Majority
Headnote
Contract — sale — action for failure to deliver goods — when offer and acceptance of partial delivery does not constitute waiver of right to cancel contract or extension of time to deliver — when manufacturer relieved by strike from liability for failure to deliver and from obligation to deliver thereafter — erroneous charge that manufacturer might be required to deliver other goods it had on hand and which purchaser was willing to accept in place of goods ordered.This action was brought to recover damages for failure to deliver silk shirtings, according to contract.
The complaint alleges that on or about the 20th day of March, 1919, the plaintiff and the defendant entered into an agreement in writing, a copy of which is annexed and made part of the complaint. The exhibit recites that the plaintiff, styled the Shirt Company, has presented to the defendant, known as the Silk Company, an order in writing dated March 20, 1919, calling for the sale and delivery by the Silk Company to the said Shirt Company of 400 pieces of shirting No. 910 at $1.60 per yard, and has requested from the Silk Company credit terms of 6/10/60 upon the said order. The agreement goes on to provide for the deposit of certificates of stock and cash as security for the purchase price and the results which are to follow from non-payment. Article V reads:
“ The written, signed order of the Shirt Company dated March 20, 1919, when accepted by the Silk Company, with all the terms and conditions thereof as appearing and referred to thereon shall, in conjunction with this document, constitute the contract between the parties and this agreement is and shall be construed as part of the said sales contract.”
Besides this exhibit annexed to the complaint, the contract, therefore, consisted of the written order of March 20, 1919, when accepted, and all the terms and conditions appearing thereon.
This written order was accepted and appears as Exhibit II upon the trial of the action. According to the plaintiff’s allegations .it is the contract, and all of the contract, regarding manufacture and delivery entered into between the parties. ■ It reads:
“ J. H. & C. K. Eagle
“ 265 Fourth Avenue
“ New York Mar. 20-1919 m.
“ Normandie Shirt Co.,
“ 164 W. 27th St., No. B-7578
“N. Y. C. Via
“ Terms 6 /10 /60 F. O. B. New York Salesman House
“ Dehvery June-July-Aug.-Sept.
Psc. Assorted Pcs. Unassorted[1] Description Quality Yd. Psc. Price
-- 400 32" Shirting — 1 Split Edge 910 75 /80 1.60
“ Above order confirmed.
“ J. H. & C. K. EAGLE,
“ B. M. Fessler,
“ Sales Manager.”
On the reverse side of this order appear two clauses referred to in this case:
“2 — Fire; war, strikes, legislative, judicial or public administrative acts, errors or defaults of the seller’s mill, manufacturer, dyer, finisher, carrier or vendor, or any cause not within the seller’s control, preventing the dehvery of merchandise in- accordance with the terms of this contract, shall absolve the seller from any hability hereunder.
“ 9 — Failure on part of the sellers .to make specific deliveries shall not invahdate the balance of this contract.”
Clause 9 may be eliminated from further consideration, for it evidently means that if goods are not delivered in June as called for by the contract, nevertheless the July dehvery holds good, and so regarding the other months specified. A failure to dehver in a previous month the amount called for would not affect the requirements for subsequent months. This clause, therefore, has httle or no bearing upon the point raised in this case.
To understand this contract, and the claims of the
* Assortment to be given. Wks. before delivery desired Patterns to be selected as soon as Mr. Licking gets paintings together.
We may now understand the meaning of that part of the order or contract which reads, “ assortment to be given, patterns to be selected as soon ás Mr. Licking gets paintings together.” Mr. Licking was in the defendant’s employ and the paintings referred to indicate samples or representations of shirting showing the coloring of the shirting and the width of the stripes. These various paintings or drawings had numbers. The plaintiff when these paintings were ready/ was to select the numbers showing the coloring and design of stripe which it desired. It did this by two selections made in writing on the order blank of the defendant, one dated May 3, 1919, and the other June 13, 1919. These are in the case as Exhibits 7 and 8. The numbers, such as 487, 720, 718, indicate, as I read the evidence, the design. Blue, gold, helio, indicate the color. Each selection was to be made up in sets of the various colors.
It will be noticed that while the contract was made March 20, 1919, no assortment or selection was given by the plaintiff until May 3, 1919. Other selections were designated as early as April 10th, but as I understand the parties, these selections were replaced by the selections
A strike occurred at the mills on May 26, 1919. “All the looms and all the machinery were stopped, totally stopped, no wheels were turning whatsoever” The strike continued until August 18th when the mill started up with about 40 per cent of its help. At- the time of the strike there was warp then in the looms. Hertel testified:
“ Q. Now did you resume operations again, in the end of August of 1919? A. Partly,, yes.
“ Q. Now was it necessary to run off the looms,' the warp, that was then in the looms? A. Yes, sir.
“ Q. How long did that take? A. From 4 to 6 weeks, according to the length of the cuts on the looms.
