Majority
Headnote
Defendant contracted to do the work and furnish materials in constructing tracks for the N. T. O. and H. R. R. R. Co. The contract provided “ that all stone taken from excavations which may, in the opinion of the engineer he suitable for masonry shall be deposited in some convenient place * * * to be designated by him, and shall be the property of the company.” Plaintiff entered into a sub-contract with defendant for a portion of the work. In an action to recover a balance alleged to be due thereon, defendant offered to prove that plaintiff took from excavations and used 1,149 yards of stone, and that in defendant’s final settlement with the company he was charged with the value thereof $1,546.80. This was objected to and excluded, held, no error; that the provision contemplated that the engineer should point out such stone as he deemed fit for masonry and designate the place to which he desired it removed; that plaintiff was entitled to use stone as to which no such designation was made, and as defendant did not offer to prove that plaintiff used stone so pointed out, the first part of the offer was insufficient and so properly rejected; and that the fact that a charge was made by the company against defendant for the stone, was not competent proof of his liability for it.Independently of the question of the admissibility of the evidence offered, under the answer, we are of opinion that it was properly rejected on the merits.
The clause of the contract upon which the offer was based was as follows : “ All stone obtained from excavations which may, in the opinion of the engineer, be suitable for masonry, shall be deposited in some convenient place, within eight hundred feet haul, to be designated by him, and shall be the property of the company.”
This provision necessarily contemplated that during the progress of the work the engineer should point out such stone as he deemed suitable for masonry, and should designate the place to which he might desire it to be removed. The parties must have intended that the opinion" of the engineer should
The offer which was rejected was not to prove that any stone was used by the plaintiffs which the engineer had claimed under the clause in question, or which was, in his opinion, suitable for masonry, but simply that the plaintiffs had used in the work stone taken from the excavation. There was nothing in the contract which precluded the plaintiffs from using such stone, if not claimed by the engineer and directed by him to be deposited. That branch of the offer was consequently insufficient and was properly rejected.
The second branch of the offer was clearly objectionable. The fact that in the final estimate a charge for stone taken from the excavation had been made by the company against the defendant was not competent pi’oof of liability for such stone. For all that appears in the case the charge was not a proper one.
The rejection of this offer being the only subject of exception, the judgment should be affirmed.
All concur.
Judgment affirmed.