Majority
Headnote
Where a valid contract has been entered into, on behalf of the State by its duly authorized agents, for the construction of a public work, it cannot, in the absence of any stipulation authorizing it so to do, destroy or avoid the obligation of the contract.By the act chapter 427 of the Laws of 1870, the building of the State Reformatory at Elmira was provided for, and the governor was authorized to appoint five persons to act as a board of building commissioners, who were empowered to purchase the site and proceed with the erection of the buildings for the reformatory, and were charged with the general superintendence of the grounds and the design and construction of the buildings. Pursuant to the provisions of the act, the governor appointed five persons to act as such building commissioners, who afterward, in' the year 1871, entered into several contracts relative to the work to be done by them, three with George W. Aldridge and three with John Kiley. These contracts were all let to the lowest bidders for the work and materials, and there was uncontradicted proof tending to show that they were fairly let and made upon terms then favorable to the State. "After they were made, they were all, with the consent of the commissioners, assigned to George D. Lord and Charles A. Danolds, who proceeded to perform them. They continued in the performance of the contracts until the year 1874, having prior to that time done work and furnished materials under them, for which they had been paid a large sum, when by the act chapter 323 of the Laws of 1874, and the action taken thereunder, the further performance of their contracts was arrested. At that time they had on hand a
Under the act of 1874 a superintending builder was appointed by the governor to take charge of the construction of the reformatory, and he refused to permit Lord and Danolds to complete their contracts, and he advertised for bidders and let the remaining work to other contractors, who completed the same. Thereafter Lord assigned all his interest in the contracts and in the claims against the State on account thereof to Danolds, who in 1878 presented a claim to the State board of audit for damages for breach of the contracts on the part of the State. The damages so claimed were mainly for prospective profits which the contractors would have made if they had been permitted to perform their contracts according to their terms and conditions. The claim was heard before the board of audit, and in April, 1879, it awarded to the claimant $65,000. From this award under the act chapter 211 of the Laws of 1881, the attorney-general on behalf of the State appealed to the General Term of the Supreme Court, where the award was affirmed and then he appealed to this court. The attorney-general here asks for a reversal of the award upon several grounds which for convenience will be considered under separate heads.
First. He claims that the commissioners appointed and acting under the act of 1870 had no authority to make the contracts. Under that act they were to purchase the land for the site of the reformatory and take the deed therefor to the people of the State. Upon the site thus purchased the reformatory was to be constructed and it was to belong to the State. The State was to furnish the money for its construction, which they were fully authorized and empowered to expend. There was no limitation placed upon their powers and there was no specification in the act as to the manner in which they should proceed in the expenditure of the money or in the construction of the buildings. They were the selected agents of the State, clothed with all the power necessary and usual for the discharge
Second. It is further claimed that these contracts contain provisions which defeat the claim for the prospective profits. One of the contracts contains this clause: “ It is further mutually understood and agreed that, in case the execution of this contract shall be suspended by the parties of the second part at any time and for any' cause, no claim for prospective profits on work not done .shall be made or allowed; but the party of the first part shall have the right to complete the work when the party of the second part shall order it to be resumed ; ” and the other contracts contain provisions somewhat similar. These provisions did not authorize or contemplate the entire abrogation or repudiation of the contracts on the part of the State and an absolute arrest of the performance thereof. Then, too, if the language “the parties of the second part ” found in these contracts is to be taken as meaning the building commissioners personally, it may be said that the execution of the contract was not suspended by them ; but it was suspended by the act of 1874 and the action taken under that act. If by the parties of the second part the State was meant, then that provision cannot protect the State from liability for the prospective profits, because the contractors were denied the right to complete the work when it was resumed.
The contracts contain another provision substantially like this: Whenever the quantities of work, or any of them, shall in
There was another provision in one or more of the contracts as follows : “ It is further understood that in the event of the suspension of the work mentioned in this contract for the period of six months, by reason of the legislature failing to make the necessary appropriations to carry on the same, the party of the second part shall direct the superintendent and engineer to make up an estimate and account to the time of such suspension and present them to the commissioners, who shall review them, and when correct and satisfactory, shall proceed, if in funds, to pay the same, including the percentage reserved up to the time of such suspension. ” Here there was not a case of suspension of the work within the meaning of this provision; but the contracts were entirely repudiated. This provision was intended simply to secure to the contractors full payment up to the time of suspension for all the work they had done, including the percentage reserved under the contracts, and nothing more.
