This is a condemnation proceeding and the principal question is: Must plaintiff obtain the approval of the State Water Resources Commission before condemning defendant’s property?
Plaintiff-respondent Great Neck Water Authority (hereafter called “ Authority ”) is a public benefit corporation organized in 1959 under the “ Great Neck Water Authority Act ” (Public Authorities Law, tit. 7-A), empowered by the act to supply and sell water within a Water Authority District which comprises what is known as the Great Neck Peninsula in the Town of
Defendant Citizens Water Supply Company of Newtown, a corporation (hereafter called “ Company”), supplies and sells water within a territory coterminous with, or nearly coterminous with the Great Neck Water Authority District. Company owns and operates a water supply plant and business with appropriate franchises and property. In other words, Company is using its franchises and tangible property to supply water within the Authority’s district and Authority’s petition is to be allowed to condemn all Company’s property so as to operate it as a governmentally owned utility.
Company served an answer to the condemnation petition, pleading these defenses: that the petition does not sufficiently show that the taking is for a public use, that the statutorily limited borrowing power ($3,000,000) of Authority is inadequate to compensate plaintiff for the full value of its property sought to be condemned, and that the proceeding is prematurely brought in that Authority did not in good faith attempt before bringing the proceeding to negotiate with Company for the acquisition of the property. After so pleading Company moved for summary judgment on another ground, that is, that Authority had not before commencing the proceeding obtained the prior approval of the State Water Resources Commission for the taking. Authority cross-moved to strike all the defenses for insufficiency, and prayed for summary judgment of condemnation.
The Nassau County Court denied both summary judgment motions but struck out as insufficient in law all the defenses except the one alleging a failure to negotiate, the court being of the opinion that this raised a question of fact. After examining
Company alone appealed to the Appellate Division which dismissed so much of the appeal as sought to reinstate the defenses stricken from Company’s answer. The Appellate Division held that this part of the order was, by reason of section 19 of the Condemnation Law, not appealable. The County Court’s denial of defendant’s summary judgment application was affirmed by the Appellate Division which ruled that the Conservation Law did not require prior commission approval for such an acquisition as is here attempted. The two Appellate Division Justices who dissented thought that this was such an acquisition of a “ water supply ” or a “ water supply from an existing approved source ” as to be included in the requirement of commission approval stated in section 450 (subd. [1], par. [a]) of the Conservation Law. The conflicting views of the Justices at the Appellate Division set up the principal issue on the appeal to this court.
Before discussing that issue we will take up the question of appealability. Company argues that the Appellate Division committed error in dismissing Company’s appeal from the striking of three of the defenses pleaded in its answer. As to this, we agree with the Appellate Division. It is now settled that section 19 of the Condemnation Law, here applicable, means that no intermediate order made in the course of such a proceeding (including an interlocutory judgment of condemnation) is appealable unless it involves a fundamental jurisdictional question as to the petition’s sufficiency or a triable issue of fact determination of which against petitioner would render the petition fatally defective (Matter of Thomson, 86 Hun 405 , affd. 147 N. Y. 601 ; Matter of Manhattan Ry. Co. v. O’Sullivan, 6 App. Div. 571 , affd. 150 N. Y. 569 ; City of Buffalo v. Hayman, 283 App. Div. 1010 , motion for leave to appeal dsmd. 307 N. Y. 685 ; City of Albany v. Yaras, 1 A D 2d 989 , affd. 2 N Y 2d 844 ; City of Albany v. Yaras, 6 N Y 2d 749 ; City of Buffalo v. Ferry
The remaining question is: Was approval by the Water Resources Commission a prerequisite to the bringing of this condemnation proceeding? We think it was. The pertinent part of section 450 of the Conservation Law (as amd. in 1960 and as applicable to this proceeding) reads thus: “ (1) No person or public corporation authorized and engaged in, or proposing to engage in, the acquisition * * * use and distribution of water for potable purposes * * * shall have any power (a) to acquire or take a water supply or an additional water supply from an existing approved source; or (b) to take or condemn lands for any new or additional sources of water supply or for the utilization of such supplies; or * * * until such person or public corporation has first submitted the maps and plans therefor to the Commission, as hereinafter provided, and