Majority
Headnote
Where an executory contract for the sale of goods contains no provision as to the time when delivery is to be made by the vendor, its legal effect is an agreement to deliver within a reasonable time, and in an action brought by him against the purchaser for failure of the latter to perform, where by the terms of the contract payment is to be made upon delivery, plaintiff must allege in his complaint and prove upon the trial performance or offer to perform on his part within a reasonable time.The defendant’s counsel, on the opening of the case, moved to dismiss the complaint on the grounds (1) that it did not allege when the contract was to be performed, and (2) that it did not allege performance, or offer or tender of performance within the time. The court denied the motion and exception was taken. The plaintiffs did not offer to amend the complaint and no amendment was made at any stage of the trial. We think the motion should have been granted. There is no allegation in the complaint as to the time within which the contract was to be performed by delivery of the iron, and no time is mentioned in the written contract. The law supplies the omitted term, and the contract in legal effect was an engagement on the part of the plaintiffs to deliver within a reasonable time. (Benjamin on Sales, § 683, note and cases cited; 2 Pars. on Con. 535, and cases cited.) The promise of the plaintiffs to sell and deliver the iron, and of the defendant to receive and pay therefor were mutual and concurrent and neither party can maintain an action against the other for a breach of the contract without proving performance on his part. It was, therefore, necessary, as matter of proof, that the plaintiff should show that he delivered, or offered to deliver, the iron within a reasonable time, for this was his contract, and whatever is essential to a cause of action must be averred. The principle is very clearly stated in Osborne v. Lawrence ( 9 Wend. 135 ), in which the court say: “The time when a promise is to be performed is always material and must be stated according to the truth, and proved as stated, whether it be upon the request of the plaintiff, or upon a particular day, or in a reasonable time.” The eom
Other questions have been argued, but as the point already considered is decisive of this appeal, it becomes unnecessary to consider them.
The judgment should be reversed, and a new trial ordered.
All concur.
Judgment reversed.
Cases cited
- Osborne v. Lawrence 9 Wend. 135 at 137 p. 63, p. 64, p. 65
- Pope v. Porter 102 N. Y. 366 p. 64
- Norrington v. Wright 115 U. S. 188 p. 64
- Scofield v. Whitelegge 49 N. Y. 259 p. 64
- Pelton v. Ward 3 Cai. 73 p. 64
- Stewart v. Marvel 101 N. Y. 357 p. 64
- Davis v. Talcott 14 Barb. 611 p. 64
- Minor v. Happersett 21 Wall. 162 p. 64
- Harris v. Panama Railroad 58 N. Y. 660 p. 65
- Tooker v. Arnoux 76 N. Y. 397 p. 66