It will be seen by a careful reading of the contracts that there is nothing in them which authorized the agents of the State to repudiate them or to absolutely arrest their performance without liability for damages. The contracts were binding upon the State; it could refuse to perform them on its part and arrest the performance of them by the contractors, but it could in no way destroy or get rid of the obligation of them, and so it was substantially held in the case of Lord v. Thomas.
Third. It is further claimed (and this claim presents the important question to be considered in this case) that the State
■ As was well said by Judge Allen, in People v. Stephens ( 71 N. Y. 549 ), “ There is not one law for the sovereign and another for the subject, but when the sovereign engages in business and the conduct of business enterprises, and contracts with individfials, whenever the contract in any form comes before the courts, the rights and obligation of the contracting parties must be adjusted upon the same principles as if both contracting parties were private persons. Both stand upon equality before the law, and the sovereign is merged in the dealer, contractor and suitor.” So far as is needful, the sovereign can protect itself against prospective profits by stipulations in its
These contracts were protected, not only under the constitutional provision referred to, but the right to these prospective profits, any advantage of value under them, was a species of property finding protection under both the Federal and State Constitutions, in the provisions that private property shall not be taken for public use without just compensation.
There is no common and universal usage in this State which denies the liability of the State for prospective profits which may be claimed under contracts made with it. It is matter of common knowledge that such profits have frequently been allowed and sanctioned by the legislature of this State. It has undoubtedly been usual in such contracts to provide against liability for prospective profits, and the very fact that such provision has been deemed necessary in such contracts evinces the understanding that but for such provision the liability would exist.
, Under the act chapter 55 of the Laws of 1870, entitled “An act to abolish the contracting board and the system of repairing the canals by contract,” contractors for repairs on the canals were authorized to surrender their contracts, and the canal board was also authorized to cancel such contracts; but it was specially provided that, in a case of a surrender or cancellation of any contract, the contractors should not be entitled to demand or receive, and should not be allowed for any prospective damages or any compensation for any prospective or unearned profits. It is probable that in the contracts dealt with by that act there was a provision authorizing the canal officials, upon the terms specified in the contracts, to cancel them, and the fourth and fifth sections of that act were simply intended
To deny the right or power of the State to arrest the per formance of its contracts without liability for prospective profits in no way impairs its sovereignty. It may repudiate its contracts, it may refuse to perform them, but its sovereign right to destroy or impair the obligation of them is limited by the Federal Constitution. It may refuse to respond in damages and leave a claimant without any remedy, as it may refuse to pay its bonds; but the obligation remains. No legislative fiat can destroy or impair that.
The doctrine contended for by the attorney-general finds no sanction in the decisions of the Federal courts. In United States v. Speed ( 8 Wall. 77 ), the war department, by its proper officers, entered into a contract with Speed to furnish fifty thousand hogs to be slaughtered at a stipulated price, and only a small quantity of the hogs were furnished, and Speed presented to the Court of Claims a claim for damages for a breach of the contract on the part of the government, and the Court of Claims held that the true measure of damages was the difference between the cost of doing the work and what the claimant was to receive for it, making reasonable deduction for the less time engaged and for release from the care, trouble, risk and responsibility attending performance of the whole contract. Upon appeal from the judgment of the Court of Claims to the Supreme Court of the United States, Mr. Justice Miller, reading the opinion, approved the rule as laid down by the Court of Claims and said: “ We do not believe that any safer rule, or one nearer to that supported by the general current of authorities, can be found than the one adopted by the court,” and he cited the case of Masterton v. The Mayor (supra), as the leading case in this country on the subject. There was no intimation in that case by the counsel or court that a claim for prospective damages could not be made against the government.
