Majority
Headnote
Plaintiff contracted to furnish and put up on defendant's premises at 1, a completed machine of a specified kind, “all ready to make gas.” Defendant agreed to pay freight on the machine from New York, to furnish tank and house, and to pay §1,500 “when the works are on that ground." Plaintiff shipped the castings and materials for the machine, which defendant received and paid freight thereon, hut did not permit plaintiff to put up the machine. Held-, that an action to recover the contract price was not maintainable; that as the contract was entire and had not been performed, and as the contract price was not divisible, no recovery could be had for any portion of it.The plaintiff submitted a proposition in writing to the defendant and it was in like manner accepted. By it the plaintiff said : “I propose to furnish you, for your hotel in Luzerne, Y. Y., one of Butler’s Gas Generators and Holders. * * * The holder to be of sufficient capacity to contain fifteen hundred cubic feet of gas. To furnish all pipes to connect the generator with the holder, and the holder with the main pipe leading to the hotel; all weights and chains, sheaves and pulleys to support and balance the holder. All labor for putting up and setting the retorts, and hanging the holder, and connecting the pipes as before mentioned, and a sufficient air mixing meter, for the sum of fifteen hundred dollars. You (the defendant) are to furnish the tank and house for holder and generator and gallows frame for support of holder, to pay the freight on the machine from Yew York, and board one mechanic while putting up and connecting as above, exclusive of the cost of the machine and furnish one man to help rivet the gas-meter. , I guarantee * ■ * * that the machine shall be put up in the best and most workmanlike manner and all ready to make gas by June seventh, if your part of the work does not delay us. Payments to be $500 cash when the works are on that ground, $500 in one bond, due September 25, 1872, and $500 in one bond, due September 25, 1873, with interest.”
The plaintiff in his complaint -alleges that he “ delivered the gas-works to the defendant at Luzerne in accordance with the contract; ” avers a constant readiness on his part
Upon the trial the referee found in accordance with the complaint, and among other things, “that the plaintiff delivered the gas-works to the defendant at Luzerne, that the extra expense which the plaintiff would have incurred to set the same up and make the connections is one hundred dollars,” and, deducting that from the contract price finds, that the plaintiff is entitled to recover the balance and directs judgment therefor with interest from the 1st of July, 1871. The defendant excepted to these findings, and the exceptions, I think, are well taken. The contract is single and entire. If performed by the plaintiff he would be entitled to recover the full sum of $1,500, part in cash, part in bonds. He was not to furnish materials and perform labor upon them for the defendant, but from his own materials and by his own labor furnish to the defendant properly affixed to his premises, a completed machine of a particular kind “ all ready to make gas.”
It is not pretended that this has been done; on the contrary, the defendant has not permitted him to do it,— and as the contract price is not devisible, there is no ground on which a recovery can be had for any part of it. (Inchbald v. The Western, etc., 17 C. B. [N. S.], 733 ; Blanch v. Cocheran, 8 Bing., 14.) Mor is it in any sense true that the gas-works have been delivered to the defendant. Certain materials, among others, sheet and other kinds of iron ,• in bundles and rolls ; castings, grates, rings, retort covers, and “ one machine bottom,” which, when properly arranged and joined together may compose a machine ; where delivered by the plaintiff to a common carrier, who received, them at “ owner’s risk.” They were marked B. C. B., or B. C. B. for B. C. Butler, Luzerne, N. Y., and the defendant paid the freight upon
All concur.