Majority
Headnote
Contract — construction of contract for grading and filling in street—basis of computation of amount of material used for filling.I think that the judgment appealed from must be reversed.
I do not assent to appellant’s contention that there is a difference in the meaning of the terms 4 4 embankment in excess of excavation” and “earth filling furnished,”used in the contract and various instruments connected there
Neither do I give the importance, which is asserted in behalf of the appellant, to the fact that in the contract proper the printed blank which originally read “earth filling furnished ” was changed to “'all embankment in excess of excavation, ” wherefrom it seeks to give especial emphasis to the word “all” as justifying a different measurement than was applied by the engineer of the. city to this item of work done by the contractor.
As I have indicated, in my opinion the two terms “ embankment in excess of excavation ” and “ earth filling furnished” actually mean the same thing. They were used interchangeably in the various instruments which made up the contract, and I think that the explanation of the change in the printed blank already referred to may be found outside of the reasons given by appellant. In the published proposal for this work the term used was “ earth filling furnished, ” but when the contractor made his bid he evidently used a printed blank, in which the term employed was “ all embankment in excess of excavation.” Under these circumstances it was quite natural that the agreement which followed the bid should
If the foregoing view is correct, then the word “ all ” in the clause referred to in the agreement ceases to possess the significance urged for it. It is argued that it is to be construed as indicating an intention to include as embankment everything which generally would answer to that description, but it seems to me that the clause is to be construed in connection with the other provisions of the contract, and doing this the clause provides for payment for everything in the way of embankment when measured as such in accordance with the other provisions of the contract. If there is any provision in the contract prescribing a particular method of computing embankment and filling which excludes allowance for material sinking below the original surface of the ground, the effect of this provision would not be nullified by the use of the word “ all ” in the phrase quoted. Thus far, therefore, I agree with the reasoning which has led to the judgment in behalf of the city, but at this point I encounter difficulties in affirming the judgment which I have not been able to avoid.
Clause 14 of the specifications, which has been quoted and under which the computation has been made of which appellant complains, provides that “ The total amount of filling done will be determined by calculation, and will be only so much as is included between the elevation of said surface of deposit, as recorded by the engineer, and the grades hereinbefore set forth.” This clause, therefore, requires, as a basis for its application, a record by the engineer of the surface of deposit. As already
In addition to this, it is significant that the proposal and estimate for this work did specify as the amount of filling to be done a quantity which corresponds with a surface of deposit, not at the original surface of the ground, hut at the submerged level where the deposited filling finally found a foundation. Under these circumstances I do not think that we can hold as matter of law that the lines drawn on the blue print map and referred to in behalf of the city were intended or understood by the parties to be that record of the surface of deposit provided for by the specifications and on which the computation made by the engineer can rest. If it should he properly determined as a matter of fact or, through additional evidence as matter of law, that the parties did intend and understand them to be such, then in my opinion the measurement made by the engineer which disallowed any compensation for earth sinking below the level of those lines would be valid. But if, on the other hand, it should he determined that these lines were not thus understood and intended and binding on the parties it would result that no surface of deposit was indicated and recorded by the engimeer, and in that case I see no reason why the amount of embankment and filling furnished by the contractor must not be measured in such manner as would he lawful and proper independent of the provisions of said clause 14.
For these reasons I advise the reversal of the judgment and that a new trial be granted, costs to abide event.
Chase, Collin, Cuddeback and Cardozo, JJ., concur; Willard Bartlett, Oh. J., and Miller, J., concur in result.
Judgment reversed, etc.
Cases cited
- Agawam Bank v. Strever 18 N. Y. 502 p. 150
- Goix v. Knox 1 Johns. Cas. 337 p. 150
- Bradley v. Buffalo, New York & Erie Railroad 34 N. Y. 427 p. 150
- Greenfield v. Gilman 140 N. Y. 168 p. 150
- Kennedy v. Porter 109 N. Y. 526 p. 150
- St. George Contracting Co. v. City of New York 205 N. Y. 121 p. 150
- MacKnight Flintic Stone Co. v. Mayor of New York 160 N. Y. 72 p. 150
- Bowery National Bank v. Mayor of New York 63 N. Y. 336 p. 150
- Burke v. Mayor of New York 7 App. Div. 128 p. 150
- Neidlinger v. Onward Construction Co. 188 N. Y. 572 p. 151
- Condict v. Onward Construction Co. 210 N. Y. 88 p. 151
- Kihlberg v. United States 97 U. S. 398 p. 151
- Martinsburg & Potomac Railroad v. March 114 U. S. 549 p. 151
- Chicago, Santa Fé & California Railroad v. Price 138 U. S. 185 p. 151
- Ripley v. United States 223 U. S. 695 p. 151
- Hart v. City of New York 201 N. Y. 45 p. 151
- Cunningham v. City of New York 185 N. Y. 549 p. 151
- Riley v. City of Brooklyn 46 N. Y. 444 p. 151
- Sullivan v. President & Trustees of the Village of Sing Sing 122 N. Y. 389 p. 151