Majority
The plaintiff, Margaret Doyle, was injured on March 6, 1932, by falling into a hole or depression in the roadway of Morris avenue in the city of New York. She and her husband, James Doyle, brought
The plaintiffs at the trial produced evidence sufficient, it is conceded, to show negligence on the part of the plumbers in performing the work which they undertook at the request of the abutting owner. The jury brought in a verdict awarding damages to each of the plaintiffs against the city and against the plumbers Marshack and Kosachiner. The trial judge, with the consent of all the parties, reduced the verdicts. Then he passed upon the cross-claims of the city of New York and awarded judgment in favor of the city against the plumbers Marshack and Kosachiner, and also against the defendant Zaslow. None of the defendants appealed from the judgment in favor of the plaintiffs. It was not challenged in the Appellate Division and is not challenged here. The defendant Zaslow appealed to the Appellate Division from the judgment against him in favor of the city. Upon that appeal the Appellate Division reversed that
The only question presented to this court for review is whether the city of New York has made out a cause of action against Zaslow for indemnity against the liability which the plaintiffs have successfully asserted against it. To make out such a cause of action it must show that the damages were the result of a failure by Zaslow to perform some duty which he owed to the city. Upon that point the relevant facts are established either by stipulation of the parties and official documents, or by testimony which is not challenged.
After the city had discovered that the leak was in a service pipe leading to the premises of an abutting owner and had called upon the owner to make the repairs, it turned over the opening in the street to the defendants Marshack and Kosachiner, the plumbers selected by the owner. Marshack obtained from the Department of Water Supply, Gas and Electricity a temporary permit under which he agreed “ to take over and be responsible for the guarding and maintenance of the opening made by the Department of Water Supply, Gas and Electricity from the time of signing this agreement, and within 24 hours from the date hereof, apply to the President of the Borough for a permit to open the street and arrange for the replacing of the pavement.” The plumbers made the necessary repairs and then refilled the excavation made by them in the sidewalk, and also refilled the excavation which the city had made in the roadway, the same day, February 18, 1932.
In accordance with the agreement upon which the temporary permit had been issued, they were still required to apply for a permit “ to open the street and arrange for the replacing of the pavement.” Instead of applying for such a permit, Marshack requested the defendant Zaslow
An ordinance of the city of New York provides: “ In all cases where any person shall perform any of the work mentioned in the preceding section, either under contract ivith the city or by virtue of permission obtained from any department, board or officer of the city, such person shall be answerable for any damage which may be occasioned to persons, animals, or property by reason of carelessness in any manner connected with the work.” (New York Code of Ordinances, ch. 23, art. 1, § 4.)
The work “ mentioned in the preceding section ” includes opening a street. The permit issued to Zaslow grants to Zaslow permission to open the street or sidewalk. It is expressly made “ subject to the strict observance of all laws, ordinances, and regulations enacted for the protection of the city so far as they may apply, and particularly to those set forth on the reverse side of this instrument.” On the reverse side it appears that “this permit is granted on the following conditions: * * * That the pavement over the excavation be replaced immediately after the connection or repairs have been made, * * * ” and there follow extracts from ordinances of the city relating to the manner in which excavations must be made, and thereafter must be filled in and the pavement relaid.
Judgment of the Appellate Division should be reversed and that of the Trial Term affirmed, with costs in this court and in the Appellate Division.
Crane, Ch. J., O’Brien, Hubbs, Loughran and Finch, JJ., concur; Rippey, J., dissents.
Judgment accordingly.
Cases cited
- Irvine v. Wood 51 N. Y. 224 p. 454
- Schumacher v. City of New York 166 N. Y. 103 p. 454
- Mayor of Troy v. Troy & Lansingburgh Railroad 3 Lans. 270 p. 454
- Mayor of Troy v. Troy & Lansingburgh Railroad 49 N. Y. 657 p. 454
- Brooklyn Central Rail Road v. Brooklyn City Rail Road 32 Barb. 358 p. 454
- City of Rochester v. Rochester Railway Co. 98 App. Div. 521 p. 454
- Murray v. Cunard Steamship Co. 235 N. Y. 162 p. 454
- Ell Dee Clothing Co. v. Marsh 247 N. Y. 392 p. 454
- Argersinger v. Macnaughton 114 N. Y. 535 p. 454
- City of Brooklyn v. Brooklyn City Railroad 47 N. Y. 475 p. 454
- Shuba v. Greendonner 271 N. Y. 189 p. 454
- Draper v. Oswego County Fire Relief Ass'n 190 N. Y. 12 p. 454
- Continental National Bank v. National Bank of the Commonwealth 50 N. Y. 575 p. 454