Majority
OPINION OF THE COURT
The issue before us is whether the parties’ disputes should be resolved by arbitration or litigation. Appellants, seeking arbitration, urge that respondents are bound by written agreements to arbitrate, while respondents contend that any right appellants may have had to arbitrate has been lost by extensive courthouse proceedings, and in any event would be defeated by the fact that one of the parties — a public agency — never
At the hub of the controversy is a December 1972 limited partnership agreement (the RPC Agreement) for the development of a housing project near Riverside Park in New York City. The partnership, organized pursuant to the Private Housing Finance Law, is known as RPC Associates. Richard Sherrill, Louis Yavner and Daniel Gray served as the managing general partners; Riverside Park Community (Stage I), Inc., a limited-profit housing company (or Mitchell-Lama company) under article II of the Private Housing Finance Law, became a general partner; and several private investors were limited partners.[1] The partnership, as well as the project, were subject to oversight by the City of New York Housing Preservation and Development Department (HPD), the agency charged by law with supervisory responsibility for limited-profit housing companies in New York City. While HPD was not itself a partner or even a signatory to the partnership agreement, the agreement provided that so long as the project was encumbered by a mortgage held by the City or by HPD it could only be changed by a writing executed by all partners, with the consent of HPD. The partnership agreement expressly forbade disposition of the general partners’ interests except as provided in the agreement, and restricted any act by them directly or indirectly affecting the project unless required or approved by HPD. The agreement further provided that any dispute or controversy between the partners arising out of, or in connection with, the partnership would be determined by arbitration. A second agreement was executed in January 1975 concerning another Manhattan housing project (the “60th Street Agreement”). That agreement required arbitration of all disputes “based upon or arising out of this Agreement or its performance.”
As a result of acrimony between Sherrill and Gray, the RPC managing general partners attempted to modify these arrangements. On December 29,1976, by a series of four brief, informal documents allegedly prepared and even typed by Gray, none of
1 As part of a program to provide housing and induce private investment through tax incentives, the Private Housing Finance Law contemplates the organization of limited-profit housing companies, which may serve as general partners in limited partnerships with private investors. Consistent with this statutory scheme, Riverside Park Community (Stage I), Inc., the legal owner of the housing project, became a general partner in RPC Associates, which owns the equitable interest.
Whether Sherrill indeed withdrew is the subject of vigorous controversy on the merits, with Sherrill and Yavner aligned on one side, contending that his relationship never actually terminated because neither HPD nor the limited partners consented to his withdrawal from RPC Associates, and Gray, contending that Sherrill’s “retirement” needed no consent, on the other.[2] Whether this issue, and consequential issues, must be resolved by arbitration or litigation is the subject of this appeal.
The first move was Sherrill’s: in 1978 he brought suit to rescind one of the December 29,1976 agreements regarding the 60th Street project and recover his payments. The sole theory of recovery is that the package of December 1976 agreements rested on a mistaken belief then held by all three RPC general managing partners that Sherrill could withdraw as a general partner of RPC when in fact he could not obtain the necessary consents of HPD and the limited partners. For nearly three years this litigation proceeded, with no mention of arbitration. Gray filed a general denial, initiated his own action in May 1980 for an accounting and injunction against Sherrill and Yavner, which was dismissed for failure to prosecute, conducted a deposition of Sherrill during which he inquired into the RPC Agreement, pursued document discovery, and then secured both am order to take discovery of Yavner and his joinder as an additional defendant.
In November 1981, Gray served two arbitration demands — one on Sherrill and Yavner as managing general partners of RPC Associates annexing the RPC Agreement, and a second on
2 For simplicity, the parties will be referred to as Gray, representing appellants, and Sherrill, representing respondents. Gray and certain companies and individuals associated with him are appellants; Sherrill and his associated companies, as well as Yavner, HPD, Riverside Park Community (Stage I), Inc., and the limited partners share respondents’ position.
On the very day the arbitration demand relating to the 60th Street project was served, Gray subpoenaed Yavner for examination in the pending litigation. Gray completed the deposition of Sherrill, conducted the deposition of Yavner, and the parties exchanged approximately 100,000 documents. Complete discovery of all issues raised by the pleadings was the stated objective. At least five Judges, in response to Gray’s motions in part premised on the contention that the various agreements were interrelated and thus material, directed that examinations be given, or documents produced, or other relief afforded.
To complete the procedural mosaic, in October 1982 Sherrill commenced a second action, this time seeking a declaratory judgment that he remains a managing general partner as well as limited partner of RPC Associates, and that his attempt to withdraw was ineffective because of a failure to obtain necessary consents. As Gray’s counsel himself later pointed out in a motion to compel arbitration, Sherrill’s 1982 litigation has “a companion action seeking the same result, which has been pending in this Court since 1979.”
The court below on its own motion consolidated Sherrill’s two suits, perceiving that a “unity of discovery and procedure can effect an efficient resolution of the confusion over Sherrill’s status in RPC and all of the issues which have been born of that confusion.” (99 AD2d, at p 967.) The propriety of the consolidation is not before us. Also not before us is the propriety of an earlier order joining HPD as a party defendant in the litigation, the combined result of consolidation and joinder being that there will now be a single litigation joining all interested parties — assuming the courthouse is the appropriate forum. The court below, further, permanently stayed arbitration, concluding that either directly or indirectly the parties had all chosen the courtroom for resolution of their dispute. On that issue, which is before us for review, we affirm.
