Majority
Headnote
A sum specifically named, in a written agreement “ as liquidated damages," in case either party should fail to perform the contract, must nevertheless he construed as a penalty, where, upon the face of the instrument, it appears that such sum will necessarily be an inadequate compensation for the bre&ch of some of the provisions and more than enough for the breach of others.According to the just rules of construction, the sum of $500 was intended as liquidated damages for a total and entire non-performance of all the stipulations of the contract, on either side j and a total or partial breach iof either of the stipulations, on the part of the defendant, is not within the intendment of that clause. The agreement does not say that a breach of each or either of the stipulations shall be visited with $500 liquidated damages,
But, if this agreement were susceptible of the construction that a partial failure of either stipulation of the contract would forfeit the $500 as liquidated damages, then the case could not be construed as one of liquidated damages, because one of the stipulations is that the defendant is to give his own note for the payment of $200. It is fully settled that where a large sum is agreed to be paid, in default of paying a smaller sum agreed to be paid by the same instrument, then the larger sum is a penalty, although the instrument denominates it liquidated damages.
But the judgment should be affirmed on the ground first mentioned, viz., that although the damages are liquidated, vet it does not arise or accrue in this case, because the -defendant partially performed one of the stipulations of the contract, whereas the contract provides only for an entire non-performance.
The case in which, according to the terms jf their contract, $500, as liquidated damages, are to be paid by one party to the other, arises if either party shall fail to perform the contract according to the instrument; and either party has failed if he has so conducted, in respect to the performance of the contract, that the other party can maintain an action against him for non-performance according to the terms of the instrument. Any breach which can be assigned will make out a failure to perform. If the damages are liquidated, then they form the only measure of damages, for either party, upon the breach of all or either
The judgment should be affirmed.
Denio, Oh. J., Selden, Brown, Paige and Bowen, Js., concurred in the opinion of Johnson, J.; Comstock, J., did not sit in the case.
Judgment affirmed.