Majority
Headnote
Contracts made under "and in pursuance of the act of 1870 (Chap. 378, Laws of 1870), organizing “ the Buffalo State Asylum for the Insane” for furnishing materials for the construction of buildings, were not abrogated by the provisions in the appropriation bills of 1874 and 1875 (Chap. 333, Laws of 1874, and chap. 364, Laws of 1875) in reference to that institution.In 1870, the legislature passed the act, chapter 378, “ to establish and organize the Buffalo State Asylum for the Insane.” The governor was authorized to appoint, by and with the consent of the senate, ten managers for the asylum who, among other duties, were to procure plans, designs and specifications for the construction of the necessary buildings, and to contract for the construction of the same, provided such plans, designs, specifications, contracts and the terms thereof should be approved by the governor, State engineer and comptroller, and further provided that the managers should not adopt any plans for the buildings, nor alter or change the plans adopted without the assent of the State officers named. In pursuance of the act the governor appointed the managers, and they prepared plans, designs and specifications which were approved by the State officers. The plans provided for a central building, and five connecting male wards upon one side designated A, B, O, D and E, and five female wards upon the other side designated by the same letters, and several out-buildings.'
The managers afterward advertised for bids for furnishing the dimension stone and block work required for the buildings, and for the cutting of the same, and the firm of Peek & Co. were the lowest bidders for such materials and work; and the managers thereupon awarded the contracts for the materials and work to that firm at the prices bid for them, and the contracts were afterward duly and formally executed. From time to time, during the years 1871, 1872, 1873, 1874, 1875, and
The claim was brought to a hearing before the board of claims, and it found, among other things, that Peclr& Co. sustained damages from the breach of the contract on the part of the State, but dismissed the claim on the sole ground that it was barred by the statute of limitations; and whether it was so barred or not is the sole question for our determination.
It is claimed on behalf of the State that the contracts were abrogated by the acts, chapter 323 of the Laws of 1874 and chapter 264 of the Laws of 1875, and that the breach of the contracts was not later than the date of the passage of the last act, which was more than six years before the presentation of the claim to the board of audit. On the other hand, the claimant contends that the breach which gave his assignors a cause of action was not earlier than the 25th day of May, 1876, within six years before the presentation of the claim.
The act, chapter 323 of 1874, appropriated for “ the Buffalo State Asylum for the Insane, to be expended only for the completion of the buildings already commenced, the sum of $150,000.” This provision in no way interfered with the contracts. It simply directed how the money thus appropriated should be used, and in no way worked a repudiation of the contracts. The act also contained the following provision: “ The governor is hereby authorized to appoint two superintending builders to take charge of the following buildings in process of construction, namely: the Buffalo State Asylum for the Insane, the State Reformatory at Elmira, the Hudson River State Hospital for the Insane at Poughkeepsie, and the State Homoeopathic Asylum for the Insane at Middletown, to
This provision did not entirely supersede the managers appointed under the act of 1870, but substituted in their 'stead only so far as concerned the construction of the asylum buildings two superintending builders.- It did not alter the plans for the buildings, nor expressly abrogate or repudiate any contracts which the managers bad entered into for the construction of the buildings. It cannot be inferred from the. language used that the legislature meant to abrogate valid existing contracts, and thus leave the State liable for damages for their breach.