until the Commission shall have approved the same, or approved the same with such modifications as it may determine to be necessary as hereafter provided.” Although the phrase “ water supply” is not defined in the statute, it reasonably includes such a complex of lands, waters thereunder, structures and equipment as is owned by Company and used by it in selling water to the public. Section 450 thus requires permission for the taking of a water supply owned by an existing corporation as well as for the acquisition of an additional water supply from an existing approved source or of lands for a new or additional water source or the utilization thereof. Whether we regard Company as the owner of a “ water supply ” or of a “ water supply from an existing approved source ” or both, the statute applies. The fact that Company previously received commission approvals of its facilities and water sources does not make a new consent unnecessary for a transfer or condemnation. Such a construction of the Conservation Law is necessary to carry out the legislative purpose of giving the Water Resources Commission broad regulatory powers over the potable
Authority’s argument, as well as decisions below, bases itself largely on Village of Waverly v. Waverly Water Co. ( 117 App. Div. 336 , affd. 189 N. Y. 555 , supra). But the Waverly case was decided under an earlier statute (L. 1905, ch. 723) which made commission approval necessary only as a preliminary to the power “ to acquire, take or condemn lands for any new or additional sources of water supply”. In 1907 the Waverly case came down with its holding that this provision did not apply to the transfer of a fully equipped and operating water plant. In 1911 the commission’s annual report recommended to the Legislature “ That the acquisition of private water companies by other private water companies, or by municipalities or the consolidation of private water companies without the consent of the Commission be prohibited” (p. 19). In the same year the Legislature responded (ch. 647) by inserting the language above quoted requiring submission of plans to and approval by the commission before any prospective supplier should have power “ to acquire, or to take a water supply.” The Attorney-General’s brief tells us that, ever since the 1911 statutory change, the commission has considered the Waverly case as having been overruled, that all or nearly all applicants have acted on that same belief and that the commission has dealt with petitions for such approvals in some 25 cases from 1914 to 1961.
So much of the Appellate Division order as denies defendant’s motion for summary judgment of dismissal should be reversed, with costs to defendant in this court and in the Appellate Division, and the motion granted; otherwise, the order should be affirmed; first and second certified questions answered in the negative, third certified question not answered.
That part of the order which affirms the denial of defendant’s motion for summary judgment dismissing the petition reversed, with costs to defendant in this court and in the Appellate Division, and the motion granted; otherwise, the order affirmed in all respects. First and second questions certified answered in the negative; the third question certified not answered.
Cases cited
- Sweet v. City of Syracuse 129 N. Y. 316 p. 169
- City of Syracuse v. Gibbs 283 N. Y. 275 p. 169, p. 170
- Bloodgood v. Ayers 108 N. Y. 400 p. 169, p. 170
- Pixley v. Clark 35 N. Y. 520 p. 169
- Barkley v. Wilcox 86 N. Y. 140 p. 169
- Forbell v. City of New York 164 N. Y. 522 p. 169, p. 170
- Hathorn v. Natural Carbonic Gas Co. 194 N. Y. 326 p. 169, p. 170
- People v. New York Carbonic Acid Gas Co. 196 N. Y. 421 p. 169, p. 170
- Village of Waverly v. Waverly Water Co. 189 N. Y. 555 p. 169, p. 170, p. 173, p. 175
- Ferraiolo v. O'Dwyer 302 N. Y. 371 p. 169
- Kaskel v. Impellitteri 306 N. Y. 73 p. 169
- Cuglar v. Power Authority 4 Misc 2d 879 p. 169
- Cuglar v. Power Authority 3 N Y 2d 1006 p. 169
- Sage v. City of Brooklyn 89 N. Y. 189 p. 169
- Brewster v. J. & J. Rogers Co. 169 N. Y. 73 p. 169, p. 171
- In re Yaras 308 N. Y. 864 p. 169
- City of Albany v. Yaras 2 N Y 2d 844 p. 170, p. 173
- City of Albany v. Yaras 6 N Y 2d 749 p. 170, p. 173
- In re City of Rochester 102 App. Div. 99 p. 170
- In re Broadway & Seventh Avenue Railroad 69 Hun 275 p. 170
- Erie Railroad v. Steward 59 App. Div. 187 p. 170
- City of Jamestown v. Sfetko 15 A D 2d 403 p. 170, p. 174
- Ohio Oil Co. v. Indiana 177 U. S. 190 p. 170
- Dunbar v. Sweeney 230 N. Y. 609 p. 170
- In re the Board of Water Supply ex rel. City of New York 211 N. Y. 174 p. 170
- Hotel Ass'n of New York City, Inc. v. Weaver 3 N Y 2d 206 p. 171
- Ferguson v. Village of Hamburg 272 N. Y. 234 p. 171
- Spring Valley Water Works & Supply Co. v. Wilm 14 A D 2d 658 p. 171
- In re Thomson 86 Hun 405 p. 173
- Manhattan Railway Co. v. O'Sullivan 6 App. Div. 571 p. 173
- City of Buffalo v. Hayman 307 N. Y. 685 p. 173
- City of Buffalo v. Ferry-Woodlawn Realty Co. 8 N Y 2d 983 p. 174