Majority
Headnote
One who guarantees the performance of a contract has the right, after default by his principal which would justify its termination, to require that the contract be terminated and the claim against himself, as surety be confined to the damages then recoverable.By a contract dated August 12, 1861, the plaintiffs’ agreed with Crossley to do the carpenters’ work on the houses for the sum of $2,625, and to complete the work on or before the 15th of October, 1861; Crossley was to furnish the materials. The defendant guaranteed the fulfillment of the contract on the part of Crossley.
The work was not finished on the 15th of October, and between that day and the 1st of Hovember the defendant gave notice to the plaintiffs that if they did not complete the
It appears from the findings of the referee, that the delay in completing the work was owing to the fault of Crossley in furnishing the materials and preparing the houses. And further, that the defendant had, under a contract with Henry Day, the owner of the lots, assumed the obligations of Grossley in those respects, so that the default was in fact that of the defendant. What the arrangements were between Grossley and the defendant does not appear.
The defence cannot be sustained on the ground of any. breach of the contract on the part of the plaintiffs, but rests wholly upon the effect of the defendant’s notice that he would not be bound as guarantor after the 1st of November.
By the terms of the original contract, the work was to have been completed on the 15th of October. If not performed at this time, the defendant, had he not interfered in the transaction, or consented to an extension of the time, would have been entitled to have the matter closed. If the delay had been owing to the default of the plaintiffs, the defendant would have been discharged. If it was caused by Crossley, he had been guilty of a breach, and the defendant would have been entitled to insist upon the contract being terminated, and, on such termination, would have been liable as guarantor ' for the work done up to that time, and for the damages sustained by the plaintiffs in not being allowed to complete the job. .
The effect of the notice was to extend the time for completion, as far as the guaranty was concerned, to the 1st of November. We think that the extension left the parties in the same position on the 1st of November in which they would otherwise have been on the 15th of October, and that it did not operate as an extension of the guaranty indefinitely to such time as might be necessary to complete the work, but
The referee finds, however, that after having given the notice that he would not be responsible as.guarantor after the 1st of November, 1861, and from that date to June 13th, 1862, the defendant continued to urge the plaintiffs to perform their contract with Orossley, and supplied them with materials for that purpose, and continued to superintend the work, and that he and Orossley waived a strict performance of the work within the time specified by the contract.
These acts of the defendant, if unqualified by eotemporaneous declarations explaining their intent, would have justified the-referee in finding that the defendant abandoned the position he had taken as to the continuance'of his liability as guarantor, and consented that the plaintiff should go on after the 1st of November and complete the work under the original contract and guaranty.
But the referee further finds that after the 1st of November, and while .the plaintiffs were engaged on the work, the defendant stated to them that he would not be personally responsible therefor. The evidence fully substantiates this finding, and shows that the defendant persistently maintained this position throughout all the dealings subsequent to the 1st of November.
It appears that the defendant had an interest in the completion of the buildings, though the precise relations between him and Orossley are not disclosed; that he desired their completion, but was not willing to be personally responsible for work done after the 1st of November. This he communicated to the plaintiffs. His request to them was'in substance that they should go on and finish the building, trusting to Orossley or to the arrangements with Hr. Day for work done after the 1st of November, but not looking to the defendant as guarantor after that date.
The fact that the defendant was interested in the building, or that, under his contract with Day, he was bound to have furnished the materials, and that his default was the cause of Crossley’s default, cannot vary the rights of the parties in this action. The defendant made no contract with the plaintiffs as principal The plaintiffs contracted with Orossley as principal, and the defendant became his surety. The parties having made their contract in this form, and the action being founded on that contract, the defendant was entitled to assert all the rights of a surety. The arrangements, between Day and Orossley and the defendant, concerned them only, and their rights or equities, as between each other, cannot affect the contract between the defendant and the plaintiffs.
If the defence rested upon the allegation, that the plaintiffs had failed to perform their part of the contract, or that the contract had been varied, the facts found by the referee would have been abundant answers to those defences. But such is not the nature of the defence. It is, that after the contract had been broken, the defendant, in his character of surety, insisted that the plaintiffs should not go on and add to his liability as guarantor, but that, if they continued, they should look to the principal alone for all work done after that time. If they did not think proper to continue on those terms, they should have stopped work, and would have been entitled to recover of the defendant what they had earned up to that time and their damages for not being allowed to complete the job.
The learned referee, in substance, denied all effect to the notice given by the defendant, and seems to have held that he
The judgment should be reversed and a new trial ordered, with costs to abide the event.
All concur, except Peokham, J., who dissents on the ground, that the subsequent directions of the defendant were inconsistent with, and a waiver of his notice that he would no longer continue liable as surety.
Judgment reversed and new trial ordered, costs to abide the event.