p. 84exceed the expense of restoring navigation in either of the other ways. The defendant, in good faith, exercised his judgment and discretion in the premises, and in good faith determined that the best method óf restoring navigation was to cut out of plaintiff’s boat a piece large' enough to enable him to close the gates of the lock. He ordered it done, and it was done, without any want of care in the act of severing the boat; the pieces cut out being just long enough to allow the gates to be closed. The injury done to the boat was no greater than the act necessarilyinvolved. Every day’s delay in restoring navigation caused great damage to the State and to persons navigating the canal. The plaintiff’s boat grounded in the gates of the lock, without any fault or negligence on the part of the plaintiff or his servants or agents; he was not notified to remove the boat, and no time nor opportunity was given him to do so. Ho evidence was given on the trial that at or prior to-the time defendant commenced cutting up the boat the plaintiff, or his servants or agents, had commenced removing it from between the lock-gates or had taken any steps to do so, or that when defendant commenced removing it they designed to or would do so. The defendant, at the close of plaintiff’s testimony, moved for a non-suit, and again at the close of the evidence. The motions were denied, defendant each time excepting. The referee assessed plaintiff’s damages at $1,500 and interest from the time of cutting up the boat. As conclusion of law, he held defendant hable, to which he excepted, and on the entry of judgment appealed therefrom to this court.
N. C. Moak, for the appellant.
Isaac Lawson, for the respondent.
Present — Miller, Ingalls and Peckham, JJ.
By the Court
It was the duty of the defendant, as superintendent of repairs on the Erie canal, to remove obstructions which hindered or prevented navigation thereon.
p. 85(Adsit v. Brady, 4 Hill, 630 ; Fulton Fire Insurance Co. v. Baldwin, 37 N. Y., 648 .) It was not only made his duty by law, but he was expressly instructed by the canal commissioners to discharge that duty. The referee finds that the defendant acted in good faith in all that he did, and the injury to the plaintiff’s property was no greater than the act necessarily involved. The defendant properly determined in regard to the necessity and propriety of removing the defendant’s boat as an obstruction, and can only be held responsible upon the ground that he was chargeable with negligence, or improper conduct in executing the work. The right of an individual in regard to his property should be respected; and even public officers are not at liberty to disregard such rights, unless there is a clear and urgent necessity therefor, to subserve an important and pressing public necessity. Mere convenience on the part of the public in regard to the mode to be adopted in accomplishing a result, would not, in my judgment, create such a necessity as would justify a material injury to, or destruction of, the property of an individual. Certainly not, if any other legitimate mode could be resorted to, and produce the same result, without serious injury to public interests. In other words, there must exist a pressing necessity, both in regard to the work to be performed, and the manner in which it should be executed, to justify such an act. No other rule would be safe, or furnish adequate protection to the citizen, against the encroachment of superior power. It is not pretended that the plaintiff was guilty of negligence, or improper conduct, in the management of his boat. The question therefore, presented for the determination of the referee was, whether, in view of all the circumstances, it was necessary for the defendant to destroy the plaintiff’s boat, in order to remove it, as an obstruction to navigation. In determining this question, it became necessary for him to ascertain, from the evidence, whether the defendant could not reasonably have adopted some other method to accomplish the same result, and thereby avoided doing the plaintiff such serious injury. If the defendant could have repaired the breach occasioned
p. 86by the- water,- by a resort to c/rdmary means, and thereby continued navigation, without material interruption, or serious detriment.to..the public welfare, it certainly was his - duty to -have done, so, instead of adopting this eosbraordwia/ry measure, so fraught with injury to the plaintiff. The evidence discloses, and the referee has.found, that there were several methods by which the obstruction could have been removed, and the -difficulty obviated, which were brought to the attention of-the defendant. before he entered upon the work. ■ One was, by constructing a coffer dam in the basin of the canal, around the stem of the boat, and raising the water so as to float the boat, which could -have .been accomplished in two or • three days, at an expense of $900, and $250 or $300 to remove the dam. .. Another was, to repair the banks of the dry dock, • which could have been done in two days. Another, by damming, up the culvert, -and thereby raising the water so as to. float the boat and close the gates. It appears, that from eight to ten hours were expended in cutting the boat, and about twelve hours to restore.navigation,-and plaintiff was damaged to.the extent of $1,500. . There is .considerable evidence, bearing upon the feasibility of the several methods. In my opinion, a fair question of fact was presented for the determination of the referee, whether, in • view of all the circumstances, the defendant .exercised reasonable .prudence in executing the work, in .question; whether he was justifiable in pursuing an extraordinary, rather than an ordinary method, in removing .the obstruction. .The evidence shows pretty clearly that, with possibly some "additional delay and expense, the work could have , been accomplished, and the plaintiff’s property preserved. Is it just or reasonable to- conclude in this case, that there existed, what Senator Sherman, in his opinion in Russel v. The Mayor, &c., of New York ( 2 Denio, 475 ), denominated “ an.overruling necessity,” which justified the sacrifice, of the .plaintiff’s property ? I am of opinion that, at least, the evidence does not so far preponderate, in that direction, as to call upon this court to reverse the decision