Majority
Headnote
Under the provision of the Slew York city consolidation act (§ 1813, chap. 410, Laws of 1882), as amended in 1883 (§ 17, chap. 276, Laws of 1888), in reference to the enforcement of mechanics’ liens, a lien ceases to bind the property after the expiration of ninety days from the time the claim is filed, unless the lienor within that time either commences an action to enforce the lien, and files a notice of pendency of the action, or unless he within that time be made a party to an action to enforce *' any other lien,” and in that action a notice of pendency is filed by him or in his behalf.This action was brought to foreclose a mortgage. The defendant Simonson was made a party defendant, as having or claiming to have some interest in or lien upon the mortgaged premises, which interest or lien, if any, had accrued subsequently to the lien of the mortgage.
The answer interposed alleged, in substance, that the mortgage was executed by the defendant, Andrew Kelly, as a security for money thereafter to be advanced by the plaintiff, under an agreément, in writing, by which Kelly had agreed to erect four buildings upon the premises covered by the mortgage, and that the plaintiff was to advance $8,000 on each of such buildings as they progressed in construction; that the defendant, Simonson, furnished materials for such buildings, at prices agreed upon, and which, in the aggregate, amounted
Hpon the trial it appeared that the defendant’s lien was filed on the ISth/day of April, 1884, and that on the 5th day of September, 1884, no notice of pendency of action to foreclose the lien had been filed. Thereupon the referee ruled out and excluded the evidence. offered by the. defendant, to prove the defenses alleged in his answer, and found as facts that the defendant had not filed any notice of pendency of any action to foreclose his hen within ninety days after the filling of such lien.
The question presented for review is as to whether the claim of the defendant continued a lien upon the premises after the expiration of ninety days from the time it was filed.
The statute in force at the time provided that “no lien provided for in this title shall bind the property therein described for a longer period than ninety days after the claim has been filed, unless an action be commenced within that time to enforce the same and a notice of the pendency of such action filed with the clerk of the county and an entry of the fact of such notice made on the lien docket. And where a claimant is made a party defendant to any action brought to enforce any other lien, the notice of the pendency of such action must be filed by him or in his behalf. But the neglect to file such notice shall not abate any action which may be pending to enforce the lien. Such action may be prosecuted to judgment against the persons liable for the debt.” (Laws of 1882, chap. 410, § 1813, as amended by Laws of 1883, chap. 276.)
The second clause of the section, as we have seen, provides that where a claimant is made a' party defendant to any action brought to enforce any other lien, a notice of the pendency of such action must be filed, etc. Although he appeared in the foreclosure action and answered, he did not file any notice of the pendency of such action. If, therefore, the lien of the mortgage is one within the contemplation of this statute, the defendant’s lien has expired and no longer exists, for he has omitted to comply with the provisions of the statute for continuing the life of his lien. It is contended, however, that the lien referred to in this connection means other mechanics’ liens, and does not include a lien by mortgage; that the word “ other,” appearing in the statute, means the same class or kind previously described; and that, inasmuch as the chapter pertains to mechanics’ liens, that other mechanics’ liens than the defendant’s were the liens referred to; and our attention is called to the case of People v. Richards ( 108 N. Y. 137 -150). In that case the defendant had been convicted of the crime of burglary for violating a sepulcher. The question was as to whether the sepulcher was an erection or an enclosure within the meaning of the Penal Code. The words under construction were “ other erections or enclosures.” It was held in that case that the word “ other ” included things of a similar nature to those already described.
Another case to which our attention is called is.that of Flanagan v. Hollingsworth (2 How. Pr. [N. S.] 391). .The parties were owners of real estate in the same vicinity, which
Were the word “other” the only word to be construed, the former case would have some application, but in construing the provision we must consider that which precedes and follows in order, if possible, to determine the legislative intent. Where a claimant is made a party defendant to any action brought to enforce any other lien a notice of pendency, etc., must be filed. The word “ other ” is preceded by the word “ any ” and, under the rule of Flanagan v. Hollingsworth, we must give each word its appropriate meaning.
The word “ any ” is used in various ways and may convey different meanings." It may mean one or many, each or every. In some instances it means an indefinite number. The connection in which it is used in the statute under consideration appears to us to indicate each and every, and is the same as if the statute read “ any action brought to enforce each and every other lien.” It consequently appears to us that the statute is , broad enough to include a mortgage lien and is not confined to mechanics’ liens.
Again, it does not appear to us that it was the intention to limit the provision to mechanics’ liens. The object of the notice of pendency of action was to give notice to subsequent-purchasers or incumbrancers, and all persons interested, of the nature of the claim, that an action had been commenced upon it and was pending, so that purchasers, incumbrancers and persons having an interest might be warned and placed upon their guard. There is just as much necessity for a notice of pendency to be filed where a foreclosure action is brought as there is when an action is brought to foreclose another mechanics’ lien. The notice of pendency filed by the plaintiff
Concurrence
It is claimed that this statute was construed in the case of McDermott v. McDonald (18 J. & S. 153). In that case the court was construing section 4 of chapter 315 of the Laws of 1878. That section was similar to- the provisions of the first clause of the section we have under consideration; but it did not contain the latter clause, which we are here called upon to construe. It does not, therefore, become a precedent that aids us in this case.
For these reasons the judgment should be affirmed, with costs.
I concur in the result reached by Judge Haight. The statute (Laws of 1882, chap. 410, § 1813, as amended by the Laws of 1883, chap. 276) provides, in effect, that the lien provided for by that act shall not bind the property for a longer period than ninety days after the claim has been filed, unless, first, the lienor commence an action within that time to enforce the same ; or, second, the claimant be made a party defendant in an action brought to enforce any other lien and in which a notice of pendency of such action shall be filed by him, or in his behalf.
This defendant did not commence an action within the prescribed ninety days. Neither was a notice of pendency of
It follows that at the expiration of ninety days his claim ceased to be a lien binding upon the real estate in controversy, and the decision of the referee was, therefore, warranted.
All concur; Parker and Brown, JJ., in result as stated in the opinion of Parker, J.
Judgment affirmed.
Cases cited
- Gildersleeve v. Landon 73 N. Y. 609 p. 330
- McKenna v. Edmundstone 91 N. Y. 231 p. 330
- People v. Richards 108 N. Y. 137 at 147-150 p. 330, p. 333
- Sheridan v. Andrews 49 N. Y. 478 at 481, 482 p. 331