Majority
Headnote
."Defendant employed plaintiff to manufacture for him a set of circus tents, within a specified time, material to be furnished by plaintiff. No place of delivery or price was specified. Plaintiff performed, and thereafter was requested, by letter, to ship the tents to defendant at L. Plaintiff shipped them C. O. D., and they were destroyed by fire en route. In an .action to recover their value, held, that defendant was liable; that the contract, being for labor and materials, was not within the statute of fraud; that defendant’s liability did not depend upon the question as to where the technical title was, but was complete when the request to ship was made; that plaintiff had a lien upon the tents for the value of his labor and materials, and Ms retaining the lien, by shipping them C. O. D. was not inconsistent with, and did not affect, his right to enforce such liability. "Plamtiff forwarded the tents, marked to defendant at L., by steamboat to P. It did not appear but that was the usual mode of shipment to L. Held, that it could not be presumed that there was no connecting route; that the obligation was imposed upon the consignee at P. to forward by a connecting carrier; and that, as it did not appear that the loss was occasioned by plaintiff’s negligence or fault m not properly shipping the .goods, it was no defense.The action is not strictly for the sale of the article manufactured, but for work, labor, and materials, performed aud used in its manufacture (Mixer v. Howarth, 21 Pick., 205 ); and hence is not within the statute of frauds. It is undisputed that the plaintiff performed his contract, and if the defendant had refused to take the tents, an action upon the agreement would have been sustained. (Crook-shank v. Burrell, 18 J. R., 58.) There is some confusion in the authorities as to when the title passes to the purchaser in such cases. In Andrews v. Durant ( 11 N. Y., 35 ), Denió, J., lays down the rule, that in such a case “the title does not pass until the article is finished and delivered, or at least ready for delivery, and approved by such party; ” and there are other authorities to the same effect. (Grippen v. N. Y. C. R. R., 40 N. Y., 36 ; Comfort v. Riersted, 26 Barb., 473 .)
It is urged in this case that the title did not pass, for two reasons : First. Because there was no acceptance; and, second. Because the plaintiff shipped the property C. O. D., thereby refusing to deliver until the value was paid. This last ground was sustained in Baker v. Boucicault ( 1 Daly, 24 ), where certain cards were ordered to be sent to New Orleans, and were sent C. O. D., and lost at sea.
The important question to determine is when the liability of the defendant attached. If the article had burned during the progress of construction, it is clear- that no action would lie, for the reason that the contract was an entirety, and until performed no liability would exist. And this rule, I apprehend, would apply when the contract is to make and •deliver at a particular place, and loss ensues before delivery at the place, and for the same reason. But when the contract is fully performed, both as it respects the character of the article, and the delivery at the place agreed upon or implied, and the defendant is notified, .or if a specific time is •fixed, and the contract is performed within that time, upon general principles I am unable to perceive why the party .making such a contract is not liable. One person agrees to
If the plaintiff had agreed to deliver the tent in Lewiston, as a part of the contract for its manufacture, he could not have recovered anything; but this was not a part of the contract. Suppose the tent had reached Lewiston in good order, and the defendant had refused to accept or receive it, his liability would be clear and complete. As before stated, the point as to who had the title is not decisive. It may be admitted that the plaintiff retained the title as security for the debt, and yet the defendant was liable for the debt in a proper personal action. This is a case of misfortune where
The judgment must be affirmed.
All concur, except Allen and Miller, JJ., absent.
Judgment affirmed.