Majority
Headnote
By the terms of a contract for the sale of certain lands by defendant to plaintiff, the latter agreed to pay a portion of the purchase by executing and delivering his bond, secured by mortgage on the premises, and the remainder in cash, “ on delivery of the deed on the first day of April, A. D. 1879, ’ at a place specified; defendant “on receiving such payment at the time, and in the manner above mentioned,agreed to deliver a deed. At the time and place specified the parties met; defendant produced a deed bearing date February 19 1879, .the day the contract was executed; plaintiff produced and handed to defendant the bond apd mortgage, and had a certified check for the cash payment called for; neither party made a tender. Defendant claimed that he was entitled to interest on the whole purchase-money from the date of the contract; after discussing the subject, he and his counsel left the room for consultation, and upon their return, defendant offered to carry out the contract according to its terms; he neither expressly withdrew his construction of the contract, or intimated that he had changed his mind, and made no proposal to change the date of the deed In an action to compel specific performance, held, that the action was maintainable without a formal tender; that defendant having taken an untenable ground, if he changed his views, or receded from his position, he was bound to notify plaintiff, and his refusal to pass the title, except upon payment of the interest claimed, was a good excuse for not making such tender.It is not .disputed, and the judge before whom this ease was tried found among other things that at the time and place fixed by the contract the parties met, and the defendant produced a deed of the premises mentioned, executed by himself and wife, and dated February 19, 1879, but did not formally tender the same to the plaintiff; that it was • then and there claimed on behalf of the defendant, through his agent .and counsel, that the true construction of the contract was. that the interest should b¿ paid on the whole purchase-money from February 19th, and that there was no express or affirmative withdrawal of the construction so insisted upon. The evidence and the findings also establish that after discussing the subject the defendant and his counsel retired to another room for consultation, and upon their return the defendant offered to carry out the contract according to its terms. He made no remark, and gave no indication whatever that he had changed his. mind as to the construction of the contract in respect to the interest, and made no proposal to change the date of the deed.
The defendant was clearly wrong as to the interest, and was we think bound to say so if he had changed his conclusion on the subject. He had withdrawn to consider that question and upon his return was clearly called upon to speak on the subject, and to express his views if they were changed, so that the plaintiff could know and understand that such was the fact. By his silence he assented to the idea that he still maintained his former position, and the plaintiff would naturally and necessarily infer that such was the case. Having thus led the plaintiff to such a reasonable conclusion he has no ground for complaint that the plaintiff did not tender either the money or the mortgage. On the start, and throughout, his attitude was that he had a right to interest from the 19th of - February, and from this position he never receded. Upon his return he did not even hesitate.' He said he would fulfil according to
For the reasons stated without considering the other questions raised, the order of the General Term should be affirmed and judgment absolute ordered for the plaintiff.
All concur.
Order affirmed and judgment accordingly.
Cases cited
- Kent v. Manchester 29 Barb. 595 p. 107
- Welles v. Yates 44 N. Y. 525 p. 107
- Savino v. Merchants Mutual Insurance 44 N. Y. 625 p. 108
- Haight v. Child 34 Barb. 186 at 191 p. 108
- Myers v. De Mier 52 N. Y. 647 p. 108, p. 109