Majority
Headnote
In an action to recover damages for the alleged breach of a contract, the complaint alleged that in August, 1884, the plaintiffs S. and F., with E. and B. as joint contractors, entered into a contract, in writing, with defendant, to construct a tunnel in its quarry for a certain amount per foot; that prior to any breach thereof, E. and B., with consent of defendant and of S. and F., abandoned the work, leaving further performance to the latter, who continued it and received, from time to time, the contract price, as the work progressed; that on January 2, 1885, D., the other plaintiff, became, with the consent of defendant and S. and F., one of the contracting parties, and was substituted in place of E. and B., by formally executing the original contract; that on December 20,1885, plaintiffs, at defendant’s request, consented to a suspension of the work for two weeks; at the end thereof, they presented themselves at the tunnel, and at defendant’s place of business, and offered to resume work under the contract, but defendant would not permit them to do so, and, from day to day thereafter, they notified defendant of their willingness to do so, but the latter would not permit them, and they were compelled to seek other employment. Defendant set up as a defense a default of parties plaintiff, in that E. and B., who were still living, were not joined as plaintiffs. Held, that the connection of E. and B. with the contract and the work was fairly disclosed by the allegations of the complaint; that, under the circumstances, it did not appear that when the action was commenced they had any interest in the contract; but that if there was a defect of parties plaintiff it appeared upon the face of the complaint, and defendant could only object by demurrer, and not having done so, the objectionThe plaintiffs recovered damages in this action for the breach of a contract to construct a tunnel at the defendant’s cement works. The complaint alleges and it appears that on the 15th day of August, 1884, the plaintiffs Sullivan
The complaint alleged that, before any breach thereof, Bradley and Enright, two of the original contractors, with the consent of the defendant and of their two associates before named, abandoned the work on account of ill-health, and left the performance of the contract to their associates, who continued the work and received the contract price per foot from the defendant, from time to túne, as the work was performed. That on January 2, 1885, the plaintiff Daniel Buckley became, with the consent of the defendant and Sullivan and Foley, one of the contracting parties in the place of the other two who, as before stated, had abandoned the work. At this time Buckley was substituted as a party by formally executing the original paper, the defendant assenting thereto. That on the 20th of December, 1885, the plaintiffs, at the request of the defendant, consented to the suspension of the work for two weeks and not longer. That at the expiration of that time the plaintiffs presented themselves at the tunnel and at the defendant’s place of business and offered to resume the work under the contract, but the defendant w'ould not permit them to do so, nor furnish them the necessary materials to continue it. That the plaintiffs after that time, from day to day, continued to hold themselves in readiness to go on with the contract, and signified to the defendant their willingness to do so, but were not-permitted to by the defendant, until at last the plaintiffs were compelled by necessity to seek other employment. That
On the trial, the written contract, as changed by the substitution of Buckley, was produced, and there was no controversy in regard to its execution, delivery or validity. As to the breach alleged by the plaintiffs there was conflicting evidence ; the plaintiffs claiming that the suspension was for two weeks only, while the defendant claimed that no time was specified for resuming the work, or, at all events, it was not to be resumed until the commencement of the other general work upon the quarries, which had been suspended at the same time.
Evidence was given by both parties on this question, and it appeared that on the 18th of December, 1885, the defendant’s agent and the plaintiffs agreed to a temporary suspension of the work on the contract, and the work was accordingly suspended, the plaintiffs having been paid the balance due them for work up to that time. At the same time the general work in the quarries was also suspended and was not fully resumed until on or about the twenty-fifth of January following. After the expiration of the two weeks several conversations took place between the plaintiffs and the defendant’s agent in regard to a resumption of the work under the contract in question ; but the defendant did not, according to the plaintiffs’ version, fix any definite time for resuming work, though the plaintiffs expressed a desire to go on, and negotiations to the same effect continued and were had between the plaintiffs and defendant from time to time without any results, until the 11th of February, 1886, when a letter was addressed by the plaintiffs to the defendant demanding a definite answer whether or not they were to be permitted to perform the contract, stating at the same time that they were ready to complete it on their part, and requesting an immediate reply.
While it may be said that the acts and omissions of the defendant in regard to the contract prior to the eleventh day of February were waived by the plaintiffs’ letter of that date offering,to-go on with the work, had the defendant consented, the question still remains whether the delay in answering the plaintiffs’ letter, or complying with their definite request, was unreasonable; and upon this question the negotiations between the parties prior to the date of the letter, the condition in which the plaintiffs were placed after the suspension, and the fact that in the meantime they sought and obtained employment elsewhere,, as well as the conduct and motives of the defendant, and all the other circumstances were to be considered. If the defendant’s permission to allow the plaintiffs to resume work under the contract was unreasonably withheld or delayed, the- plaintiffs, under the circumstances, had the right
The trial court submitted to the jury the question as to flow long the work was actually to be suspended under the agreement between the plaintiffs and the defendant, and also the question whether the defendant’s delay in omitting to notify the plaintiffs to resume work after request was or was not,' under all the circumstances of the case, unreasonable, instructing them that if, in their opinion, the delay on the part of the defendant was unreasonable, then a breach of the contract was established.
