Majority
Headnote
The attorney general has authority to bring an action in the name of the People, to restrain a municipal corporation from exercising authority in making a contract, or performing similar acts, not possessed by it under its charter, or by law.It is apparent from the opinion of Justice Ingraham, on the decision of the motion made before him in this case, at special term, for an injunction, and I have also learned from conversation with him on the subject, that he intended to decide for the purpose of the motion, that the attorney general has authority to bring an action in the name of the people, to restrain a municipal corporation from exercising authority in making a contract, or performing similar acts, nof possessed by it under its charter, or by law. He denied .the motion in respect to a restraint to that extent in this case, on the ground- it did not appear that defendants were about to do the acts of that nature stated in the complaint, except upon information and belief, which was not sufficient. This defect existed in the plaintiff’s papers, but it appears to have been supplied by papers introduced by the defendants, and the fact to have escaped the attention of the court. The further papers now produced by the plaintiffs removed this ground of objection.
On this renewal of the motion, in pursuance of the leave given therefor, I shall not examine the question as to the right of the attorney general to bring this action, but shall follow the decision of Justice Ingraham on that point, and allow the plaintiffs an injunction if they have made a case in other respects which calls for such an interposition by the court.
The prayer of the complaint is, that the action of the defendants in passing a resolution directing the Croton aqueduct board to have the gate houses, aqueduct, and their appurtenances, for the new reservoir, constructed by Fairchild, Walker & Co., under the contract made with them the 2d of April, 1858, &c., be adjudged to be without authority and a usurpation of power; and that the defendants be enjoined from passing the resolution or any resolution directing the work to be done by those persons, or any person, except the same be awarded in the ordinary way
It was held by Justice Ingraham, that passing the resolution was a legislative act, and that the defendants could not be enjoined from any legislation they might deem proper; and following that decision, aside from the facts that the resolution has passed and is in force as far as it could be made operative by the defendants, I shall hold that an injunction against the passage of the resolution cannot be granted.
In regard to the residue of the relief sought, that the defendants be enjoined from employing Fairchild, Walker & Co., or any person, to construct the work mentioned in the resolution, and that the defendants be precluded from carrying out the provisions of the resolution, several questions have been raised which must be considered.
The theory of the complaint being, that the defendants are about to carry out the resolution by employing Fair-child, Walker & Co., to do the work without lawful authority, and to the injury of the public, I perceive no reason why any persons should be united with the present plaintiffs or defendants as parties to the action.
Baldwin & Jaycox, to whom as the lowest bidders, in pursuance of due notice inviting proposals, the Croton
Fairchild, Walker & Co., have no interest, legal or equitable, involved in the litigation. So far as their contract for constructing the reservoir, embraces the work in question, it is not sought to be, and will not be, affected by the result of this action. They will be entitled to perform their contract, and to damages if the contract is violated by the defendants. Their rights under their contract are in no way in question to their prejudice; and they have no rights under the resolution directing the Croton acqueduct board to employ them to do the work specified in it. , .
It is claimed by the defendants, that they have the power to give this work to Fairchild, Walker & Co., without any letting or contract, by a three-fourths vote, under sec. 38 of the laws of 1851, chap. 446. That section, after providing that all contracts to be made or let by authority of the common council, for work to be done or supplies to be furnished, shall be made by the appropriate heads of departments, under such regulations as shall be established by the common council, proceeds: “whenever any work is necessary to be done to complete or perfect a particular job, or any supply is needful for any particular purpose, which work and job is to be undertaken or supply furnished for the corporation, and the several parts of said work or supply shall together involve the expenditure of more
Another position of the defendants is, that the work in question is covered by the terms of the contract of Fair-child, Walker & Co., and, therefore, there is no ground for granting an injunction. If the work is within that contract, an injunction against a new employment of those persons and the carrying out of the resolution would certainly be harmless; that fact, however, is not a reason for issuing an injunction. But if the contract of Fairchild, Walker & Co., does not cover that work, the resolution for their employment to do the work was unauthorized, and the carrying out of the resolution by the defendants, or a
It is impossible for the court, and the court ought not if it could, upon this motion to decide precisely how far Fairchild, Walker. & Co., are entitled under the contract to do work which will be in aid of the construction of the gate houses, and other things mentioned in the 27th speci
I think the complaint sufficient as a pleading to warrant the relief demanded to that extent. As a pleading, it sufficiently shows an intention by the defendants, beyond the passing, to carry out or execute the resolution. In regard to a public injury, it shows that according to the bid of Baldwin & Jaycox for the work, there would be a saving to the corporation of New York by letting the work pursuant to the charter, instead of having it done under the contract of Fairchild, Walker & Co., upon a single item of the work of $16,730.
An undertaking must however be executed on the part of the plaintiffs as a condition of granting the injunction, in such sum, and with such sureties, as shall be approved by the court, on one day’s notice to the defendants, and be duly approved and filed.
An injunction is ordered according to this opinion upon such an undertaking being first given within ten days.