Majority
Headnote
Oh February 2, 1881, the parties entered into a contract, by which plaintiffs sold to defendant about 100 tons old iron “for prompt shipment by sail from Europe and for delivery on dock at the port of New York (dangers of the sea excepted),” the purchase-price to be paid after delivery. On February third, iron answering the description of that contracted for was shipped on board a sailing vessel lying at a port in a river in Germany, about forty miles from the sea. The river was at that time frozen over, it remained closed to navigation until about April third, on which day the vessel sailed, and after a voyage of ordinary length, arrived in New York. On June fourteenth plaintiffs tendered the iron to defendant, who refused to accept. In an action on the contract it appeared that iron of the kind specified could have been obtained at any time at other European ports. Held, that the condition of prompt shipment was a precedent to delivery, and so related to theThis action is for not accepting certain goods according to a contract made through brokers in these words:
“Hew York, Feb. 2d, 1881.
u Sold to Mr. L. Lissberger, Hew York. For account Messrs.
O. Tobias & Go., Hew York.
“ About one hundred (100) tons old iron vignol rails, for prompt shipment by sail from Europe, and for delivery on dock at the port of Hew York (dangers of the sea excepted), at twenty-eight (28) dollars per ton of 2,240 lbs. weight, as per United States weighmaster’s return. Terms of settlement as follows: Eighty (80) per cent cash, payable when rails are
landed on dock, and balance payable on receipt of United States weigher’s certificate.
“ MANN & JONES,
“ Accepted, “ Brokers.
“ L. Lissbebgeb.”
The complaint, after setting out the agreement, alleges “ that the plaintiffs promptly shipped by sail from Europe a lot of about one hundred tons of such rails and duly performed all the conditions of the contract on their part, and on the 14th of June, 1881, were ready and willing to deliver, and duly tendered ” the rails to the defendant, who refused to accept or pay for them; that upon notice to defendant they sold the rails on his account, and after applying the proceeds there remained due $345.15, for which, with interest from June 14, 1881, they ask judgment. The defendant by answer expressly admits the contract, and that on the fourteenth of June the plaintiffs were willing to deliver, and then tendered to him, the rails mentioned in the complaint, a refusal on his part to accept, and that the plaintiffs after notice sold the same ; he denies, however, the other allegations in the complaint, and particularly denies that the goods were promptly shipped from Europe, and says that, on the contrary, there was a delay of two months or thereabouts in such shipment, in consequence of which the goods were of less value in the market than they would have been if promptly shipped; that in this omission the plaintiffs failed to perform the contract on their part, and he, therefore, refused to accept the rails.”
Upon the trial of these issues the plaintiffs read the deposition of the captain of the ship “ Bnirin,” to the effect that his-vessel, then lying at Stettin, in Germany, was chartered on the 1st of January, 1881, for different kinds of goods for New York. Stettin was about forty miles from the sea, situated upon a river. That on the 3d of February, 1881, he received on board from the shippers, Tgnatz Rosenthals, Wie & Companv, 535 pieces of old rails, deliverable in New York, on
It is stated by the respondent that the only question litigated at the trial was whether the goods were promptly shipped according to the terms of the contract, and the record sustains that view. The trial judge, against the exception of the defendant, directed a verdict for the plaintiffs. Upon denying a new trial, he was of opinion that “ prompt shipment,” under the words of the contract, was within the shipment proven, saying also that s< if the defendant wished to provide against a distant .port in Europe, or any other delaying cause, it was in his power to make it part of the contract,” and failing to do this, says: “I think the point he makes cannot be sustained.” But he added: “ I do not put the decision of the case on the grounds above stated, but upon the ground that after the contract, after notice of shipment, the defendant waited until after the arrival here before making the objection now made.” The General Term discusses only the ground first stated by the trial judge, and by a divided court sustained his decision.
