Majority
Headnote
The parties entered into a contract for the doing of certain work by plaintiff for defendants, the contract price ($8,500) to be paid in installments ■as the work progressed. The contract contained a provision that before plaintiff could demand any payment, he should obtain a certificate of the architect named. In an action brought to recover a balance alleged to be due upon the contract, the complaint alleged that the provisions therein relating to the certificate, were inserted by mistake, and asked to have the contract reformed in this respect and to recover the balance due. Plaintiff noticed the action for trial at Special Term as an equity action; defendants claiming a jury trial, moved that the case be stricken from the Special Term calendar, and, unon their stipulation that it might be tried by j ury with the same effect, so far as the reformation of the contract was concerned, as if tried at an equity term, the motion was granted, and subsequently the case was moved for trial at Circuit. Upon the trial defendants’ counsel stated that there was no necessity for any reformation of the contract and the trial proceeded on the merits; plaintiff offered evidence bearing upon the issue as to the reformation of the contract, but upon the objection of defendants’ counsel, it was excluded. EM, that no question as to the architect’s certificate could be raised on appeal; that so much of the contract as lias reference thereto must be deemed to have been stricken therefrom.In June, 1881, the plaintiff entered into a written contract with the defendants to excavate and remove the earth and boulders from certain lots in the city of FTew York, upon which they were to erect a building. It was provided in the contract that they should pay him $3,500 for the work, in payments as it progressed. It was also provided that before he could demand any payment he should obtain the certificate of the architect employed by them, tie entered upon the execution .of the contract, and during the progress of the work, received from them $900. After their refusal to pay him the balance of the contract price he brought this action to recover the same.. He alleged in his complaint that all the portions of the contract relating to the certificate of the architect were inserted therein by mistake, and, besides other relief, he prayed that the contract should be reformed by striking therefrom so much as related to the architect’s certificate. The answer put in issue all the material allegations of the complaint, and the plaintiff noticed the action for trial at a Special Term as an equity action. At that term the defendants appeared, and, claiming a jury trial, moved that the case be stricken from the Special Term calendar; and upon their stipulation that it ipight be tried at a Circuit before a jury with the same effect as if tried at an equity term of the court as to the reformation of the contract, the court ordered the case to be stricken from the calendar ;■ and it was thereafter moved for trial at a Circuit Court, and at the commencement of the trial plaintiff’s comisel handed to the. court the stipulation just referred to. Thereupon the defendants’ counsel stated as follows: “ That he claimed in this action that the issues in the case were triable
Upon the trial the plaintiff offered evidence bearing upon the issue as to the reformation of the contract, and the defendants’ counsel objected to such evidence, and, upon his objection, it was excluded, and no evidence was received bearing upon that issue. The trial proceeded, and it was undisputed that the plaintiff had been paid only $900, and the jury awarded hiña a verdict for $2,000 besides. interest. Judgment upon the verdict having been affirmed, the defendants have brought this appeal, and they now claim, among other things, that the plaintiff was not entitled to payment without the production to them of the architect’s certificate, as required in the contract as originally drawn.
We think the counsel for the plaintiff is right in his claim that that portion of the contract requiring the production of the certificates must be deemed to have been stricken from the contract, and thus that the contract was reformed in reference thereto. We think that is the plain purport and effect of the stipulation given at the commencement of the trial, and that it was so understood by the defendants’ counsel when, upon Ms objection, all the evidence offered on the part of the plamtiff upon the issue as to 'the reformation of the contract was excluded by the court. After what took place upon the trial, it would be extremely unjust now to hold that the plaintiff was bound by so much of the contract as he claimed was inserted
Thus the only issue to be tried at the Circuit was, whether the plaintiff had performed his contract. Upon that issue, the plaintiff gave evidence tending to show that he had performed his contract, and that the defendants promised to pay him the balance of the contract price. The defendants gave evidence tending to show that he had not performed liis contract, and that they had been obliged to expend considerable sums of money to complete the work which he had contracted to do ; and the trial judge charged the jury that, if he had not substantially performed Ms contract, he could not recover the balance of the contract price; but that, .if he had substantially performed the contract, although a small and unimportant portion thereof remained to be performed, he could recover the balance of the contract price less the expense of performing the portion left unperformed by him. There was no exception to the rule of law thus laid down, and there could be no valid exception thereto. (Glacius v. Black, 50 N. Y. 145 ; Heckmann v. Pickney, 81 id. 211 ; Nolan v. Whitney, 88 id. 648 ; Whelan v. Ansonia Clock Co., 97 id. 293 .)
