Majority
Headnote
In an action to recover damages for an alleged breach by defendant of a contract to deliver plaster stone, plaintiff’s evidence tended to show that defendant contracted to ship from IT. 8. and to deliver to plaintiff, at IT. Y. or W., 3,000 tons of said stone during the season, the same to be delivered as fast as vessels could be obtained in IT. S. to carry them, to be paid for on delivery. Defendant, during the season, shipped two cargoes of the stone to IT. Y., delivery of which defendant, upon arrival, demanded and was réady to receive and pay for, but defendant refused to deliver. The court nonsuited plaintiff. Meld, error; that the right to take the whole season for delivery was limited by the provision to ship as fast as vessels could be obtained; that the proof that defendant had shipped cargoes which arrived, was evidence that it could have obtained vessels before the close of the season; also, that as plaintiff was ready to receive and pay for the cargoes which did arrive, it was no defence to the action that he was not ready to receive and pay for the balance at the end of the season.If, by the contract, the defendant had the whole season in which to deliver the plaster, and was not, under any circumstances, bound to deliver any part of it until the very close, the complaint was properly dismissed for two reasons; first, the refusal to deliver the cargoes of the “ Kedron” and “ Simpson,” which arrived in December, before the close of the season, was not a breach of the defendant’s contract, and, second, the failure of the defendant to deliver the plaster at the close of the season, gave no right of action to the plaintiff, unless he was then ready to receive and pay for it. This he was bound to aver and prove, and no proof was given upon the subject. (Porter v. Rose, 12 J. R., 209; Coonley v. Anderson, 1 Hill, 519 .) But the jury would have been authorized to find from the evidence that it was a part of the
If the plaintiff was ready to receive and pay for the cargoes of the “ Kedron ” and “ Simpson,” it is no answer to the action that he was not ready to receive and pay for the balance of the plaster remaining undelivered at the end of the season, and if the defendant is entitled to damages for any subsequent breach of the contract by the plaintiff, they may be recovered in an independent action, or they might have been made the subject of a counter-claim. (Tipton v. Feitner, 20 N. Y., 425 .)
The judgment should be reversed and a new trial granted.
All concur.
Judgment reversed.