Majority
Headnote
Waiver — estoppel — question of fact — contract of sale — waiver a voluntary giving up of known right — estoppel may be based thereon — duty to speak — mere silence not enough to fix liability — action for breach of contract of sale — when waiver of right to terminate deliveries at certain date question of fact.The action is to recover damages for breach of a written contract dated May 4, 1916, for the sale of cement. The defense was a denial of the breach. Defendant also counterclaimed for an unpaid balance due for the purchase price of cement delivered under the contract. The trial court directed a verdict for the plaintiff and directed that defendant’s exceptions be heard in the first instance by the Appellate Division under the provisions of the Code of Civil Procedure (§ 1000). The Appellate Division sustained the exceptions and ordered judgment for the defendant.
The contract provided for the delivery of approximately 60,000 barrels of cement alongside dock Coney Island, N. Y., in lots of not less than 500 barrels for the performance of plaintiff’s contract with the public service commission to construct the Coney Island subway terminals. The contract then reads: “ Time of delivery during life of job estimated to be completed by December 31st, 1917. The Purchaser shall give the Cement Company shipping instructions, in writing, a reasonable time before shipments are to be made; the Cement Company shall not be obliged, except at its option, to make deliveries after December 31st, 1917.”
Up to October 27th, 1917, less than 20,000 barrels of cement had been delivered under the contract. Upon October 27th the plaintiff gave an order for 15,000
In response to this letter, and upon December 3d, the defendant wrote to the plaintiff: “ In accordance with yours of November 24th, we have reduced shipping schedule on contract for the Coney Island Terminal to approximately 250 barrels, or 1,000 sacks daily.” Four bags make one barrel of cement. A thousand bags a day would be equal to 250 barrels.
The defendant thereafter shipped cement at various times before December 31st, and made four shipments thereafter, but upon January 18th it refused to make further shipments on the ground that under the contract it was not required to ship any cement after December 31st, 1917, except as it should elect so to do, Meanwhile the market price of cement had risen from $1.12 per barrel, the contract price, to $2.75 a barrel.
The contention of the plaintiff is, and the ruling of the trial court was, that, as matter of law, when defendant accepted the orders of October 27th and October 31st, and thereafter at plaintiff’s request, by its letter of December 3d, reduced its shipping schedule to approximately 250 barrels daily, without notifying plaintiff that it would not continue deliveries after December 31st, the necessary effect of its silence was to lull plaintiff into the secure belief that it would receive the full amount of its order although the period of delivery extended beyond December 31st, and that it could not thereafter exercise its option to withhold deliveries after that date.
The court below held that the defendant had the unqualified right to avail itself of the time limit placed in the contract and to refuse to make deliveries after December 31st, and that its conduct revealed no contrary intention on its part.
The question is whether in law or in fact the defendant’s conduct was deceptive and beguiling and whether plaintiff was thereby allowed to believe and justified in believing that its orders would be filled. Waiver is the voluntary giving up of a known right. It may be established by conduct. When established, an estoppel-may be based thereon which bars the subsequent assertion of such right. It is an incident of performance and relieves against forfeiture. (Clark v. West, 193 N. Y. 349 .) “ A waiver, not express, found in the acts, conduct or
The question is, therefore, as to the intent with which the parties acted. Was it the purpose and intent of defendant to deceive? Was the natural result of its conduct to lead plaintiff to act to its disadvantage? The language of the contract is plain. The option to refuse deliveries after December 31st was to be exercised only after that date. Defendant had until that date to decide what action to take. If plaintiff’s letter of November 24th was in substance and meaning this: “ You have accepted our order for 28,800 barrels of cement. We need the cement to complete the job, but we are being delayed in our work and want the order filled, for the present, only at the rate of 250 barrels a day. That will obviously continue the period of delivery long past December 31st unless we change our shipping instructions; ” if it is to be read with this meaning, unqualified acceptance establishes a waiver of the right to refuse deliveries after December 31st.
Plaintiff’s letter and defendant’s reply are, however, susceptible of another construction, when read in the light of surrounding circumstances. Plaintiff’s letter
The deductions of fact are for a jury to make.
The judgment should be reversed and a new trial granted, with costs to abide the event.
Hiscock, Ch. J., Cardozo and McLaughlin, JJ., concur; Hogan, Crane and Andrews, JJ., dissent.
Judgment reversed, etc.
Cases cited
- Kiernan v. Dutchess County Mutual Insurance 150 N. Y. 190 at 194 p. 412, p. 416
- Clark v. West 193 N. Y. 349 p. 412, p. 415
- Roby v. American Central Insurance 120 N. Y. 510 p. 412
- Jennings v. Grand Trunk Railway 127 N. Y. 438 p. 412
- Underwood v. Farmers' Joint Stock Insurance 57 N. Y. 500 p. 412
- Toplitz v. Bauer 161 N. Y. 325 p. 412
- Feinberg v. Allen 208 N. Y. 215 p. 412
- White v. Hoyt 73 N. Y. 505 p. 412
- Gillet v. Bank of America 160 N. Y. 549 p. 412
- Nellis v. Western Life Indemnity Co. 207 N. Y. 320 p. 413
- Broadway Realty Co. v. Lawyers Title Insurance & Trust Co. 226 N. Y. 335 p. 413
- Alsens American Portland Cement Works v. Degnon Contracting Co. 222 N. Y. 34 at 37 p. 416
- Wiser v. Lawler 189 U. S. 260 at 271 p. 416
- Eltinge v. Santos 171 Cal. 278 p. 416