Gray contends that the activity in Sherrill’s initial suit is without consequence because that action sought only rescission of a two-page profit-sharing agreement which did not provide for arbitration, and issues concerning the right to remain as an RPC managing general partner and participate in the 60th Street venture were raised only in his arbitration demands. To be sure, not every difference between the parties was subject to arbitration, but only those arising under the agreements providing for arbitration (Matter of Priore [Schermerhorn], 237 NY 16 , 17). There can be no doubt on this record that the pivotal issue in the litigations as well as the arbitrations — made all the mor e evident upon consolidation — is the purported modification of the underlying agreements by Sherrill’s attempted termination, resignation or retirement, an issue arising out of or in connection with the partnerships and therefore under the agreements subject to arbitration (see, Matter of Hosiery Mfrs. Corp. v Goldston, 238 NY 22 , 27-28; see also, Matter of Schlaifer v Sedlow, 51 NY2d 181 ). This issue was pointedly presented by Sherrill’s initial complaint alleging that the 1976 agreement he sought to rescind was premised on mutual mistake regarding his withdrawal from RPC Associates, and that his attempt to resign was a nullity, all of which Gray put in issue by his general denial.
Even if there were no basis for assertion of Gray’s right to arbitration by way of immediate response to Sherrill’s first action, still that right emerged as Gray litigated, well before his
Not every foray into the courthouse effects a waiver of the right to arbitrate. Where claims are entirely separate, though arising from a common agreement, no waiver of arbitration may be implied from the fact that resort has been made to the courts on other claims (Denihan v Denihan, 34 NY2d 307 , 310). Moreover, where urgent need to preserve the status quo requires some immediate action which cannot await the appointment of arbitrators, waiver will not occur where plaintiff “moves in court for protective relief in order to preserve the status quo while at the same time exercising its right under the contract to demand arbitration” (Preiss/Breismeister Architects v Westin Hotel Co., 56 NY2d 787 , 789; but see, Hadjioannou v Avramides, 40 NY2d 929 ). But this is not such a case. The same issue lies at the heart of the litigations and proposed arbitrations, and no reason is even suggested to permit prosecutions in both forums.
The court below declined to fix the precise act constituting Gray’s election to pursue litigation, as do we: “it is enough that the totality presented here is so conclusively waiver that it ‘may not be unilaterally recalled.’ ” ( 99 AD2d 965 ,968 [quoting Rusch Factors v Fairview Mfg. Co., 34 AD2d 635 ].) Both prior to and after the arbitration demands in November 1981, Gray affirmatively sought the benefits of litigation, by actions inconsistent with a claim that the dispute must be resolved only by arbitration. Parties electing the benefits of arbitration, including freedom from disclosure in accordance with the CPLR, from strict application of substantive principles of law and evidentiary rules, and from judicial review for errors of law and fact (see, Matter of Silverman [.Benmor Coats], 61 NY2d 299 , 308) cannot also draw on the judicial process for a particular advantage,[3]
3 By the same token, a party seeking to stay arbitration, in favor of litigation, cannot participate in the arbitration on the merits. (CPLR 7503 [b]; see also, Matter of Beagle [MVAIC], 19 NY2d 834 , 835.)
Finally, Sherrill urges that the absence of an express agreement to arbitrate by HPD, a party with a very substantial financial interest, as well as public policy considerations deriving from the nature of the venture defeat any right the partners may have to privately arbitrate disputes fundamentally affecting governance of the partnership. Since we conclude that appellants have by their course of conduct lost any right they may have had to arbitrate their existing disputes, it is unnecessary to reach these proffered alternative grounds for staying arbitration.
Accordingly, the order below permanently staying arbitration should be affirmed.
Chief Judge Wachtler and Judges Jasen, Meyer and Simons concur; Judge Alexander taking no part.
On each appeal: Order affirmed, with costs.
