Majority
Headnote
The provision in a contract for railroad construction that the work shall be executed and performed under the direction of the chief engineer or his assistants, by whose measurements and calculations the quantities and amounts of the several kinds of work performed shall be determined, does not prevent an appeal to the courts in case of fraudulent or unjust conduct of the engineer; and in such case testimony of other experts is allowable.This case has been once tried and appealed to the Court of Appeals. The report of it in that court (Byron v. Low, 109 N. Y. 291 ) contains a statement of the facts. The appellants claim that on this new trial the objection which led to the reversal before has not been obviated. But I am of opinion that the testimony of plaintiff at folios 168 to 172 inclusive makes out aprima facie case of a demand for the certificate from the chief engineer, as required by the contract. Plaintiff’s direct testimony on the former trial on this point is not given, but we scarcely think appellants’ contention, that it was substantially the same as on the present trial, can be correct. His former cross-examination, which was read on this trial, may all stand consistently enough with the direct evidence of a demand for the certificate itself which he has now given. There is other evidence from which the jury might have and did conclude that the certificate had been unreasonably refused. The case would, therefore, be analogous to the unwarrantable withholding by an architect from a contractor of a certificate of the completion of his contract. The contractor rqust, as a condition precedent to recovery at law, either produce, the architect’s certificate, or satisfactorily account for its absence. Similarly, in the case at bar, facts were shown from which the jury might infer that the engineer’s certificate was kept back without just cause for an unreasonable length of time. Even under the decision of the court of last resort, therefore, we think the jury were authorized to find that the condition precedent had been complied with, and that plaintiff was not bound to wait longer before
Many of the exceptions to rulings upon the trial we do not deem of any serious consequence. The contract provided that the work should be executed and performed under' the direction of the chief engineer or his assistants, by whose measurements and calculations the quantities and amounts of the several kinds of work performed should be determined. But certainly that could not preclude the testimony of other experts in a suit to enforce plaintiff’s rights. We do not think the contract obliged plaintiff to submit to the chief engineer’s decision and allowance without the right of ap. peal to the court, if the former claimed that he was fraudulently or unjustly dealt with. And if under any circumstances he was entitled to sue, it goes without saving he had the right to call witnesses, such as the assistant engineers Trues dell and Coons, to prove the nature, extent, and value of the work. This exception was not well taken.
Considerable evidence was excepted to because it was alleged to relate to transactions with the original defendant now deceased, but none of such exceptions seem valid. Many of the answers complained of do not as matter of fact relate either to “conversations” or “transactions” with the deceased, and such of tliem as may seem impliedly to do so come within the exception to the rule, made a part of the rule itself by section 829 of the Code. The testimony of the deceased defendant on the former trial was read on behalf of the defense here, and plaintiff, therefore, became entitled to give his version orally of the matters therein referred to.
The rulings as to the testimony o.f said deceased, excluding a considerable portion of it, seem from the printed record rather strict, but they were within the discretion of the trial judge. In the ruling especially complained of, at folios 520, 521, 522, much of the long answer was clearly irresponsive, as the court held, and, moreover, it contained conclusions and calculations.
Nevertheless, we are constrained to hold that the exclusion
“ Q.—What proportion of the 365 51-100 yards of rip-rap wall that Byron has estimated at a dollar and a half a yard —what proportion of it should be at a dollar a yard ? ”
This question was put to Mr. Wood later on and excluded :
“ Q.—From what you saw there on the ground at Indian Ladder Bluff; what amount of rock in your opinion was taken out outside of the slopes as provided for in the contract and specifications ? ” The contract provided that the plaintiff should be paid “ for rock cut at Indian Ladder Bluff one dollar and twenty-five cents per cubic yard,” and a portion of the judgment rendered depends upon the jury’s estimate of how much of such work was actually cut. It must be remembered that the contract did not specify a gross sum for plaintiff’s compensation, but merely rates for different kinds of work; and, therefore, both from the very nature of the agreement, and because directly raised by the answer, the amounts and kinds of work actually performed were at issue. This witness, Mr. Wood, was not only the Chief Engineer of The New York '& Scranton Construction Company, but by the contract itself he was “appointed a common arbiter, to whom all and every question of difference between the parties, growing out of this contract, shall be referred, and whose decision shall be final and binding upon both parties.” Certainly he was a competent expert upon all these matters upon which his testimony was excluded, and such testimony would have been very relevant for the defense. It was as seri
Bookstaver, J., concurred.
Judgment reversed and new trial ordered, with costs to abide event.
Cases cited
- Byron v. Low 109 N. Y. 291 p. 200, p. 201