It is true that the jury apparently allowed the defendants $600 for the expense of doing work which the plaintiff was bound, under his contract, to do; and if it had appeared upon the trial, without dispute, that such a substantial portion' of the work remained undone, and the objection had been- props erly taken, it may well be that the plaintiff could not have recovered upon the theory of a substantial performance. But there is no exception which now presents the point to us. There was proof upon the trial tending to show substantial performance. The proper rule of law was laid down to the jury, and there is no exception wliicli we can consider upon wMch the defendants can claim that the judgment should now be reversed because there was not substantial performance. The trial judge could have set aside the verdict, because- the jury either misconceived the facts or his instructions upon the law. But this court reviews only exceptions pointing out errors.
There was still another groirnd upon which the plaintiff could have been excused from complete performance in case the performance was in fact incomplete. The contract required the defendants to make the plaintiff payments as the work progressed. After he had received the $900 and had earned, as the jury have found, $2,000 more, he asked the defendants for some more money, and they promised to pay him $1,500, and afterward refused to pay him anything, and thus there was a breach of contract on their part. This took place before the plaintiff abandoned work upon the contract. This breach of contract on the part of the defendants would have justified a refusal on the part of the plaintiff to proceed further with the contract and warrants a recovery for the work done.
So, if we treat the contract as reformed and all therein contained requiring the architect’s certificate as stricken out, there can be no ground for saying, upon the evidence in the case, that the jury could not properly render the verdict which they gave the plaintiff.
But we reach the same result if we regard the requirements of the architect’s certificate as still in the contract. Then the plaintiff was entitled to the certificates from time to time as the work progressed and as payments became due from the defendants, and after, as the jury have found, there was $2,000 due him in addition to the $900 which he had received, he
There was also evidence tending to show that the defendants waived the production of the architect’s certificate. After the plaintiff claimed that he had substantially performed the contract they promised to pay him $1,500 and the balance at a future time, and they made no requirment whatever that the architect’s certificate should be produced.
The objection on the part of the defendants that the complaint was not sufficient is a very technical one, as the real merits of the entire controversy between the parties were litigated ; and manifestly no harm came to the defendants from any imperfection in the complaint. A technical answer, therefore,, to the objection is justifiable, and that is, that no proper or sufficient objection was taken to the form or substance of the complaint at the trial, and it must, therefore, be deemed sufficient to justify all the evidence given. There was undoubtedly a sharp conflict in the evidence, but the verdict of the jury settled that, and concludes us as to the facts.
There are some minor exceptions appearing in the record which require no particular notice.
We see no reason to doubt that substantial justice was done by the verdict, and the judgment should be affirmed with costs.
All concur.
Judgment affirmed..
Cases cited
- Hay v. Star Fire Insurance 77 N. Y. 235 at 240 p. 383
- Dwight v. Germania Life Insurance 103 N. Y. 341 p. 384
- United States v. Robeson 9 Pet. 319 at 326 p. 384
- Newton v. Pope 1 Cow. 109 p. 384
- Tooker v. Arnoux 76 N. Y 397 p. 385
- Nolan v. Whitney 88 N. Y. 648 at 650 p. 385, p. 386
- St. John v. Northrup 23 Barb. 25 p. 385
- Wall v. Buffalo Water Works Co. 18 N. Y. 119 p. 385
- Balcom v. Woodruff 7 Barb. 13 p. 385
- McGrane v. Mayor of New York 19 How. Pr. 144 p. 385
- Harris v. Tumbridge 83 N. Y. 92 p. 385
- Smith v. Holland 61 Barb. 333 p. 385
- Bowdoin v. Coleman 3 Abb. Pr. 431 p. 385
- Harrower v. Heath 19 Barb. 331 p. 385
- Dauchy v. Tyler 15 How. Pr. 399 p. 385
- Glacius v. Black 50 N. Y. 145 p. 388