Majority
Headnote
Contract — construction of building contract — when contractor not responsible to sub-contractor for losses caused by delays of architects in furnishing plans and drawings.By this action the plaintiff has sought to recover from the defendant the balance due upon a contract between them and, in addition, damages for its alleged breach. When made, the defendant was under contract with Andrew Carnegie for the construction of a residence, which was to be performed under the direction of Babb, Cook and Willard, architects, and plaintiff’s contract was for the furnishing of the granite work called for in that contract. He agreed that he would provide all the material and perform all the work in the furnishing and the setting of the granite, necessary in the completion of the residence, “ under the direction and to the satisfaction of Messrs. Babb, Cook and Willard, architects, acting for the purposes of this contract as agents of the owner.” By the next article of the contract, it was provided that the “ architects shall furnish to the party of the first part, (the plaintiff), such further drawings, or explanations, as may be necessary to detail and illustrate the work to be done ; ” which the plaintiff was to conform to “ as part of this contract.” Another article of the contract required the plaintiff to complete the work comprehended within the agreement on, or before, a date mentioned. In the event of a failure to so complete it, the sum of $25 was mutually agreed upon
At the conclusion of the trial, the court directed a verdict for the balance, which was admitted to be due under the contract, and as to other claims- for damages the complaint was dismissed. This disposition of the case has been affirmed by the Appellate Division and the only important question, upon this appeal of the plaintiff, for our consideration is whether, under the contract of the parties, the defendant can be made answerable for any losses caused by the default of the architects. The argument is that the positive duty imposed upon the plaintiff must be considered in the light of a coiTesponding obligation to be implied as resting upon the defendant “ to furnish the necessary drawings and plans so as to enable the plaintiff to complete the work within the contracted time.” It is contended that without a construction, which would imply such an obligation on the part of the defendant, the mutuality of contract would be destroyed and it is insisted that the architects “ acted in a twofold capacity,” which is to say, they were as much the agents of the defendant as those of the owner. The appellant refers to that pro
The relative obligations of these parties are to be determined by the terms of their contract and they are not left to surmise, or inference. Their determination is not to be influenced by any considerations save those justified by their agreements; for when parties have made their contract, it is the duty of courts to enforce it, as they have elected to make it, without regard to the fact that, in the light of subsequent events, a hardship may be worked. (Coulter v. Board of Education, 63 N. Y. 365 .) Ordinarily, as between a subcontractor and the contractor, who is in control of the general work to be performed, the law places the latter under an obligation to the former to make good all losses consequent upon delays in the progress of the work, not attributable to the former. The rule may be assumed to be well settled by the authorities, and it is founded in justice, that, where a party has assumed a positive obligation of the nature of this plaintiff’s agreement, a corresponding obligation, if not expressed in terms, will, nevertheless, be implied as resting upon the other party, to whom the agreement runs, to be answerable for all losses caused by delays, which his control of the work should make him responsible for; either because he might have prevented them, or because the contract itself was not so framed as, in the event of their happening, either to exempt him, or to permit the inference of an intention that responsibility should rest elsewhere. Reference to the cases cited, of Allamon v. Mayor, etc., of Albany, ( 43 Barb. 33 ), Del Genovese v. Third Ave. R. R. Co., ( 13 App. Div. 412 ; affd., 162 N. Y. 614 ), and Mansfield v. N. Y. C. & H. R. R. R. Co., ( 102 N. Y. 205 ), will illustrate the application of this rule of mutuality of obligation. In Mansfield v. N. Y. C. & H. R. R. R. Co., the action was by the contractor against the owner
This just rule, which the authorities sanction, will have its proper application in all like cases; but it is made inapplicable to the present case by the express and peculiar provisions of the contract; which, as between sub-contractor and contractor, refer the former to the owner’s agents, the architects, and offset their delaj's in furnishing plans by equivalent extensions of time for completion. Giving to the appellant the benefit of the rule, in its fullest extent, he is met with an insuperable difficulty, in the enforcement of a claim for damages suffered from delays of the architects, by the explicitness of the agreements. They negative the assumption that it was within the contemplation of the parties that any obligation rested upon the contractor to respond for such defaults and compel the construction that the contrary was intended and provided for. The plaintiff knew of the defendant being under a contract with the owner of the property, which gave the absolute control of the work to Babb, Gook and Willard, the owner’s architects, and, with such knowledge, he was, also, willing to agree, in his contract, to perform his work under their direction and to their satisfaction “ acting for the purposes of this contract as agents of the owner.”
Cullen, Oh. J., Edward T. Bartlett, Vann, Willard Bartlett and Chase, J J., concur; Haight, J., absent.
Judgment affirmed, with costs.
Cases cited
- Mulholland v. Mayor of New York 113 N. Y. 631 p. 337
- Allamon v. Mayor of Albany 43 Barb. 33 p. 337, p. 338, p. 341
- Cross v. Beard 26 N. Y. 85 p. 337, p. 338
- Belden v. Burke 147 N. Y. 542 p. 337
- Randel v. President of Chesapeake & Delaware Canal 1 Harr. 233 p. 337
- Harmony v. Bingham 12 N. Y. 99 p. 337
- Beebe v. Johnson 19 Wend. 500 p. 337
- Smith v. Nelson 62 N. Y. 286 p. 337
- Genovese v. Third Avenue Railroad 13 App. Div. 412 p. 338, p. 341
- Mansfield v. New York Central & Hudson River Railroad 102 N. Y. 205 p. 338, p. 341
- Bien v. Parsons 15 Misc. Rep. 457 p. 338
- Barnum v. Williams 115 App. Div. 694 p. 338
- Coulter v. Board of Education 63 N. Y. 365 p. 338, p. 341
- Murphy v. Buckman 66 N. Y. 297 p. 338
- Wakeman v. Wheeler & Wilson Manufacturing Co. 101 N. Y. 205 p. 338
- Warren Chemical & Manufacturing Co. v. Holbrook 118 N. Y. 586 p. 339
- Cassidy v. Le Fevre 45 N. Y. 562 p. 339
- Nicholls v. American Steel & Wire Co. 117 App. Div. 21 p. 339
- Leonard v. New York, Albany & Buffalo Electro Magnetic Telegraph Co. 41 N. Y. 544 p. 339
- Snell v. Remington Paper Co. 102 App. Div. 138 p. 339
- Meyer v. Haven 70 App. Div. 529 p. 339
- Genet v. President of the Delaware & Hudson Canal Co. 136 N. Y. 593 p. 339