Majority
Headnote
Contract — arbitration — construction of arbitration clause in building subcontract — delays and hindrances — alterations in work and additions thereto — subcontractor caused additional expense in removing hoists and cement plant and for additional men and overtime —■ alteration in form of construction — erroneous appointment of third arbitrator by court.The respondent, Smith Fireproof Construction Company, Inc., made a contract with the appellant, Thompson-Starrett Company, whereby, for a consideration expressed, it agreed, as “ Sub Contractor,” to perform all concrete construction work required in the erection of a building, which the Thompson-Starrett
Obligations not to delay or hinder the subcontractor in the performance of the work were doubtless imposed by implication upon the contractor. However, the implication arose, not from a particular contract clause, but from the entire contract and the relationship which was thereby established between the parties. Arbitration was to be invoked in case the parties disagreed “ in relation to any clause in this contract.” Disputes as to delays and hindrances, not being referable to “ any clause in this contract,” were not made arbitrable by the parties. The further provision which we have quoted made “ all clauses ” of the contract applicable “ to any changes, omissions, or extra work.” Doubtless the arbitration clause was one of the clauses thus made applicable. Consequently, disputes as to additional costs, caused by alterations of the work, or additions thereto, were made arbitrable.
The subcontractor complains that the contractor
The subcontractor also complains that it erected two cement mixing plants and hoists and one platform hoist at points designated by the contractor; that it was subsequently required by the contractor to dismantle and remove the two cement mixing plants and hoists at great expense to itself; that it was forbidden by the contractor to use the platform hoist except during certain hours of the day; that as a result it was compelled to use a passenger elevator for hoisting concrete and delivering it upon the work; that it was thereby caused great additional expense in the prosecution of the work. It also complains that it was compelled by the contractor to employ a large force of additional workmen, and to work its employees overtime, with a consequent loss of efficiency and a great increase of cost. No clause in the contract relates to the removal of hoists and plants once installed, or to restrictions upon the use of platform hoists. No clause in the contract gave to the contractor the right to compel the subcontractor to use an additional force of men or to work employees overtime. The subcontractor’s claims for damages in respect to these items, therefore, are not arbitrable, since the disputes involved are not referable to any clause in the contract.
The contract called for a monolithic cement finish upon substantially every floor of the building. This form of construction was changed, by order of the con
• The order appealed from required the Smith Fireproof Construction Company, Inc., and the Thompson-Starrett Company each to select its own arbitrator, designated by name a third arbitrator, and directed the parties to proceed to arbitration. The contract provided that the two arbitrators named by the parties should themselves select the third arbitrator. It was, therefore, error for the court to make the designation.
The order should be modified in accordance with the opinion and, as modified, affirmed, without costs.
Cardozo, Ch. J., Crane, Andrews, Lehman and O’Brien, JJ., concur; Pound, J., not sitting.
Ordered accordingly.
Cases cited
- Young v. Crescent Development Co. 240 N. Y. 244 p. 278
- Borough Construction Co. v. City of New York 200 N. Y. 149 p. 278
- S. A. Wenger & Co. v. Propper Silk Hosiery Mills, Inc. 239 N. Y. 199 p. 278
- Goulet v. Asseler 22 N. Y. 225 p. 278
- Buxton v. Mallery 245 N. Y. 337 p. 278
- Berkovitz v. Arbib & Houlberg, Inc. 230 N. Y. 261 p. 278