Majority
Headnote
Upon trial of an action on a promissory note a motion for a nonsuit was made on the ground that the note in suit was barred by the statute of limitations. The plaintiff asked leave to amend his complaint by substituting as his cause of action a claim for lumber sold and delivered, which he alleged was the original consideration of the note. An order was thereupon entered, which provided that on payment of certain costs plaintiff have leave to withdraw a juror and move at Special Term for leave to amend his complaint. In case said motion was denied the order provided that the complaint should be dismissed, with costs, “ as moved by the defendant.” A juror was withdrawn, plaintiff made the motion for leave to amend, which was denied and judgment was entered dismissing the complaint. Upon appeal by him the General Term reversed the judgment for error in the rejection of evidence. Defendant appealed to this court, claiming that plaintiff could not review the judgment because he accepted its rendition as one of the conditions of the withdrawal of a juror and the permission granted him to move for an amendment of his complaint. Held, untenable; that the purpose of the order was to give plaintiff an opportunity for his motjon, and if he failed,We do not think that the circumstances of the trial put the plaintiff in the attitude of consenting to the judgment of nonsuit rendered against him, or debar him from , assailing that judgment as erroneous. When the motion was made it seemed likely to be successful upon the ground that the note upon which he sued was barred by the statute of limitations, and the plaintiff thereupon asked leave to amend his complaint by substituting as his cause of action his claim for lumber sold and delivered, which he declared to have been the original consideration of the note. Thereupon an order was
This brings us to the alleged errors in the rejection of competent and material evidence. To appreciate them properly it is necessary to understand the issues presented for trial. The complaint counted upon a note made by defendants to plaintiff’s order, dated November 10, 1877, and alleged that no part thereof had been paid, except the sum of ' $278.11, on or about February 12,1880. The answer denied “ that any sum was ever paid by the defendants, or either of them, as part payment of said note or on account of it.” The denial is’not of the alleged payment of $278.11, but of its
The order of the General Term should be affirmed, with costs, and judgment absolute be entered against the defendant upon 1ns stipulation.
All concur.
Order affirmed and judgment accordingly.
Cases cited
- Bennett v. Van Syckel 18 N. Y. 481 p. 260
- Reese v. Smyth 95 N. Y. 645 p. 260
- Sands v. Codwise 4 Johns. 536 p. 260
- In re Larson 96 N. Y. 381 p. 260
- Briggs v. Waldron 83 N. Y. 582 p. 260
- Boos v. World Mutual Life Insurance 64 N. Y. 236 p. 260
- Tooley v. Bacon 70 N. Y. 34 p. 261
- Miller v. Montgomery 78 N. Y. 282 p. 261
- Blair v. Lynch 105 N. Y. 636 at 640 p. 261
- Murray v. Bethune 1 Wend. 191 p. 261
- Ehle v. Chittenango Bank 24 N. Y. 548 p. 261
- Train v. Holland Purchase Insurance 62 N. Y. 598 p. 261
- United States v. Wilder 13 Wall. 254 p. 261
- Rouse v. Whited 25 N. Y. 170 p. 261
- Smith v. Ryan 66 N. Y. 352 p. 261
- Bell v. Morrison 1 Pet. 351 at 362 p. 262
- Purdy v. Austin 3 Wend. 187 p. 262
- Shepherd v. Thompson 122 U. S. 231 p. 262
- Deyo's Executors v. Jones' Executors 19 Wend. 491 p. 262
- Fort v. Gooding 9 Barb. 371 p. 262
- Scott v. Hickman 112 U. S. 150 p. 262
- Levin v. Russell 42 N. Y. 251 p. 262
- Moran v. New York Central & Hudson River Railroad 67 Barb. 96 p. 262
- Ward v. Kilpatrick 85 N. Y. 413 p. 263
- Murphy v. People 63 N. Y. 590 p. 263
- Coleman v. Manhattan Beach Improvement Co. 94 N. Y. 229 p. 263
- Ryan v. Ward 48 N. Y. 204 p. 263
- Nicolay v. Unger 80 N. Y. 54 at 57 p. 263
- Webb v. Odell 49 N. Y. 583 p. 263
- Keeler v. Salisbury 33 N. Y. 648 at 653 p. 263