Majority
Headnote
Plaintiff was the owner of a bond and mortgage, by the terms of which interest was payable annually, and in case of any default in the payment thereof, for more than thirty days after it was due, plaintiff had the option to consider the whole sum secured as due. Such a default having occurred, plaintiff so elected and commenced an action of foreclosure. Negotiations were thereupon entered into between the parties for an arrangement, and plaintiff made a proposition in writing to discontinue the action and to reconsider her election, upon "condition that the mortgagors would pay the intex'est due with interest thereon and the costs of the foreclosure, would execute with one G., a subsequent mortgagee, an agreement that the whole principal should become due when, by the terms of the bond and mortgage, the first installment became due, and that interest should be paid semi-annually, and would execute to plaintiff a lease of the premises for one year without rent. The mortgagors accepted the proposition, executed a lease, paid the interest and costs, and signed the required agreement, which they retained to procure the signature of G., and plaintiff gave a receipt for the payment, stating therein that the action was discontinued. The mortgagor's did not procure the signature of G.; plaintiff then offered to accept the agreement without such signature, but the mortgagors represented that it was lost or mislaid; they refused to sign a new agreement and refused to make a semi-annual payment of interest, on the ground that interest was not due. Plaintiff discontinued the action and commenced this action to .foreclose. The mortgagors thereafter, when the annual payment of interest became due by the terms of the mortgage, tendered the amount thereof, which was accepted, without any waiver by plaintiff of the default or of the right to continue the foreclosure. Held, that the mortgagors, by refusing to execute the proposed agreement, were precluded from insisting that they were relieved from the consequences of themBy the default in the payment of the interest due April 1, 1875, for more than thirty days thereafter, the plaintiff had the right to elect to consider the whole sum secured by the bond and mortgage as due, and having elected so to consider it, she brought her action of foreclosure in May, 1875.
The mortgagors then stood in the position of debtors owing a debt past due, secured by a mortgage immediately payable. The mortgagees could, of course, defer the enforcement of the mortgage, or make any arrangement for giving time to the mortgagors which the parties might agree upon. While this was the situation, the mortgagors applied to the plaintiff to make some arrangement of the matter, and it resulted in the plaintiff, on the seventh of May, making to the defendants a written proposition to discontinue the foreclosure and reconsider her election as to the maturity of the principal indebtedness upon the conditions: First. That the mortgagors would pay the interest due April 1,1875, and the interest thereon, and the costs of the foreclosure. Second. Execute with one Greenbaum, a subsequent mortgagee, an agreement that the whole amount of the principal debtshould become due April 1, 1877, and that interest thereon should be paid semi-annually from April 1, 1875. Third. Execute to the plaintiff a. lease of the mortgaged premises for one year, without rent.
The mortgagors accepted the proposition and the parties met May 12th to complete the arrangement. The mortgagors executed the lease, paid the back interest, and the costs in the foreclosure proceedings, and signed an agreement in accordance with the arrangement, but as Greenbaum had not signed it they retained it for the purpose of procuring his signature, which they promised to procure the next day, and then send it to the attorney for the plaintiff. The plaintiff gave the morgagors a receipt acknowledging the payment of the interest and the costs of foreclosure,
The mortgagors by refusing to execute the agreement provided for by the arrangement of May 7, 1875, are precluded from insisting that they are relieved from the consequences of their default in not paying the interest due April 1, 1875. The agreement of the plaintiff to waive the default was provisional and conditional only. The undertaking of the mortgagors to pay interest semi-annually, and the whole debt in 1877, was an important consideration for the plaintiff in making the arrangement. The plaintiff accepted the interest due, the lease and the costs of the foreclosure in part execution of the agreement, but upon the express understanding that the mortgagors should immediately procure Greenbaum’s signature to the contract and return it to them. This they did not do, and finally refused to comply in any way with this provision in the agreement, or even to recognize it as effectual to change the time for the payment of the interest. They stood in the position of insisting upon the
We think the judgment should be affirmed.
All concur, except Miller, J., absent.
Judgment affirmed.