Majority
Headnote
P., together with C. & G., his sureties, gave a bond to the plaintiffs, which, after reciting a written contract of P. and the plaintiffs with B.', and that the plaintiffs and P. jointly owed B. a sum of money thereon, was conditioned that P. should pay that money, or save the plaintiffs harmless, &e. Afterward, B. sued P. and the plaintiffs for the money, who put the cause at issue, suffered an inquest to be taken against them at the circuit; and then the plaintiffs, before judgment, settled with B., giving their negotiable note for the amount of the verdict and B.’s taxable costs, which he received in full satisfaction. Held, that P., not only, but the sureties, were liable on the bond for the amount of the recovery and B.’s taxable costs.There can be no doubt that the proof of the verdict, was admissible, to show the amount of damages. The suit was stopped at that stage by the now plaintiffs giving their note forthe amount, which was taken in full satisfaction and discharge. A negotiable note so given and accepted, is equivalent to the payment of cash. So it would now probably be holden of a note not negotiable; but no objection was taken on this distinction.
The defendants were estopped to deny that Beekman executed the agreement by Webster, his attorney. The agreement was definitely recited in the bond as having been executed by him; and such a recital is primary proof of the verity of the agreement as against the defendants. It also shows that the now plaintiffs properly suffered the verdict in the former suit to.pass against them.
No notice of the former suit was necessary. The condition' of the bond was to pay, or save the plaintiffs harmless. Where parties, principals or sureties, stipulate for an indemnity in this form, a verdict recovered by reason of their default, is at least frima facie, not to say .conclusive evidence against them, though they 'had no notice. (Duffield
I do not go over the cases which sustain the views we take; they were cited in the corase of the argument. Duffield v. Scott is full to the merits of the plaintiffs’ claim; and the technical questions are of common occurrence, and perfectly well settled.
' New trial denied.