Cases cited
- W. T. Grant Co. v. Uneeda Doll Co. 15 NY2d 571 p. 265
- Tilbury Fabrics, Inc. v. Stillwater, Inc. 56 NY2d 624 p. 265, p. 267
- Stillman v. Stillman 80 AD2d 356 p. 265
- Stillman v. Stillman 55 NY2d 653 p. 265
- New York Telephone Co. v. Speciner 55 NY2d 1002 p. 265
- In re the Arbitration between the County of Rockland & Primiano Construction Co. 51 NY2d 1 at 8 p. 265, p. 267, p. 272
- Schlaifer v. Sedlow 51 NY2d 181 p. 265, p. 272
- Preiss/Breismeister Architects v. Westin Hotel Company-Plaza Hotel Division 86 AD2d 844 p. 265
- In re the Arbitration between Jonathan Logan, Inc. & Stillwater Worsted Mills, Inc. 31 AD2d 208 p. 265
- In re the Arbitration between Raisler Corp. & New York City Housing Authority 32 NY2d 274 p. 265
- Sullivan v. Kisly 93 AD2d 783 p. 265, p. 266
- Rusch Factors, Inc. v. Fairview Manufacturing Co. 34 AD2d 635 p. 265, p. 266, p. 273
- In re the Arbitration between United Paper Machinery Corp. & Di Carlo 14 NY2d 814 p. 265, p. 266
- Malan Construction Corp. v. Allis-Chalmers Manufacturing Co. 35 AD2d 788 p. 265
- De Sapio v. Kohlmeyer 35 NY2d 402 at 406 p. 265, p. 266, p. 267, p. 272, p. 274
- East Ramapo Central School District v. East Ramapo Teachers Ass'n 91 AD2d 969 p. 265
- Denihan v. Denihan 34 NY2d 307 at 310 p. 265, p. 266, p. 273
- In re Arbitration between Michigan Millers Mutual Insurance & Hilliard 70 Misc 2d 693 p. 265, p. 266
- In re the Arbitration between Allstate Insurance & Carrillo 69 Misc 2d 350 p. 265
- In re the Arbitration between Matarasso & Continental Casualty Co. 56 NY2d 264 p. 265, p. 266
- Scarburgh Co. v. American Manufacturers Mutual Insurance 53 NY2d 1056 p. 265
- Esquire Industries, Inc. v. East Bay Textiles, Inc. 68 AD2d 845 p. 265
- Schuylkill Fuel Corp. v. B. & C. Nieberg Realty Corp. 250 NY 304 p. 266
- Israel v. Wood Dolson Co. 1 NY2d 116 p. 266
- Schwartz v. Public Administrator 24 NY2d 65 p. 266
- Potter v. Motor Vehicle Accident Indemnification Corp. 73 AD2d 787 p. 266
- In re Zimmerman 236 NY 15 at 19 p. 266, p. 267, p. 272
- Gabor v. Spicyn 99 AD2d 1000 p. 266
- Nagy v. Arcas Brass & Iron Co. 242 NY 97 p. 266, p. 274
- In re the Arbitration between Ladin & D. & C. Textile Corp. 20 AD2d 8 p. 266
- Clurman v. Clurman 52 NY2d 1036 p. 266
- Young v. Crescent Development Co. 240 NY 244 p. 266
- Zurich Insurance v. Evans 89 Misc 2d 717 p. 266, p. 267
- In re the Arbitration between United Paper Machinery Corp. & Di Carlo 19 AD2d 143 p. 266
- Opan Realty Corp. v. Pedrone 36 NY2d 943 p. 266, p. 268
- Legislative Conference v. Board of Higher Education 38 AD2d 478 p. 266, p. 268
- Legislative Conference of the City University v. Board of Higher Education 31 NY2d 926 p. 266, p. 268
- Wertheim & Co. v. Halpert 48 NY2d 681 p. 266, p. 268
- Crawford v. Merrill Lynch, Pierce, Fenner & Smith, Inc. 35 NY2d 291 p. 267
- Braten Apparel Corp. v. Rutger Fabrics Corp. 35 AD2d 921 p. 267
- Tanbro Fabrics Corp. v. Deering Milliken, Inc. 35 AD2d 469 p. 267
- Tanbro Fabrics Corp. v. Deering Milliken, Inc. 29 NY2d 690 p. 267
- Berkey v. Third Avenue Railway Co. 244 NY 84 p. 267
- Menaker v. Padover 75 AD2d 807 p. 267
- In re the Arbitration between Deering Milliken, Inc. & Fab Industries, Inc. 50 AD2d 515 p. 267
- Epstein v. Grover 21 Misc 2d 948 p. 267
- Schubtex, Inc. v. Allen Snyder, Inc. 49 NY2d 1 p. 267, p. 268
- Lowendahl v. Baltimore & Ohio Railroad 272 NY 360 p. 267
- In re the Arbitration between Aimcee Wholesale Corp. & Tomar Products, Inc. 21 NY2d 621 p. 268
- Cadplaz Sponsors, Inc. v. Cadman Towers, Inc. 84 Misc 2d 961 p. 268
- Weiner v. Weiner 88 Misc 2d 920 p. 268
- In re the Arbitration between Greenblatt & Ottley 106 Misc 2d 169 p. 268
- In re the Arbitration between Knickerbocker Agency, Inc. & Holz 4 NY2d 245 p. 268
- In re the Arbitration between American Silk Mills Corp. & Meinhard-Commercial Corp. 35 AD2d 197 p. 268
- In re the Arbitration between Priore & Schermerhorn 237 NY 16 at 17 p. 272
- Hosiery Manufacturers Corp. v. Goldston 238 NY 22 at 27-28 p. 272
- Preiss/Breismeister Architects v. Westin Hotel Company-Plaza Hotel Division 56 NY2d 787 at 789 p. 273
- Hadjioannou v. Avramides 40 NY2d 929 p. 273
- Sherrill v. Grayco Builders, Inc. 99 AD2d 965 at 968 p. 273
- Norris v. Cooper 61 NY2d 299 at 308 p. 273