Majority
Headnote
Plaintiffs’ complaint alleged that they performed services and furnished materials, at the request and for defendant, of the value of $8,423.49, which defendant agreed to pay. Before the answer a hill bf particulars was demanded and served. Defendant answered admitting that plaintiffs performed work and furnished materials for him as alleged in the complaint, but denied they were of the value specified. EM (Earl, 0., dissenting), that the answer only put in issue the value of the services and materials, and that, on the trial, an offer to show that the work and materials charged were not rendered and furnished for defendant was properly rejected.Ho exception was taken to the report of the referee, or question made as to any ruling made by him on the trial, other than, one founded upon his rejection of the defendant’s offer to prove that the work and materials alleged in the plaintiffs’ complaint to have been rendered and furnished by them for him had not been rendered or furnished. The defendant had, by his' answer to the plaintiffs’ complaint and bill of particulars before him, admitted in express terms that the plaintiffs had performed “ work, labor and services, and furnished materials ” for him, as alleged in their complaint; and thus the parties had, by their pleadings, agreed to what the plaintiffs had alleged in their complaint in that respect; and by this agreement they were bound to abide. “.That what the parties have agreed to in their pleadings shall be admitted though the jury find otherwise” (7 Bacon’s Abridgement, 459), is an ancient rule, not to be departed from, except in cases where an amendment has been ordered. All that was put in issue was the value of the services and materials. The offer was properly rejected; and the judgment should be affirmed.
(dissenting). The plaintiffs, in their complaint, alleged that, during the years 1869 and 1870, at the city of Brooklyn and town of Flatbush, they did and performed ser
Upon the trial, the defendant offered to show that the work and material alleged in the complaint had not been furnished or rendered to him. To this evidence the plaintiffs objected, on the ground that the answer did not deny the quantity of work performed and material furnished. The referee sustained the objection, and defendant excepted to such ruling.
The object of defendant’s offer, as it was manifestly understood by plaintiffs’ counsel and the referee, was to dispute the quantity of plaintiffs’ work and materials. The plaintiffs claimed, and the referee held, that the defendant could not dispute the quantity but was confined, under his answer, to disputing the value of the work and materials; and whether the ruling of the referee was correct, is the question to be determined, and is before us upon defendant’s exception.
The complaint alleges the time when and the place where the work was done and materials furnished, and the character of the work and materials. All this is admitted by the answer. It does not specify the items of the work and materials, nor their quantity, except that they were of the amount and value stated in dollars and cents in the complaint. The answer denies that they were of the value mentioned; and thus puts in issue everything which the plaintiffs would have to prove to show that they amounted to as much as they
It appears that a bill of particulars was furnished by plaintiffs before the answer was put in; but it does not appear in the case, and hence, we can give it no effect. In any event, however, it formed no part of the pleadings, and did not modify their effect; its only office was to inform the defendant of the particulars of the plaintiffs’ claim and to confine them in their proofs to the items contained therein.
I am, therefore, of opinion that the referee erred, and that the judgment must be reversed and new trial granted, costs to abide event.
For affirmance, Lott, Ch. C., Gray and Dwight, CC.
For reversal, Earl, C.; Reynolds, C., not voting.
Judgment affirmed.