Majority
Headnote
The legal existence of a corporation authorized to construct a railroad is at the foundation of the right to taire property for its use, under the right of eminent domain; it is a fact which it is compelled to allege in proceedings to acquire title to lands, and which may be controverted.The company making this application was organized and became incorporated under the general laws for the formation of railroad corporations in force at the time of its organization, February 3, 1869.
Every corporation formed under those laws was required by the Laws of 1867, chapter 775, section 1, to begin the construction of its road and expend thereon ten per cent, on the amount of its capital, within firm years after its articles should be filed and recorded in the office of the Secretary of State, and to finish its road and put it in operation in ten years from the time of such filing of its articles of association, and if it failed to begin the construction and make the expenditure named within the time limited for that purpose, or having made such beginning and expenditure, it failed to finish and put its road in operation within the further time allowed for so doing, then, and in either case, it was declared that “its corporate existence and powers shall cease.” The existence of the corporation was determined by the omission to comply with either of the prescribed conditions, and the omission to begin the construction and to expend the ten per cent of the capital within- the five years was as fatal as the failure to finish the road within the ten years. The statute is not susceptible of any other reading.
Reliance is placed upon an act passed in the following year for a further extension of time for constructing the road. (Laws of 1875, chap. 598.) That statute is general, and applicable to all railroad companies within its provision, and was not enacted for the benefit or relief of the appellant company by name, as were the other acts quoted.
But this company does not come "within the class of companies for which that law was enacted, or within the terms
The failure of the appellant company to begin the construction of its road within five years, and the consequent loss of the corporate powers, was condoned by the grant and acceptance of a new and extended term within which to complete the road for three years from February, 1874, and it was not, and never had been in default, for not completing and putting in operation its road. It was not in need of the relief extended by the act of 1875, and was neither within the letter or spirit of the act or the intent of the Legislature. It was then in life by virtue of a special act made and accepted for its relief, and had the two years by the private act, which was granted to other roads not thus favored by the law of 1875, and cannot have the benefit of a general law passed for roads differently circumstanced, and for purposes inapplicable to its condition.
The order must be affirmed.
All concurred, exceut Miller, J., absent, and Earl, J., not voting.
Order affirmed.