Majority
Headnote
Rescission of contract — delivery of goods after seller has been notified that contract of sale has been rescinded by purchaser — when seller cannot recover the value thereof.In November, 1911, the parties to this action entered into a contract by which the plaintiff, the owner of a creamery, agreed to sell to the defendants, and they agreed to purchase, for one year beginning December 1,1911, and ending December 1,1912, skimmed milk at twenty-three cents per can of forty quarts. Defendants purchased the milk for the purpose of manufacturing it into pot cheese at their factory located some distance from the plaintiff’s creamery. Shortly after its execution the contract was modified, to obviate the transportation of the milk, by permitting defendants to install in the creamery the vats and fixtures necessary for there receiving the milk and mailing the cheese. In consideration of such modification the defendants agreed to pay twenty-five instead of twenty-three cents a can for the milk. The fixtures and vats were installed and defendants then put into the creamery a cheese maker by the name of Margolin, who made the cheese until some time in February following, when he left, having previously employed for defendants a man by the name of Cole in his place. Cole thereafter continued to make the cheese until about the 21st of June, when one of the defendants had an interview with the plaintiff and notified him that the cheese which was being made was not satisfactory. There then arose a dispute as to whose duty it was to make the cheese — defendants insisting that from the. first of April, under the contract, it was the plaintiff’s, and the plaintiff insisting he had nothing to do with the making of the cheese; that he was simply obligated to deliver the milk at the creamery to defendants. As a result of this interview the defendants, on the 21st of June, wrote the plaintiff two letters, in one of which they said: “ If you make any further shipments same will be returned to you at your expense;” and in the other, “ I beg to call your attention to the fact that * * * we will not be responsible any
The plaintiff knew, when he received the letters, that the defendants had rescinded the contract; that Cole thereafter had no authority to receive the milk, and having this knowledge it was his duty to use reasonable effort to reduce the loss. He could not, without making some effort in this direction, permit the milk to become a total loss, and then hold the defendants fiable for the contract price. (Dustan v. McAndrew, 44 N. Y. 72 ; Van Brocklen v. Smeallie, 140 N. Y. 70 ; 13 Cyc. 71.)
The defendants paid for the milk delivered to the 16th of June and plaintiff was entitled to recover for deliveries from that time until the letters were received. Plaintiff testified that he delivered from- the 16th of June to the 1st of July, 493 cans and 15 quarts, which,
The other errors alleged have been examined, but they do not affect the validity of the judgment.
The judgment appealed from, therefore, should be modified by reducing the amount of the damage to $71.80, with interest from December 3d, 1913, and as thus modified affirmed, without costs to either party in this court or the Appellate Division.
Hiscock, Ch. J., Chase, Collin, Hogan, Pound and Crane, JJ., concur.
Judgment accordingly.
Cases cited
- Fulton v. Canno 162 App. Div. 203 p. 189
- Dustan v. McAndrew 44 N. Y. 72 p. 189, p. 191
- Van Brocklen v. Smeallie 140 N. Y. 70 p. 189, p. 191