Majority
Headnote
Kumberger v. Congress Spring Co., 45 App. Div. 629 , reversed.When this case was here before, ( 158 N. Y. 339 ), a judgment recovered by the plaintiffs upon a verdict^ which had been directed by the court, was reversed and a new trial was ordered upon two grounds. The suit was to recover the purchase price of a gas engine, which the plaintiffs had sold to the defendant under a contract between them, as expressed in a written proposal of the former “ to furnish and erect in their building * * * one White and Middleton gas engine of six actual horse power, put up complete, including all necessary connections, etc., * * * leaving engine in satisfactory working order and ready for driving belt, for the sum of $700, payable thirty days after satisfactory completion of the contract,” etc. The engine was erected upon the defendant’s premises at Saratoga Springs, in this state, and, after being in operation for about two days, it failed to work satisfactorily, because of the instability of the foundation upon which it was erected. The defense to the action was that the plaintiffs had failed to perform their contract, in erecting the engine upon an improper foundation, and a counterclaim was set up for damages sustained by the defendant. When the parties came to the trial, the plaintiffs gave evidence with respect to circumstances under which the contract was entered into, which bore upon the question as to whether there was any ilnderstanding between the parties as
Upon the new trial which was had, we do hot find the same conflict in the evidence which existed on the first trial, with respect to there being any understanding between the parties as to whether one or the other of them should provide the foundation upon which the engine was to be erected. The issue between the parties upon the last trial was submitted to the determination of the jury, and, because of certain erroneneous refusals on the part of the trial judge to instruct the jury, we are compelled to order a new trial.
The plaintiffs’ counsel asked the court to charge, as a matter of law, “ that the contract did not require that the plaintiffs should furnish the foundation.” The court declined so to
Furthermore, there was error committed in the refusal of the request made by the plaintiffs’ counsel to the trial judge to charge the jury “ that the plaintiffs were entitled to a verdict for the contract price of the engine, subject to diminution of any damages which the defendant suffered by reason of the plaintiffs’ neglect to inform defendant that the floor was an insufficient foundation.” The request resumes, in effect, the whole difficulty and involves the real point of the case. Under our previous opinion, the rule was laid down for the case that if the plaintiffs neglected to perform the duty resting upon them, of informing the defendant’s officers if the foundation furnished was inadequate and improper for the satisfactory working of the engine, then they should be held responsible for any consequent damage to the defendant, which was a direct result of that neglect of duty. If the trial judge had charged as requested, the jury could then have determined the issue between the parties upon the true principle which should govern the determination.
For the errors pointed out; we think there should be a reversal of the judgment and a new trial should be ordered, with costs to abide the event.
Pabker, Oh. J., Gray, O’Brien, Martin, Cullen and Werner, JJ., concur; Landon, J., not sitting.
Judgment reversed, etc.
Cases cited
- Kumberger v. Congress Spring Co. 158 N. Y. 339 p. 591