Majority
The present claim for moneys due under a contract involves the interpretation of the contract and three subsequent agreements extending claimant’s time for completing performance under the contract.
' On September 15, 1955 the parties entered into a contract whereby claimant was to do certain construction work in connection with New York State highways. The contract provided that claimant’s work was to be completed on or before December 1, 1956, and that engineering and inspection expenses incurred
In the Court of Claims claimant successfully contended that the statement in the third extension agreement, ‘1 Extension is granted to: August 1, 1958 with engineering and inspection charges, after December 31, 1957 ”, was an agreement by the State not to make such charges for the period prior to December 31, 1957. However, the evidence is insufficient to support that court’s finding that claimant had been induced to believe that the State would not assess any engineering or inspection charges for that period. Not only did he specifically agree, in all three applications for extensions of time, to bear such charges “ from the completion date originally fixed in the contract to the final completion of the contract ” but he was also informed by the defendant that the extensions were granted with these engineer
This is not a case in which an innocent promisee relies on the terms of a promise to his detriment. In those eases “ The promise, if uncertain, was to be taken in the sense ‘ in which the promisor had reason to suppose it was understood by the promisee ’ ” (United States Rubber Co. v. Silverstein, 229 N. Y. 168 , 171). Here the claimant did not complete his contract in reliance on the fact that he would not incur engineering charges prior to December 31,1957. The completion of his performance was an obligation incurred under the original contract. The contract provided that, if the job were not completed by December 1, 1956, engineering and inspection expenses incurred by the State could be charged to claimant and deducted from the final moneys due. The State was not required to grant the extensions of time, and the fact that it did so, subject to the charges in question, cannot give claimant any greater rights under the contract merely because he thought, through some “ secret operation of his own mind ” (Wood v. State of New York, 15 A D 2d 723 , 724), that the State was granting him an extension without prior charges. What the claimant thought the State meant by its third extension letter is of no importance, since it did not change his obligations under the contract. His reliance on this belief was at his own risk. Claimant testified that he knew, at the time he signed the final agreement, that some engineering charges were going to be deducted, but he did not know the amount. Claimant could have ascertained the charges incurred for engineering and inspection before signing the final agreement, if he had requested the information, but he did not. Under those circumstances, claimant was not justified in relying on his interpretation.
Since, therefore, the trial court’s finding that claimant’s version of the third extension agreement became a part of the final agreement is rebutted by the documentary evidence, the State is not bound by the claimant’s impression of the agreement.
Accordingly, the judgment appealed from should be reversed and the claim dismissed, with costs in all courts.
Judges Dye, Fuld, Fboessel, Van Voobhis and Fosteb concur with Judge Bubke ; Chief Judge Desmond dissents and votes to affirm because on the whole record the issue was one of fact put beyond our reach by the affirmance of the Appellate Division.
Judgment reversed, etc.
Cases cited
- Homer v. Guardian Mutual Life Insurance 67 N. Y. 478 p. 26
- Clark v. Dales 20 Barb. 42 p. 26
- Weed v. Spears 193 N. Y. 289 p. 26
- Smith v. Board of Education 208 N. Y. 84 p. 26
- O'Keeffe v. City of New York 176 N. Y. 297 p. 26
- Rusciano & Son Corp. v. State 201 Misc. 690 p. 26
- Rapid Transit Subway Construction Co. v. City of New York 259 N. Y. 472 p. 26
- Harrington v. Harrington 290 N. Y. 126 p. 26
- Drivas v. Lekas 292 N. Y. 204 p. 26
- Duane Jones Co. v. Burke 306 N. Y. 172 p. 26
- United States Rubber Co. v. Silverstein 229 N. Y. 168 at 171 p. 26, p. 28
- Debes v. Monroe County Water Authority 16 A D 2d 381 p. 26