“ Q. Did you on the 18th of August immediately begin to make new warps for the various looms in the shirtings? A. Yes, sir.
“ Q. Will you tell his Honor and this jury how long it takes to make warps? A. For shirtings?
“ Q. Yes? A. 9 to 10 weeks.”
The relation of these facts one to the other, is this: The plaintiff on May 3d and on June 13, 1919, made certain selections of silk to be manufactured. Before the goods could be made, as it took 6 to 9 weeks to manufacture them, a strike occurred, compelling the mill to close down. The mill • was closed from May 26th to
It is, therefore, quite apparent, and so far as I can see, not seriously contradicted, that the strike prevented the manufacture of any portion of the plaintiff’s order, with possibly a small exception, within the months of June, July, August and September. The plaintiff both in the evidence and in its theory of the case, does not claim that the defendant during or after the strike could have manufactured its shirting according to order.
The plaintiff has brought this action upon the theory that the time of delivery did not end with September 30th; that the contract called for deliveries after September 30th, within a reasonable time thereafter, if by reason of a strike deliveries were delayed. The defendant interprets the contract to mean that if a strike occurred of such a substantial nature that the plaintiff’s order could not be delivered before September 30th, then all or such part of it as could not be manufactured and delivered terminated 'and was canceled. In his brief the plaintiff’s counsel states the issue: “ The sole defence litigated was the sufficiency of the strike clause in the agreement to excuse defendant from performance of the uncompleted portion of its contract.” And again, “ By mutual consent the question litigated was whether the contract was rightfully cancelled under the strike clause or whether it was extended by consent.”
Before considering the strike clause it may be well to refer to the evidence upon which the plaintiff claims that there was an extension by agreement or waiver of the time of delivery.
Mr. Blanck represented the plaintiff. Around the end of September he came to the defendant’s office and saw
“ Mr. Fessler carried on most of the conversation with Mr. Blanck. He explained to Mr. Blanck when Mr. Blanck asked for a delivery of merchandise that we had a strike which had greatly delayed production at the mill, and that these particular patterns which Mr. Blanck ordered, had been delayed, and that it would be several months before the exclusive patterns which Mr. Blanck ordered could be delivered. And Mr. Blanck asked whether there was some good substitute. We explained that there might be some substitutes, but we did not feel under any obligations to make delivery, because of the strike, and we fulfilled our obligation on the contract. * * * We were adjusting this matter with our customers on a fifty-fifty basis, with those customers who were willing to sign a revised order we were giving fifty per cent of the amount of undelivered merchandise at the time of this strike. * * * Mr. Blanck refused to accept the fifty-fifty proposition, and insisted upon a delivery of the entire quantity of the original orders, or of the revised assortment, and we said that if he took that attitude, whether we were right or not we would deliver just a proportional quantity that was made in September. * * * We said whether we were under any obligations or not to make a delivery, we would give him the September portion, which we explained was one-quarter of the undelivered balance. We had delivered 27 pieces in May and we figured, with 375 pieces unshipped, we would give him one quarter of that, or 93 pieces. He said he would take the 93 pieces, but he wanted the rest of his assortment; and we said he would not get another piece. * * * then he proceeded to make his selection to get patterns that would be quicldy delivered. He selected from sample cards.”
The defendant had none of the plaintiff's patterns in
We, therefore, come back to consider the question of the strike clause, and whether this permitted the cancellation of the contract, or merely postponed the date of delivery. This, as plaintiff’s counsel has stated, constituted the only question litigated on the trial.
At the close of the case it was conceded by counsel that the strike was genuine, and the inability to deliver was
Mr. Gainsburg: “ Yes.”
On the assortment selections of May 3d and June 13th, 1919, there appeared stamped in red ink this clause:
“ In case of restrictions and regulations by any government, delays in transit, or delays due to strikes, accidents or any cause beyond seller’s control, deliveries and shipments may be deferred, or partial deliveries made on account until contract is complete.”
It is not claimed that this forms any portion of the contract sued upon. As stated at the beginning of this opinion, the contract is alleged to be an order of March 20, 1919, and the terms and conditions stated thereon. In the evidence, plaintiff’s counsel offered the papers dated March 20, 1919, the two exhibits of that date as the contract between the plaintiff and the defendant. He refers to Exhibits 7 and 8, being the assortment selections of May 3d and June 13th, 1919, as “ sheets giving the color or pattern assortment.” In his brief the respondent’s counsel refers to this clause, not as part of the contract, but as an explanation of what the parties meant by the previous contract. The contract was complete March 20, 1919. The rubber stamping does not appear until the assortment orders come along beginning with April 10, 1919, which was supplanted by the May 3d sheet.
We must, therefore, consider the contract as the plaintiff claimed it in his complaint and upon the trial, and deal with the meaning of the strike clause as printed on the order of March 20, 1919, Exhibit II, in the case. As applicable here, the clause reads, 11 strikes, * * • * preventing the delivery of merchandise in accordance with the terms of this contract, shall absolve the seller from any liability hereunder.”.
