of nonpayment by the owner. Because they are unenforceable, pay if paid provisions in construction subcontracts do not insulate
Wm. R. Clarke Corp. also emphasized the limited circumstances under which a subcontractor could waive mechanic’s lien rights which are codified in section 3262, subdivision (a), which provides: “Neither the owner nor original contractor by any term of their contract, or otherwise, shall waive, affect, or impair the claims and liens of other persons whether with or without notice except by their written consent, and any term of the contract to that effect shall be null and void. Any written consent given by any claimant pursuant to this subdivision shall be null, void, and unenforceable unless and until the claimant executes and delivers a waiver and release. Such a waiver and release shall be binding and effective to release the owner, construction lender, and surety on a payment bond from claims and liens only if the waiver and release follows substantially one of the forms set forth in this section and is signed by the claimant or his or her authorized agent, and, in the case of a conditional release, there is evidence of payment to the claimant. Evidence of payment may be by the claimant’s endorsement on a single or joint payee check which has been paid by the bank upon which it was drawn or by written acknowledgment of payment given by the claimant.” The written consent must be in the form of a waiver and release. (§ 3262, subd. (d).) The Supreme Court delineated the circumstances where lien rights would be waived as follows: “(1) a conditional waiver and release upon progress payment; (2) an unconditional waiver and release upon progress payment; (3) a conditional waiver and release upon final payment; and (4) an unconditional waiver and release upon final payment. Thus, under our mechanic’s lien law, waiver and release of mechanic’s lien rights is permitted only in conjunction with payment, or a promise of payment, and a conditional release is effective only if the claimant is actually paid. [Citation.]” (Wm. R. Clarke Corp. v. Safeco Ins. Co., supra, 15 Cal.4th at p. 889.)
In their letter briefs, the parties dispute whether Wm. R. Clarke Corp. should be applied to this case. Capitol, the subcontractor, of course, contends it does. Mega, the general contractor, asserts Wm. R. Clarke Corp. is distinguishable from the case at bench and should be limited to the specific clause at issue. Mega’s principal argument is that Wm. R. Clarke Corp. involved a private work of improvement, which is protected under California Constitution, article XIV, section 3, and no constitutional right is involved in this case, which involves a project funded by the public sector.[5]
Mega argues Wm. R. Clarke Corp. should be limited to its facts and is only applicable to private works cases. However, Mega has not cited any authority which establishes that subcontractors on public work projects are not protected by the anti-waiver provisions of section 3262. Rather, the distinction between public and private works is due to the principle of sovereign immunity which precludes recordation of mechanic’s liens on public works. (§3109; Pacific Employers Ins. Co. v. State of California (1970) 3 Cal.3d 573 , 576 [ 91 Cal.Rptr. 273 , 477 P.2d 129 ]; Miles v. Ryan (1916) 172 Cal. 205 , 207 [ 157 P. 5 ]; Sukut-Coulson, Inc. v. Allied Canon Co. (1978) 85 Cal.App.3d 648 , 654 [ 149 Cal.Rptr. 711 ].) Subcontractors and material suppliers on public improvement projects, such as Capitol, have as remedies stop notices (§§ 3179-3214) and actions on payment bonds. (§§ 3247-3252.) Under the payment bond provisions, it must inure to the benefit of all persons named in section 3181. The persons listed in section 3181, which pursuant to section 3110 includes subcontractors and material suppliers like Capitol, have a right of action on the payment bond. (§ 3248, subd. (c).)
Thus, the real issue posited by Mega is whether the pay when paid provision in this case remains enforceable because, due to the principle of sovereign immunity, laborers and material suppliers on public works are protected in the stop notice and public payment bond statutes rather than by a mechanic’s lien under the California Constitution. The purposes of
5 The parties do not dispute that the deferred payment language in the subcontract at issue has the same potential legal effect as a “pay if paid” clause as discussed in Wm. R. Clarke Corp.
Given this authority, there is no practical effect between the results in this case and in Wm. R. Clarke Corp. Here, as in Wm. R. Clarke Corp., enforcing
The judgment is reversed and the matter is remanded for further proceedings consistent with this opinion. Plaintiff, Capitol Steel Fabricators, Inc., is to recover its costs on appeal from defendants, Mega Construction Co., Inc., and Fidelity and Deposit Company of Maryland.
Grignon, J., and Godoy Perez, J., concurred.
* See footnote, ante, page 1049.
Cases cited
- Wm. R. Clarke Corp. v. Safeco Insurance of America 15 Cal.4th 882 at 888-897 p. 1052
- Parsons v. Bristol Development Co. 62 Cal.2d 861 at 865 p. 1056
- Bank of the West v. Superior Court 2 Cal.4th 1254 at 1264 p. 1056
- Pierpont Inn, Inc. v. State 70 Cal.2d 282 at 294 p. 1056
- Los Angeles County Metropolitan Transportation Authority v. Continental Development Corp. 16 Cal.4th 694 at 698-699 p. 1056
- Gill v. Stone 6 Cal.3d 311 at 318 p. 1056
- Keane v. Smith 4 Cal.3d 932 at 939 p. 1056
- Farms v. Agricultural Labor Relations Board 35 Cal.3d 726 at 735 p. 1056
- Adkins v. Lear, Inc. 67 Cal.2d 882 at 905 p. 1056
- Lear, Inc. v. Adkins 395 U.S. 653 at 676 p. 1057
- Yamanishi v. Bleily & Collishaw, Inc. 29 Cal.App.3d 457 at 462-463 p. 1057
- Action Interiors, Inc. v. Component Assembly Systems Inc. 144 A.D.2d 606 p. 1057
- Pacific Employers Insurance v. State of California 3 Cal.3d 573 at 576 p. 1060
- Miles v. Ryan 172 Cal. 205 at 207 p. 1060
- Sukut-Coulson, Inc. v. Allied Canon Co. 85 Cal.App.3d 648 at 654 p. 1060
- A-1 Door & Materials Co. v. Fresno Guarantee Savings & Loan Ass'n 61 Cal.2d 728 at 735 p. 1061
- Connolly Development, Inc. v. Superior Court 17 Cal.3d 803 at 809 p. 1061
- Mechanical Wholesale Corp. v. Fuji Bank, Ltd. 42 Cal.App.4th 1647 at 1659 p. 1061
- Department of Industrial Relations v. Seaboard Surety Co. 50 Cal.App.4th 1501 at 1508 p. 1061
- Powers Regulator Co. v. Seaboard Surety Co. of New York 204 Cal.App.2d 338 at 344 p. 1061
- A. J. Setting Co. v. Trustees of the California State University & Colleges 119 Cal.App.3d 374 at 381 p. 1061
- Consolidated Electrical Distributors, Inc. v. Kirkham, Chaon & Kirkham, Inc. 18 Cal.App.3d 54 at 60-61 p. 1061
- Globe Indemnity Co. v. Hanify 217 Cal. 721 at 730 p. 1061
- Winick Corp. v. General Insurance Co. of America 187 Cal.App.3d 142 at 146 p. 1062