The owner of a canal boat, in the performance of a contract for the carriage of freight, is hound to exercise reasonable diligence and to use ordinary forecast in anticipating an obstruction, and due 'diligence in overcoming it when it arises, and as soon as the obstruction ceases to operate he must exercise diligence in the fulfillment of his contract.We have but little difficulty.with the rules of ■ law governing this case, and but little more in determining the facts after a careful analysis of the evidence given upon the trial. Defendant in the performance of its contract is held to the exercise of reasonable diligence, must use ordinary forecast in anticipating an obstruction, and due diligence in overcoming it when it arises, and as soon as the obstruction ceases to operate it must exercise diligence in the fulfillment of its contract. Bowman v. Teall, 23 Wend. 306 ; Parsons v. Hardy, 14 id. 216; Geismer v. L. S. & M. S. R. Co., 102 N. Y. 570 .
A freezing of the.canal is such an act of intervention of the vis mayor as will excuse performance until the obstruction be removed. So,- too, the existence of conditions produced without the fault of the carrier, and attributable, to accident or misfortune, excuses delay in transportation. And if such conditions arise as to render further progress so difficult and dangerous that a person exercising ordinary care, prudence and forecast would deem it unsafe, then the carrier will be exonerated from failure to proceed, and can justify his act. in selecting a place of safety and remaining there. But in each of these cases he must justify his delay by.proof of conditions which bring him within the protection of the rule invoked, and upon him rests the burden of establishing the sufficiency of his excuse. Read v. Spaulding, 30 N. Y. 642 .; Bostwick v. B. & O. R. R. Co., 45 id. 717 .
Upon the application of these rules this case is to be -determined. So far as there was delay in obtaining a load for the boats before the twenty-ninth of November it may be dismissed, except in so far as it furnished a sufficient excuse,
. and showed necessity for going upon the dry dock at Lock-port. And it may be considered unfortunate, for had there not been this delay of nine hours defendant would doubtless have seen its way clear for proceeding; But the fact - cannot be considered as controlling, for defendant chose, notwith•'standing the delay, to accept the cargo and. enter upon its transportation. It is quite clear that when the charter was
So far as tne fact ox navigation is concerned tms. testimony is without dispute. Upon the subject of temperature it is contradicted by a large number of witnesses. But in this respect it receives certain corroboration from -the weather reports, which must be accepted as the fact. These show that on Sunday, the twenty-ninth, it was ten degrees . above zero about daylight at Buffalo, and rose. to twenty - about two o’clock in the afternoon, dropping to fourteen degrees during the night and morning of the thirtieth, and raising to thirty-four degrees at eight in the morning. On the first of December, at eight in the evening, it was forty-two degrees above at Buffalo, thirty-four degrees at Oswego, and between those two points at Rochester. On' the second it was forty-four at Buffalo and Oswego at eight p. m. The third it was fifty-four degrees at Buffalo, forty-six degrees at OsWego and forty-two degrees at Albany. The fifth, Buffalo, thirty-eight degrees; Oswego, thirty-six; Albany, forty degrees. The sixth, Buffalo, thirty-four degrees; Albany, fifty degrees. It thus conclusively appears that from eight p. m. of November ' thirtieth" up to and including .the sixth day of December the temperature was above freezing, and no ice could form. It ‘ is idle to urge the acceptance of recollection of witnesses that ice formed during this period, when the certain record shows that such could not be the case. We thus have the fact that when McCormick tied up his boats at Rochester the temperature was between forty-two and thirty-four degrees, and boats were in fact running both east and west, and that with but slight obstruction. From Rochester to the Hudson river is two hundred and fifty-two miles; the rate of speed necessary to-have .reached the river by midnight of the fifth of December was only two and one-half miles an hour,- and when extended
McCormick made no effort to find out what the condition of the canal was east prior to the time he tied up. He simply acted upon the determination, which he said he had already formed before he reached Rochester, of stopping there. After he had stopped he made an inquiry of the boat which came from the east, and was informed that conditions were bad. This undoubtedly was true in a measure, for it was a late and bad time of year. But he knew from this circumstance that this boat had made a channel and the temperature was such that no ice could form and that he could go ahead; he concluded, however, to wait, remained on his boat and prosecuted no further inquiries to determine what he ought to do. The next morning he learned from the papers that it would he warmer, telegraphed the ■ superintendent of the canals asking when the canal would close, and made an inquiry of the division superintendent about the canal east. This superintendent’s division was No. 9, extend
It is suggested that at Rochester was a good bottom and an
If we could see that it was proper for defendant to stop on .Tuesday night, the conditions existing at an early hour of Wednesday morning showed necessity for farther progress in the fulfillment of the contract, and he then had time for performance. McCormick could have known,'by the exercise of diligence, the actual condition of the canal not later than ten o’clock of Wednesday. He then had left eighty-six hours to reach the river at midnight of the fifth; this would have made a running time of two and eighty-six one-hundredths miles an hour. By adding fourteen hours, the time when the last boat passed through, it would "have reduced his time to two and fifty-two one-hundredths miles an hour. Either of these rates of speed was clearly within the capacity of the boat upon defendant’s . showing. Starting at this time, he had before him a free canal and could proceed' without any delay at locks, and, according to the custom of the canal, in entering upon the last level the boat would be let out, still further adding to the certainty of getting through. We are, therefore, convinced that defendant has not made a case showing the use of that diligence which it contracted to exercise, and is, therefore, liable for the damages sustained. The damage is measured by the difference in the contract price and the increased cost of transportation in .order to procure the delivery of the property at its destination (Ogden v. Marshall, 8 N. Y. 340 ; Briggs v. N. Y. C. Co., 28 Barb. 515 ; 3 Suth. Dam. 213), and for such further increased expense as was necessarily incurred as a consequence of the delay. Farwell v. Davis, 66 Barb. 73 ; 3 Suth. Dam. 226. It also became the right of plaintiffs, under these circumstances, to retake possession of the grain and forward the same to its destination. Laurent v. Vaughn, 30 Vt. 90 .
As the fulfillment of the contract determined the right of defendant to demand freight money, so its negligence in
Judgment is, therefore, ordered in favor of plaintiffs in accordance with this opinion.
Judgment for plaintiffs.