Majority
Headnote
Assessment for Local Improvement — City of Buffalo — Park Paving — Connecting Streets. An assessment for paving a part of the park, under contract from the park department, in the city of Buffalo, where the park department has exclusive power to pave roads and places in the park, while the common council is in charge of streets outside the park, is not invalidated by the fact that it includes work upon streets outside the park necessary to complete the paving in the park and to furnish it with proper drainage, and to make the connecting streets and approaches safe for travelers.Under the view we take of this case a brief statement of the facts will answer the purpose.
The charter of the city of Buffalo confers upon the ¡Dark department the exclusive power to pave, re-pave and repair park roads and places.
The board of park commissioners are the governing head of this department.
The common" council is in charge of the city streets outside of the park.
A certain part of the park is known as the Circle, and is a large circular place; one of the park approaches is Porter avenue ending in the Circle; Pennsylvania street is a public
In October, 1889, the city of Buffalo, by the park commissioners, entered into a contract with the Barber Asphalt Paving Company to pave the Circle with Trinidad asphalt pavement in compliance with specifications annexed and the profile in the park commissioners’ office, agreeing to pay therefor the sum of $10,425.00. The profile referred to disclosed the fact that as a part of the work necessary to pave the Circle there was certain outside work to be done in Wadsworth street, Pennsylvania street and Porter avenue.
The work under this contract was duly performed.
The findings disclose that the total assessment on the property of plaintiff Kittinger was $404.38, and on property of plaintiff Wing $246.80, it appearing that only one-half of the total expense could be assessed on the adjacent property.
It is insisted by appellants that this assessment is void, as the park commissioners were without authority of law to contract for the work outside of the Circle.
The court below determined to correct the assessment and affirm it as corrected.
It was found that for the outside work there was assessed on the property of the p aintiff Kittinger the sum of $57.02, and on the property of the plaintiff Wing the sum of $34.80.
Judgment was rendered reducing the respective assessments of the plaintiffs by these amounts, and awarding them costs against the city of Buffalo in the sum of $209.72.
This judgment was affirmed .by the General Term of the Superior Court of Buffalo, with costs.
The appellants now insist that the original assessment was void by reason- of the outside work, and that the trial court had no authority to correct it and to adjudge it to stand as corrected.
The view we take of this case renders it unnecessary for us to consider the question whether the trial court could correct the assessment, and, in doing so, whether it adopted the proper rule in computing the amount of reduction.
It is also found by the thirty-first finding as follows: “ That the pavement of the Circle under and in pursuance of the said contract with said Barber Asphalt Pavement Company was a, benefit and not an injury to the plaintiffs.”
The evidence is not returned on this appeal; there are no-exceptions to these findings, and they must be regarded as containing the facts of this case.
It seems to us quite apparent and very reasonable that a certain amount of outside work was not only proper, but absolutely necessary, in paving the Circle, which was entered by various streets leading in from the city.
We have the express finding to that effect, and it must be-deemed conclusive.
It requires no citation of authority to - justify this small amount of outside work in order to make the connecting-streets and park approaches safe and free from danger to travelers, but a similar question, was presented to this court in a. case where the plaintiff sought to recover back an assessment paid under protest for grading a certain street in the city of' Albany on the ground, among others, that the assessment was-void, for the reason that drains had been constructed outside of the street lines in order to carry water under the embankments, but it was held that this did not invalidate the assessment, as the outside work was essential to the proper grading; of the street. (Moore v. City of Albany, 98 N. Y. 396 .)
We hold that the original assessment was valid, and that the
The judgment appealed from should be affirmed, with costs.
All concur, except Haight, J., not voting.
Judgment affirmed.
Cases cited
- In re the Second Avenue Methodist Episcopal Church to Vacate an Assessment 66 N. Y. 395 p. 333
- Folmsbee v. City of Amsterdam 142 N. Y. 118 p. 333
- Merritt v. Village of Portchester 71 N. Y. 309 p. 333
- In re the New York Protestant Episcopal Public School 75 N. Y. 324 p. 333
- Moore v. City of Albany 98 N. Y. 396 p. 334, p. 336
- Lewis v. City of Utica 67 Barb. 456 p. 334
- In re Schell 76 N. Y. 432 p. 334
- Hooper v. McCulloch 109 N. Y. 609 p. 334
- In re the Mutual Life Insurance 89 N. Y. 530 p. 334