The plaintiffs then have sold a quantity of iron, and the -question arises as to how the condition shall be performed which will enable them to make delivery and entitle them to demand payment from the vendee. Ho time is specified, and if there was nothing else in the contract, it would undoubtedly be the duty of the vendors to make delivery of the thing sold within a reasonable time and to determine whether the plaintiff had been able to do so, the facts and circumstances attending the transaction would have to be considered. But although the contract specifies neither month nor day, nor duration of time within which or on which they must perform, it does specify the manner of doing the act which makes performance possible. The contract provides for “ prompt shipment,” and it is this condition on which all other stipulations hang. • So the plaintiffs understood it, and, as we have seen, they alleged as a condition precedent to the right of action that they “ promptly shipped ” the iron. This implies expedition, admits of less delay than would be permitted under a covenant to act merely within a reasonable time, and in effect the plaintiffs interpret it as
In Duncan v. Topham (8 Com. B. 225), the order was for certain goods to be put on board directly. The complaint alleged an order for goods to be delivered within a reasonable time, and the plaintiff failed in his action because the proof did not support the declaration, it being hold that “ a reasonable time ” was a more protracted delay than “ directly.” The contract here goes further.. ' “ Prompt ” is synonomous with “ quick,” “ sudden,” “ precipitate.” Indeed, one who is ready is said to be prepared at the moment, one who is prompt is-said to be prepared beforehand. Such represents the condition of the plaintiffs. Their immediate loading of the vessel shows that they were prepared beforehand, but if their construction of the contract is correct, the qualifying word might as well be one of postponement and delay. The fault, was with the plaintiffs, It was optional with them to ship from any port in Europe, If at the time of shipment the plaintiffs or their agents knew or might have known that detention and delay at the place of shipment and before ground could he broken for the voyage, were unavoidable and to be expected, they must also have known that the delivery could not be made as contracted for, and the subsequent tender was too late'. It was not a “ prompt shipment,” and the defendant was not bound to receive the cargo.
It is now contended, however, by the plaintiffs that, the appellant is estopped from denying that the rails were shipped
"We find nothing in these letters which would authorize a court to say that the defendant had waived performance by the plaintiffs. There is no evidence that he knew the circumstances attending or causing the delay, none that he was informed that the vessel, when loaded, Avas ice-bound, nor of its detention from that cause. Moreover, the sole act relied upon in the complaint as a breach of the contract on defendant’s part, a refusal to accept the rails tendered, took place, as is there alleged, and is admitted in the answer on the fourteenth of J une. Then the plaintiffs say they were ready and willing to deliver, and duly tendered the goods, and the defendant refused to receive them. If I am right in my view of the contract he was under no obligation to do so.
I have not overlooked the argument of the plaintiffs, by which our attention is directed to the difference between “ shipment ” and “ sailing,” nor failed to examine the definitions and decisions upon which the argument is founded.
Another class of cases, also cited by the respondents, shows that when goods are sold and are to be delivered on board of vessels, either provided by the purchaser or by his appointment, putting on board is a good shipment, whether the vessel is in condition or is expected to sail or not. (Fisher v. Minot, 10 Gray, 260 ; Newhall v. Vargas, 13 Me. 93 , 105.) The principle on which these cases were decided is not involved here, and the others do not lessen the strength of the appellant’s case.
The time and manner and place of shipment might, indeed, have been accepted by the defendant as in compliance with the contract, and whether it was or not, and whether with full
It follows that the judgment should be reversed, and a new trial ordered, with costs to abide the event.
All concur, except Huger, Ch. J., dissenting.
Judgment reversed.
Cases cited
- Snyder v. Atlantic Mutual Insurance 95 N. Y. 196 p. 405, p. 406
- Lowber v. Bangs 2 Wall. 728 at 737 p. 405
- Filley v. Pope 115 U. S. 213 at 220 p. 405
- Pope v. Porter 102 N. Y. 366 at 369 p. 405, p. 406
- Hill v. Blake 97 N. Y. 216 at 220 p. 405, p. 406
- Norrington v. Wright 115 U. S. 188 at 203 p. 406
- Bragelman v. Daue 69 N. Y. 69 p. 406
- Elliott v. Rossell 10 Johns. 1 p. 406
- Wheeler v. Connecticut Mutual Life Insurance 82 N. Y. 543 at 551 p. 406
- King v. Gallun 109 U. S. 99 p. 406
- Livingston v. Broeck 16 Johns. 14 p. 406
- Pollard v. Vinton 105 U. S. 7 p. 407
- Harmony v. Bingham 12 N. Y. 99 at 100 p. 407
- Worth v. Edmonds 52 Barb. 40 p. 407
- Parsons v. Hardy 14 Wend. 215 p. 407
- M'Neven v. Livingston 17 Johns. 437 p. 407
- Continental National Bank v. National Bank of the Commonwealth 50 N. Y. 575 at 582 p. 407