Majority
Headnote
A mechanic, who furnishes materials or labor in the construction of a building in the county of Westchester, acquires under chapter 384 of the Laws of 1852, a specific statutory lien on the interest of the existing owner, which may be enforced by judgment as in a personal action.The proceeding was by a sub-contractor to enforce a mechanic’s lien against the owner, under chapter. 384 of the Laws of 1852.
By the provisions of the act in question, the mechanic, who furnishes materials or labor in the construction of a building in the county of Westchester, in conformity with a contract with the owner, has a specific statutory lien to a .limited extent, on the interest of the existing owner, and this may be enforced by judgment as in a personal action. He may lose, this lien by omitting to comply with the conditions prescribed by the act; but in the case at bar, no fact is found by the referee inconsistent with the claimant’s right.
It is insisted by the appellant, that the lien did not attach until the specification was served, on the 24th of June, 1853; and that it did not attach then, as against the defendant, because he had previously conveyed the property to one Bell, after the completion of the work.
It is insisted that if this be the effect of the act, it is unconstitutional and void; as it may enable the claimant to reach the property of a third party without due process of law. There is no provision of the Constitution which precludes the legislature from declaring a statutory lien, in respect to future contracts, in favor either of the contractor, the sub-contractor or the laborer, upon the land of the owner, at whose instance and for whose benefit the services are performed. The act of 1852 was in force when the contract in question was made; and every contract is presumed to be executed with reference to existing laws, and subject to such modification, in respect to the remedies of the parties, as may result from subsequent legislation, if free from constitutional objection.
The question as to the rights of Bell, the grantee, is not legitimately involved in the present appeal; but as he purchased property, which was subject to an existing statutory lien, it is to be presumed that the price was fixed with reference to the incumbrance, or that he secured himself from loss by appropriate covenants. Be that as it may, the statute is free from constitutional objection, and the defendant cannot complain that he is not permitted, by his own act, to extinguish a subsisting lien without payment.
It is also insisted, that, on the 4th of June, 1853, the defendant, who then owed between five and six hundred dollars on the work in question, made an advance to ¡Robin son & Olough, the original contractors, of the sum of $868.50, which should inure as a payment and extinguishment of the lien. This claim cannot be sustained on the facts found by the referee. Such a payment, if made, would
The advance in question was not intended as a payment on the work in question, for it considerably exceeded the whole amount remaining unpaid. It consisted simply of an exchange of drafts for $868.80, between the owner and Bobinson & Clough, who were at the same time engaged in erecting a number of buildings for the defendant at Biverdale. The purpose of the accommodation was, to enable the contractors to avert a threatened seizure, by the sheriff, of materials prepared for the buildings at Biverdale. It is true that the draft received by the defendant from Bobinson <& Clough was never paid, and that they still remain his debtors in that regard, so far as the case discloses.
But the referee finds, as matter of fact, that at the time the specification was served, the defendant had not paid the contract price of the work now in question, and as we have no authority to disregard the findings, they are conclusive against the claim that the defendant has paid the debt.
It is insisted that the judgment is incongruous, as it operates m personam as well as m rem. It is sufficient to say that it is such a judgment as the statute authorizes; and it is no ground of objection to the validity of a remedial statute, that the remedy it provides is ample and complete.
The judgment should be affirmed.
All the judges concurring,
Judgment affirmed.