Williston on Contracts, in section 1968, discussing the effect of contracts, which were contingent upon strikes and other unforeseen casualties, says: “ It has become common for manufacturers and others to insert in their contracts clauses relieving them from liability in case of strikes and other unforeseen casualties. The words of these clauses are not identical, and it can only be said that while such agreements are legal, it is essential to prove that a strike or casualty within the terms of the clause in question was the actual cause of non-performance ; and also that unless the clause clearly indicates that increased difficulty or enhanced prices (as distinguished from impossibility) due to the casualties in question shall afford an excuse, they will not be held to do so, at least unless extreme in degree. If such a clause becomes operative and excuses the promisor from performance, the excuse has been held not merely temporary, operative only while the casualty continues, but a permanent excuse for non-performance, unless the contract provides that delay only shall be excused.”
The cases referred to by the respondent will be found to have clauses in the contracts involved clearly indicating that delivery was to be delayed and made up subsequently to the termination of the cause of delay. We conclude, therefore, that this clause entitled the defendant to terminate the contract on September 30th, and to refuse to deliver any goods thereunder of which delivery had been prevented by strikes. In other words, it could not deliver by September 30th the goods which the plaintiff had ordered, by reason of the strike. The contract as to these undehverable goods was, therefore, at an end, and the defendant was not obliged to make them up and to deliver them later. This clause did not call for a later or postponed delivery.
At the close of the case a long argument was had by
The learned trial “justice took the opposite view of this strike clause to that which we have taken. He decided that it referred merely to deliveries, and not to the contract itself. In this, for reasons here stated, we think he was in error. The case, however, was decided by him on another point. He found that the defendant had on hand September 30th sufficient yardage to supply the plaintiff with its order. If this was so, of course, the strike clause had no application whatever to the situation, and the defendant would be hable. He said:
“ It does appear that delays were caused by strikes, and there is no question that the strikes were bona fide; and it appears uncontradicted in the case that the plaintiff was willing to take goods of the same quality, but of different designs, and that he was willing to put up with delayed consignments of the goods. * * *
“As I have said before, I see nothing in this contract" that would permit the defendant to take that position on the question of prorating. Strikes are an ordinary thing in manufacturing lines, and had the defendant wanted to, it might have expressly provided in its contract that in case of strikes it would have a right to pro rate, or they might even go so far as to say that in case of strikes preventing deliveries they might declare the contract at an end, but they did not do either. The contract was extended up to a date where they probably got tired of extending it; and when the plaintiff refused to accept the fifty per cent adjustment, they then declared the contract at an end. I think they had no right to do that, especially in view of the fact that at that very time
The error in the judge’s statement and conclusion is that the plaintiff could make a new contract by electing to take different patterns from those previously ordered. A contract is a contract and the defendant had a legal right to stand upon it. The contract, as heretofore stated, called for the manufacture of certain designated patterns. Those patterns had been selected. The defendant did not have them. It had not manufactured them. The evidence is uncontradicted that none of the defendant’s stock on hand included the plaintiff’s patterns. While one witness on a previous occasion had stated that some of the plaintiff’s patterns had been sold to another party, he corrected the statement on this trial. There is no rule of law that I know of which permits a party to change his contract and elect to take something else than the kind ordered so as to put the other party in default. Conceding that the defendant had plenty of silk No. 910 on hand, it was under no contract to deliver it to the plaintiff if it consisted of different color and stripes and designs than those specifically ordered by the plaintiff. The selection of the 93 pieces by special permission and agreement was not a waiver of the defendant’s rights under the contract as to the remaining undelivered portion as heretofore explained by me. Neither was the contract extended. This has also been touched upon by me in what I have heretofore said. By reason of what I have here stated we feel that the judgment below must be reversed and a new trial ordered, with costs to abide the event.
His cock, Ch. J., Cardozo, Pound, Andrews and Lehman, JJ., concur; McLaughlin, J., absent.
Judgment reversed, etc.
Cases cited
- Texas Co. v. Hogarth Shipping Co. 256 U. S. 619 p. 219
- John F. Trainor Co. v. G. Amsinck & Co. 236 N. Y. 392 p. 219
- Norrington v. Wright 115 U. S. 188 p. 219
- Cleveland Rolling Mill v. Rhodes 121 U. S. 255 p. 219
- Sanford v. Brown Bros. 208 N. Y. 90 p. 220
- Elwood v. Goldman 217 N. Y. 585 p. 220
- Gillet v. Bank of America 160 N. Y. 549 p. 220
- Cameron-Hawn Realty Co. v. City of Albany 207 N. Y. 377 p. 220
- Milliken v. Keppler 4 App. Div. 42 p. 220
- Delaware, Lackawanna & Western Railroad v. Bowns 58 N. Y. 573 p. 229