Majority
Headnote
Hindrances by one party to a contract, whereby the other party is prevented from completing his part of the contract by the time stipulated, afford a ■ legal excuse for non-performance within such period.The written contract between parties expresses an agreement on the part of the plaintiffs to erect and finish the new building therein referred to, agreeably to the drawings and specifications made by the defendants’ architect and signed by the parties.
It is apparent from an examination of the specifications, that the only work and materials which the defendants were to do and furnish toward the erection of the building were the masons’ and blacksmithing work, and that other work and materials were necessary to its erection and completion. It also appeared in evidence that carpenters were employed by the defendant who were working upon the building at the same time with the plaintiffs. The plaintiffs adduced evidence to show that their work was so connected with that of others employed by the defendant upon the building, that at times its progress necessarily depended upon that of the other work, and that in consequence of delays in that, they were prevented from completing their work within the time limited in the contract.
The jury found these facts in their favor, but objection is made that errors were committed by the judge in receiving evidence upon those subjects, notwithstanding the defendants’ objection, and also in not expressly charging the jury that, in order to excuse the non-performance of the plaintiffs, they should be convinced that the circumstances referred to rendered it impossible for the plaintiffs to complete their work by the day named in the contract. The objection on this ground to the reception of evidence was to the proof of any excuse for the plaintiffs not fulfilling their contract, and was properly overruled; as there can be no question but that hindrances by the defendant, rendering it impossible for the plaintiffs to fulfill them contract, would afford a legal excuse for them non-performance, and the objection was so broad that it could not be sustained without establishing a rule for the exclusion of evidence of such circumstances.
To say that certain work is indispensable to the performance of a contract is, in my judgment, equivalent to a declaration that unless such work is done the contract cannot possibly be performed; and I cannot understand how it is possible for a contractor to proceed with his work when the performance of other work is essential to enable him to do so, and that other work is not done.
Even in view of the position assumed by the defendant (and upon which it is not necessary for us to pass), that a contractor is not to be excused for delays caused by his employer unless they rendered it impossible to complete the contract work within the stipulated time, this charge is sufficient; and that it must have been so understood on the trial appears from the fact that no exception was taken to it nor request made for a more explicit instruction in this respect.
It was plain from the evidence of the plaintiff, Stewart, although he did not state the fact very explicitly in his testimony, that his original estimate made upon the specifications before the contract was signed, was for $11,600, and that it included an estimate of $200 for sheath piling. When the contract was about to be signed, the defendant warranted that the store on the west side of the building would be erected forthwith, and, therefore, that sheath piling would be unnecessary, and, in consideration of this assurance, the
The defendant thus released the plaintiffs from .all claims he might have had against them for breach of the contract in refusing to do this work under it, and their subsequent agreement to do the sheath piling was sufficient consideration to support his promise to pay for it. (Lattimore and others v. Harsen, 14 Johns., 330 .)
The evidence in regard to it was therefore- properly admitted, and the exception to the charge in that respect and to the refusal to instruct the jury that the defendant was not liable "were not well taken.
It was not necessary that the architect’s certificate' should contain a statement that the work was done agreeable to the drawings and specifications, within the time, in a good, workmanlike and substantial manner, under his direction and to his satisfaction. The agreement of the defendant was, that the work should be so done to be testified.by a writing or certificate - under the hand of the architect, but the form of the certificate is not prescribed in that part of the contract which contains the obligations of the plaintiffs, and as the work was to :be done in this manner before they were entitled
But in that part of the contract which states the obligations of the defendant, provision is made for the payment of the contract price in installments, as the work progressed, and in each case the right to payment is made to depend upon the obtaining a certificate signed by the architect. There can be no doubt but that the obtaining of a certificate signed by the architect, and stating that the particular work has been done upon the performance of which the right to the payment depended, would be a sufficient compliance with this requisition. In reference to the last payment, the provision is as follows, viz.: “ $3,000 when all the works are completely finished and certified by the architect to that effect.”
It cannot be successfully contended that this renders two certificates necessary, or that the obtaining of a certificate signed by the architect, and certifying that the works are completely finished would not be a full compliance with the requirement that this fact should be certified, and that a certificate signed by the architect should be obtained in every case to entitle the plaintiffs to payment.
The question is not here, as it was in Smith v. Brady ( 17 N. Y., 173 ), and in most of the other cases cited on this point by the defendant, whether the plaintiffs can recover without obtaining a certificate of the architect, but only whether the certificate presented contained all necessary statements. In Smith v. Briggs ( 3 Denio, 73 ), the defendant had covenanted to pay the plaintiff for doing the carpenter work of a certain house “ when he should receive from the architect his certificate that the work was fully and completely finished according to the specifications.”
Here was a distinct statement of what was required to" be averred in the certificate, and it was properly held that the requirement was not answered by a letter addressed by the architect to the defendant “ pronouncing the house finished,
In that case the contract required that the certificate should embrace a declaration that the work was “finished according to the specification;” and on that ground the use of these words, or words of like import, was held essential. In the case under consideration no such particularity of statement was required in the certificate.
The judgment should be afiirmed.
AE concur except Hunt and Portee, JJ., not voting.
Affirmed.