Majority
Headnote
Party wall — partial demolition — either owner may erect new wall on his own premises in space formerly occupied by party wall — injunction denied.This is an application for an injunction pendente lite. The plaintiff and defendant are the owners of adjoining properties situated on West Thirty-fifth street, near Eighth avenue, in the borough of Manhattan. On their mutual dividing line, and located partly on the premises of each, stands a party wall from eight to twelve inches in thickness which is now the west wall of the building on the plaintiff’s lot. The history of its origin is not disclosed. The building formerly on the defendant’s lot, of which this party wall was the east wall, was torn down a number of years ago and the defendant is now engaged in erecting
A party wall which has fallen into a thoroughly ruinous condition may be rebuilt, if one or both of the buildings still remain standing (Campbell v. Mesier, 4 Johns. Ch. .334; Partridge, v. Gilbert, 15 N. Y. 601 ), but if both the wall and the buildings have been wholly destroyed the easement has perished also. Heartt v. Kruger, 121 N. Y. 386 . It has also been settled that if one of the owners carries the wall several stories higher, the other party has no right to complain, provided the method of construction does not weaken the wall or otherwise injure the other party and the latter has an equal right to use the addition. Brooks v. Curtis,
As to that portion of the wall taken down at the commencement of the present operations, the defendant, as already stated, promised to rebuild. The precise agreement is set forth in a letter quoted in defendant’s affidavits, and not denied by the plaintiff, as follows: “ As further understood, we are to take down the upper portion of the party wall where it extends dangerously above the roof and replace same when we carry up our wall, making it a part of our wall, which will make it much stronger than it was before.” It is a fair construction of this agreement that though the wall is to be rebuilt as part of the wall of the defendant’s building, it must nevertheless be serviceable for the plaintiff’s use. The plans and affidavits leave it in doubt whether this is the defendant’s intention or whether they intend even at this point to hang more than a thin masonry curtain on the steel frame. The plaintiff is entitled to protection in this respect. It is also far from clear whether certain flues have been improperly closed up and whether the wall has been adequately bonded to the steel columns. The plaintiff, however, will not be injured by the continuance of the present condition pending the trial, when the rights of the parties will fully appear. The temporary structure in front of a few feet of plaintiff’s premises seems to be in part a bridge approach required by the city ordinances, and in part shoring and underpinning consented to by plaintiff. Damages suffered through alleged negligent blasting and dropping of bricks during removal of the old wall are not under consideration on this motion.
The defendants will be enjoined pending the action from rebuilding that part of the old wall which was torn down by them in any way except in such manner that it can be used by the plaintiff as a party wall, and from doing anything which will interfere with such manner of rebuilding, and also from resting on top of the party wall any part of the new building which is not also capable of use as a party wall. In all other respects the motion is denied. Settle order on notice, and submit memoranda on amount of bond.
Ordered accordingly.
Cases cited
- Bull v. Burton 227 N. Y. 101 at 107 p. 180, p. 181
- Partridge v. Gilbert 15 N. Y. 601 p. 180
- Heartt v. Kruger 121 N. Y. 386 p. 180
- Brooks v. Curtis 50 N. Y. 639 p. 181
- O'Neil v. Van Tassel 137 N. Y. 297 p. 181
- Kerwin v. Post 120 App. Div. 179 p. 181