There are cases in the Court of Claims such as Jones and Brown’s Case (1 Court of Claims, 383), and Deming’s Case (id. 190), and Wilson’s Case (11 id. 513), in which it has been broadly laid down that the government as a contractor cannot be held liable for the public acts of the government as the sovereign, and that whatever acts the government may do, be they legislative or executive, so long as they be public and general they cannot be deemed to alter, modify, obstruct or violate the particular contracts into which it entered with individuals and thus subject it to liability for damages to individuals. But if
Hothing was decided adverse to the view we have expressed . in the case of McKee v. The United States (12 Court of Claims, 504, and 7 Otto, 233). In that case in 1864 A. entered into two contracts with the United States to deliver a specified number of tons of hay at Fort Gibson and other points within the Indian Territory, which was then the theatre of hostilities, which contracts contained this clause : “ It is expressly understood by the contracting parties hereto that sufficient guards and escorts shall be furnished by the government to protect the contractor while engaged in the fulfillment of this contract.” He cut hay within that territory and payments were made to him for that which he delivered and for that which, with other personal property, had been destroyed by the enemy; and having been prevented by the enemy from there cutting all the hay necessary to fulfill his contract, he sued to recover an amount equal to the profits he would have made had the contract been fully performed, and he alleged the United States did not “ furnish sufficient guards and escorts for his protection in the cutting and delivery of said hay; ” and it was held in the Supreme Court that the contract was for the sale and delivery of hay arid not for the cutting and hauling of grass; that the obligation of-the United States to A. was not that of an insurer against any loss he might sustain from hostile forces, but it was to protect his person and property while engaged in the effort to perform his contract, and that A. was entitled to the full value of the property actually lost by him, and having been paid therefor, his petition should be dismissed. It is thus seen that that case turns entirely upon the construction of the contracts there under consideration, and no claim was made therein by any one that the same rule as to damages did not apply to the government which applies to individual contractors.
In Jones v. Judd ( 4 N. Y. 411 ) the rule as to prospective profits laid down in Masterton v. The Mayor is fully recognized and reiterated, and that case gives no support to the contention on the part of the State in this case. A law of a general and public character, rendering it impossible for an individual to perform his contract, may excuse performance. But a law can never be upheld or have any effect, the special purpose of which is to annul or impair contracts.
I now repeat that it has never been decided in any case in this country that has come to my knowledge, and it has never been said by any judge so far as I can find, that the sovereign cannot be made liable for prospective profits when it has arrested the performance of its contracts precisely as individuals could be made liable for such profits.
The damages claimed here are, within the meaning of the law, actual damages; they are not speculative, remote, contingent or uncertain; they are capable of very precise estimation. The moment these contracts were signed, being valid and binding upon both parties, whatever value was in them belonged to the contractors; and when by the act of the State the contractors were deprived of that value, they suffered actual damages, for which upon general principles of law and justice they should receive indemnity.
The State board of audit was constituted by the act chapter 444 of the Laws of 1876. By section 2 of that act the board was to hear all private claims and accounts against the State excepting such as were required to be heard by the canal appraisers, and to “ determine on the justice and amount thereof
By the act chapter 211 of the Laws of 1881, an appeal was authorized to the General Term, and jurisdiction was conferred upon that court to decide, adjudicate and determine the action between the claimant and the State upon both the law and the facts “ as shall be equitable and just,” and thus the General Term was clothed with the same power possessed by the board of audit; and who can say that it was not equitable and just for the General Term to adopt the-same measure of damages between the claimant and the State as would be applied in litigations between individuals ? We cannot say, therefore, that there was any error of law in the decisions made by the board of audit and the General Term.
We do not understand that there is any contention that any error was committed upon the facts. We must take these contracts as we find them; they may have been extravagant; but there is no proof that they were, or that they were founded in fraud or collusion. No proof whatever was adduced on the
The judgment should be affirmed, with costs.
All concur, except Tracy, J., who took no part.
Judgment affirmed.
Cases cited
- Britton v. Mayor of New York 21 How. Pr. 251 p. 38, p. 39
- Easton v. Pickersgill 55 N. Y. 310 p. 38
- Fort v. Burch 6 Barb. 60 p. 38
- The Apollon 9 Wheat. 362 p. 38
- Lansing v. Smith 4 Wend. 9 p. 38
- Gibbons v. United States 8 Wall. 269 p. 38
- Calking v. Baldwin 4 Wend. 667 p. 38
- Lansing v. Smith 8 Cow. 146 p. 38
- Mayor of New York v. Second Avenue Railroad 32 N. Y. 261 p. 39
- Corporation of Brick Presbyterian Church v. Mayor of New York 5 Cow. 538 p. 39
- Munn v. Illinois 94 U. S. 113 p. 39
- In re Union Village & Johnsonville Railroad Co. 35 How. Pr. 420 p. 39
- Griffin v. Colver 16 N. Y. 489 at 494-5 p. 39
- United States v. Speed 8 Wall. 77 at 84-5 p. 39, p. 47
- Lord v. Thomas 64 N. Y. 107 at 109 p. 39, p. 42
- People v. Stephens 71 N. Y. 527 at 549, 550 p. 39
- Conner v. Mayor 2 Sandf. 355 p. 40