Grogan v. Mayor of New York

2 E.D. Smith 693 Court Special Term, English

Delivered by Brady, J.

Contents

Majority

p. 693
Thomas Grogan v. The Mayor, Aldermen and Commonalty of the City of New York, owners, and Patrick McAuliffe, contractor.

Headnote

In an action against an owner and a contractor, under the mechanics’ lien law of 1851 and the amendatory act of 1855, it appeared that the work and materials, for which- the plaintiff claimed, did not conform to the original contract—that the deviations therefrom were not directed by the owners, nor, except in part, by their architects—and that the work, &a., had not been accepted by them; held, that no judgment could be rendered against the owners. -
The labor and materials being in pursuance of the employment or agreement between the plaintiff and the original contractor, but not in conformity to the contract with the .owners, judgment was awarded in favor of the latter for their costs of suit, and in favor of the plaintiff, against the contractor only, for the amount claimed with interest.
Special Term,
November, 1856.
Before Brady, J.
In June, 1854, the school officers of the nineteenth ward, in the city of New York, entered into a written contract with the defendant, Patrick McAuliffe, for the erection of an edifice in 51st street, in accordance with certain plans and specifications. In July ensuing, the contractor employed the plaintiff to perform labor and furnish materials in the construction of the building, which he did, to the amount and value of $1,548 66.
For this sum, the claimant filed with the county clerk the notice of claim, provided in the sixth section of the “ act for the better security of mechanics and others,” passed July 11, 1851, and served upon the defendants the notice mentioned in the fourth section, to bring the alleged lien to a close, accompanying the service with a bill of the particulars of the demand.
The plaintiff and the defendants, The Mayor, &c., appeared by attorney, on the return of the notice last mentioned, but tiie defendant, McAuliffe, made default. The usual or
p. 694
der having been entered, the cause proceeded upon complaint and answer, the litigation being conducted by the plaintiff and the corporation only, although the contractor was also, nominally, a party to the proceeding.
Special issues having been framed by consent, the same were directed to be tried by a jury, who found, among other things, as follows: 1. That the work and materials in question were performed and furnished in pursuance of the terms of McAuliffe’s employment of the plaintiff, and were of the amount and value above stated, which amount remained due and unpaid to the plaintiff; but, 2. That the same were not in conformity with the contract between McAuliffe and the school officers ; 3. That-the deviations from the original contract were not by direction of the corporation or their agents, except partially by the architects in the employ of the school officers ; 4. That the plaintiff had not obtained the certificate of the architects, which the contract made a condition precedent to the contractor’s right to receive payment, and that such certificate had not been withheld by fraud, nor waived, except partially by a resolution of the school officers; 5. That in accordance with the direction of the Board of Education, the edifice was taken down, as not erected pursuant to the specifications and requirements of the contract; and, 6. That the board had canceled their appropriation for the construction of the building.
The case now came before the court, at special term, on an application for a judgment or decree upon the verdict.
Chauncey Shaffer, for the plaintiff.
Robert J. Dillon, counsel to the corporation, for the defendants, The Mayor, &c.

Several issues were specially ordered to be tried by a jury in this action, and were so tried. Among other findings, the jury found that the work done and materials furnished by the defendant, McAuliffe, were not done

p. 695
and. furnished in conformity to the contract between the defendants, and that the deviations in the work from such contract were not by the direction of the defendants, The Mayor, &c., except partially by their architects. These findings render it impossible for the plaintiff to succeed.

There are certain facts which must be established to enable a mechanic or material man to recover a judgment against the owner, under the provisions of the act of 1851 and amendment to secure mechanics and others, &c. There must be a contract. The work or materials done or furnished must be in conformity to the contract, unless accepted and objection waived. The defendant must be the owner of the land, upon which the building is erected, partially or otherwise. And there must be something due to the contract- or, or to become due, under the contract.

These are essential prerequisites, and it would be unjust to a defendant owner to dispense with either, but more particularly to hold him responsible to the mechanic or material man if the work done or materials furnished are not and neither of them is in conformity to the contract, and nothing, therefore, due to the contractor. It is true, that this would seem to impose upon the persons named the duty of ascertaining that the materials or work were in conformity to the contract, but the law must make their liens thus acquired by legislative enactment subservient to the owner’s right, between whom and them there is no privity of contract, and to whom they must be strangers. At all events this court has decided the proposition here stated, (Dixon v. La Farge, 1 E. D. Smith, 722,) and it is sustained by every principle of justice.

The plaintiff may suffer, but the defendants, The Mayor, &e., have also suffered by the omission of the defendant, McAuliffe, to perform his contract, and have derived no benefit, apparently, from the labor and materials done and furnished, inasmuch as the building erected was taken down by direction of the Board of Education, because it was not built according to the plans and specifications. Nothing is

p. 696
found due to the contractor, and there is nothing in the case to justify the conclusion that he was entitled to any thing from the defendants, The Mayor, &c. For these reasons judgment must he rendered for the defendants, The Mayor, &c., and against the defendant, McAuliffe, for the sum of $1,548 66, with interest from 19th June, 1855.

Ordered accordingly.