We think the verdict of the jury must be taken as a determination of this question in favor of the plaintiffs. It is true that reasonable time, or, as in this case, whether the delay was reasonable or not, is generally a question of law. But that is so only when the facts are clearly established, or are undisputed or admitted. If the facts are not clearly established, or if the question of time depends upon other controverted facts, or where the motives of a party enter into the question, it must necessarily be submitted to the jury as a question of fact. (Mead v. Parker. 111 N. Y. 262 ; Lawrence v. Ocean Ins. Co., 11 Johns. 241 ; 2 Parsons on Cont. 662; Howe v. Huntington, 15 Me. 354 ; Hill v. Hobart, 16 id. 104; Greene v. Dingley, 24 id. 131; Coder v. F. H. & F. M. Co., 3 Sum. 530; Ellis v. Thompson, 3 M. & W. 445.)
We think the evidence in this case as to the period of time during which the work was to be suspended by agreement of the parties, as well as that bearing upon the omission of the defendant to notify or permit the plaintiffs to resume the work upon which allegation a breach of the contract was sought to be established, was properly submitted to the jury.
As to the nonjoinder of Enright and Bradley, as parties plaintiff, their connection with the contract and the work,
The defect, if any, appeared upon the face of the complaint, and, therefore, the defendant could make the objection only by demurrer. Hot having done so the objection is waived. (Code, §§ 488, 498, 499.)
It is urged on the part of the defendant that, inasmuch as the complaint did not state that these two persons were living at the time of the commencement of the action, a demurrer was not proper and could not be sustained. We think that it was not necessary that the complaint should affirmatively show that the parties were living at the commencement of the action in order to make the complaint demurrable. All the other facts sufficient to warrant a demurrer appearing on the face of the complaint and the objection having been made by reason of a nonjoinder of parties plaintiff, the usual presumption of life applies for this purpose. (Burgess v. Abbott,
We have examined the exceptions taken by the defendant on the .trial and to the charge of the court, and are of opinion that none of them .are tenable.
The judgment should be affirmed.
All concur.
Judgment affirmed.
Cases cited
- Viele v. Troy & Boston Rail Road 21 Barb. 381 p. 349
- Viele v. Troy & Boston Railroad 20 N. Y. 184 p. 349
- Barney v. Loper 16 Barb. 629 p. 350
- McKnight v. Dunlop 5 N. Y. 537 p. 350
- Rodermund v. Clark 46 N. Y. 354 p. 350
- Davison v. Associates of Jersey Co. 71 N. Y. 333 p. 350
- Parr v. Village of Greenbush 112 N. Y. 246 p. 350
- Cythe v. La Fontain 51 Barb. 186 p. 350
- Smoot's Case 15 Wall. 36 p. 350
- Allamon v. Mayor of Albany 43 Barb. 33 p. 350
- Smith v. Brady 17 N. Y. 173 p. 350
- Coe v. Hobby 72 N. Y. 141 p. 350
- Kuhn v. Stevens 36 How. Pr. 275 p. 350
- Phœnix Bank v. Donnell 40 N. Y. 410 p. 350
- Brainard v. Jones 11 How. Pr. 569 p. 350
- Merritt v. Walsh 32 N. Y. 685 p. 350
- Dubois v. Delaware & Hudson Canal Co. 4 Wend. 285 p. 350, p. 351
- Taylor v. Bradley 39 N. Y. 129 at 144 p. 350
- Kipp & Brown v. Wiles 3 Sandf. 585 p. 350
- Glacius v. Black 50 N. Y. 145 at 149 p. 351
- Moody v. Osgood 54 N. Y. 488 at 495 p. 351
- Zabriskie v. Smith 13 N. Y. 322 at 336, 337 p. 351, p. 357
- Eaton v. Balcom 33 How. Pr. 80 p. 351, p. 357
- Sanders v. Village of Yonkers 63 N. Y. 489 at 493 p. 351
- Green v. Lippincott 53 How. Pr. 33 p. 351
- Patchin v. Peck 38 N. Y. 39 p. 351
- Allen v. Crofoot 7 Cow. 48 p. 351
- Delacroix v. Bulkley 13 Wend. 71 at 75 p. 351
- Jewell v. Schroeppel 4 Cow. 564 p. 351
- Devlin v. Mayor of New York 63 N. Y. 8 at 25 p. 351
- Lawrence v. Ocean Insurance 11 Johns. 241 p. 355