The contracts of Peck & Co. covered only a portion of the material and work required for the buildings, and as the act of 1870 did not require that contracts should be let at a public bidding, this act required that contracts should be so let, and all its language can have full force by confining it to -future contracts. It looked to the future, and did not purport to interfere with what had already been done, with materials already purchased, or valid contracts already made in the very mode it prescribed. Suppose the contracts had been relet at a lower price, the diminished price might at least measure, though not necessarily limit, the damages of Peck & Go. caused by the breach of their contracts, and the State would gain nothing. The construction contended for on behalf of the defendant, so unjust to the contractors, and injurious to the State, should not
That the statute of 1874 cannot be so construed is made more manifest by reference to the act of 1875, which, it is also contended, abrogated the contracts. Section 1 of that act provides as follows: “ The governor is hereby authorized to appoint three building superintendents of practical experience who shall respectively have charge of the construction of the Hudson River State Hospital for the Insane at Poughkeepsie, and the State Homoeopathic Asylum for the Insane at Middletown, and the Buffalo Asylum for -the Insane. The purchasing of the materials, and all things connected with the erection of new buildings, and the labor upon the same shall be done by the managers thereof by contract, and the contracts shall be awarded to the lowest responsible bidders, after being advertised in the State papers, and in at least two papers published in the locality where the work is to be done, once in each week for four weeks consecutively immediately preceding the letting of said work, which notice of letting, to be signed by the managers, shall state the work to be let, the quantity and quality of materials to be bid for, and the length of time which will be given for the completion of the work, or the delivery of the materials, the amount of the security required, bonds to be furnished for the faithful performance of the contracts. Before said work and materials shall be advertised and let by the managers aforesaid, full detailed plans and specifications of said work shall be made and approved of by the lieutenant-governor, attorney-general and comptroller of the State, in writing; and said plans and specifications thus made and approved shall not be altered without the consent and approval, in writing, of the lieutenant-governor, attorney-general and comptroller. The contracts for such labor and materials shall be made by the managers aforesaid after the approval of the lieutenant-governor, attorney-general and comptroller, in writing, indorsed thereon, after having been furnished by the said managers with the bids for said work and materials, which shall be filed by the comptroller in his office.” For the same reasons before
It is a fundamental rule, founded in wisdom and sound public policy, that, unless the very plain meaning of the language requires it, laws should not be so construed as to have retrospective operation, or to affect existing contracts or acts already legally done.
This obvious construction of the two acts is one that all the persons connected with the construction of the buildings understood and acted upon. The managers and superinten ding builders all recognized these contracts as subsisting, and the contractors continued to perform them long after the passage of these acts; and it does not appear that any one prior to the hearing of this matter before the board of claims ever claimed that these contracts were abrogated or broken by these acts.
The cases of Lord v. Thomas ( 64 N. Y. 407 ) and Lanolds v. The State (89 id. 36) are in no way in conflict with the views here expressed. They involved the construction and effect, besides the provision above quoted from- the act of 1874, of the following clause therein: “ For the State Reformatory, at Elmira, the sum of $300,000, provided the plans of the building be so changed as to render such sum sufficient to complete the center building and the south wing so as to receive convicts; such change of plans to be approved of and certified
We have reached this conclusion without considering the allegations of the claimant that the State subsequently to 1875 recognized and ratified the contracts as valid and subsisting, and also that it became estopped from denying the validity and continued existence of the contracts subsequently to that time by virtue of the judgment against it in the action brought by it against Peck & Co. to recover back money paid under the Contracts.
We have confined our attention to the one point-«-the statute of limitations — upon which the board of claims based its decision. The case was settled and prepared to present that point alone, and it would not be proper to consider any other
In conclusion, we repeat, as peculiarly applicable to- thicase, what was said in Corkings v. The State ( 99 N. Y. 499 ) :
“ When the State has no better or other defense than the statute of limitations it should at least, both- upon the law and the facts, establish that defense with reasonable clearness and certainty.”
The decision of the board of claims should be reversed, and a new hearing ordered, costs of this court to abide event.
All concur, except Danforth, J., dissenting, and Andrews and Miller, JJ., not voting.
Decision reversed.
Cases cited
- People ex rel. Brisbane v. Zoll 97 N. Y. 203 p. 548
- Delafield v. State 26 Wend. 192 p. 548
- Bank of the United States v. Planters' Bank 9 Wheat. 904 p. 548
- Lord v. Thomas 64 N. Y. 107 p. 548
- Landers v. Frank Street Methodist Episcopal Church 97 N. Y. 119 p. 548
- McDonald v. Mayor of New York 68 N. Y. 23 p. 549