Majority
Headnote
L. having contracted to erect certain buildings on lands of defendant, entered into a sub-contract with G. and M. for the cellar work to be paid for when the first tier of beams should be laid, and gave them an order on defendant for the amount specified, payable to them on the completion of the sub-contract and approval of the work by L., which order was accepted by defendant. In an action to recover the amount of the order, held, that the sub-contract, order and acceptance were to be taken and construed together as one transaction; that the agreement of defendant was not to answer for the debt, default or miscarriage of another, and so within the statute of frauds, but was an original agreement by him, as a party to the contract, for a sufficient consideration appearing in the papers; and that the order and acceptance operated as an appropriation of so much of the moneys payable by defendant under his contract.The first question which demands consideration in this case is as to the effect and nature of the acceptance of the order or draft drawn by Lewis upon the defendant. The draft was drawn in favor of Gosson & Monahan, who had agreed to perform a certain portion of the work which Lewis had entered into a contract with the defendant to perform, in the erection of certain buildings upon the lands of the defendant. The order was drawn at the end of the contract of Lewis with Gosson & Monahan, for the amount to be paid to them “ on the completion' of the above contract when approved by me.” The counsel for the defendant claims that the contract created by the acceptance, if valid, was collateral to an original contract on the part of Lewis — a promise to pay the debt of another, and therefore a contract of suretyship or guarantee, and hence within the statute of frauds.
As there was no guarantee the next question to be considered is : What was the effect of the order and acceptance ? By the original contract between Lewis and the defendant, the latter was to pay Lewis $5,000, on or before the first tier of beams were on; and by the contract between Lewis and Gosson & Monahan, the sum of $3,750 was payable at the same time. This provision was modified by the acceptance of the order, and the defendant was to pay $3,750 of the amount payable, when the contract was completed, and approved by Lewis; not beyond the time when the first payment was due. The defendant made Lewis the arbitrator to decide when the work was completed; and his approval and determination was a final settlement of the question. To this extent the contract was altered by the acceptance of the order.
Although the order does not specifically refer to the contract between Lewis and Nichols in terms, yet it does refer
The defendant’s counsel urges several objections, upon the assumption that the contract was a contract of guarantee and not an independent contract, and, as I have arrived at the conclusion that it was not a contract of guarantee, it is only necessary to examine such of them as possibly may be applicable to this aspect of the case: 1. As to the extension of the time of completion of the contract, it was assented
2. It is insisted that there was a failure of the condition precedent, which required that the first tier of beams should be laid on and leveled up before any payment was to be made. The answer to this position is, that the act of the defendant prevented the laying of the first tier of beams. The walls were ready for them and the defendant was bound to have them laid within a reasonable time. Instead of this, defendant and Lewis canceled the contract by mutual consent on the twelfth of August, and Nichols sold the lots. The defendant thus made it impossible for this to be done, and he is estopped from insisting upon any such condition. (Burtis v. Thompson, 42 N. Y., 246 .)
3. It is said that the order was never assigned or transferred to the plaintiff. I do not discover that this point was
4. The point that the acceptance of the defendant was without consideration, and therefore nudum pactum, is not well taken. It does not appear to have been urged upon the trial. But even if it was, a sufficient consideration appears in the papers upon which the plaintiff’s cause of action is founded. The object of the acceptance was to assure the completion of the work mentioned in the contract, which was quite enough to establish a good consideration.
There is no other question in the case which demands comment, and after a careful examination I am satisfied that the judgment was right and should be affirmed.
Church, Ch. J., concurs; Folger, Rapallo and Andrews, JJ., concur in result.
Judgment affirmed.