Majority
OPINION OF THE COURT
This contract dispute is between plaintiff, a national provi
In November 1984 plaintiff and defendant entered into such an agreement. The contract provided for the licensing of the ACES base system software for $160,000, plus some $44,000 for the preparation of functional specifications to adapt the ACES system to plaintiff’s particular needs. The Agreement required defendant to furnish the customized enhancements provided by the specifications, at a cost not to exceed some $390,000, based upon invoiced expenditures of time and materials.
The Agreement contained a broad limitation of liability clause. Section 7 provided that "[i]n no event shall [plaintiff] be liable for any lost profits, lost savings or other consequential damages, even if [plaintiff] has been advised of the possibility of or could have foreseen such damages”. Defendant was similarly absolved from liability for "loss of profit, loss of business, or other financial loss * * * resulting from * * * [defendant’s] performance or non-performance” but an exception to this limitation was provided "for intentional misrepresentations, or damages arising out of [defendant’s] willful acts or gross negligence” (emphasis supplied).
By December 1985, defendant had furnished the base system and functional specifications without dispute for an aggregate compensation of $204,000. Two sets of enhancements were offered by defendant, but were rejected by plaintiff. It was at this point, according to plaintiff’s proof, that defendant demanded an upward adjustment of the contract ceiling for enhancements, failing which it announced it would withdraw from the project. When plaintiff refused defendant’s demand, defendant discontinued further performance.
Plaintiff then commenced this action, seeking a refund of the sums it paid defendant plus general and consequential damages. Defendant interposed the limitation on liability contained in section 7 of the parties’ Agreement as a partial
The jury made a special finding that defendant’s acts were willful and awarded plaintiff $3,961,000 in damages, including $581,000 cover damages (see, UCC 2-712) and $2,807,000 in lost savings.
The Trial Judge denied a defense motion for judgment notwithstanding the verdict. It held that there was evidence upon which the jury could reasonably find defendant’s acts willful, namely, (1) defendant had no excuse or justification for demanding an increase in compensation in excess of the contract’s maximum price; (2) defendant was aware that if it withdrew from the project before completion, plaintiff would have "to start from scratch and find an entirely new system”; and (3) defendant’s refusal to perform was "motivated by its desire to eliminate contractual obligations it perceived to be an obstacle to any sale of its computer division to a company known as Erisco”.
On appeal, the Appellate Division modified on the law, reducing damages to the $204,000 plaintiff paid defendant for its partial performance, plus interest, costs and disbursements ( 192 AD2d 83 ). The Court interpreted the willful act exception to the limitation of liability provision in the contract as requiring acts constituting the commission of a tort. It found, as a matter of law, that the proof did not establish any such tortious conduct, but merely an intentional abandonment which was held insufficient to invoke the exception. In part, the Appellate Division concluded that intentional abandonment alone could not constitute the willful acts referred to in the parties’ contract because " '[w]illfuP is a term of tort, not contract” (id., at 90), and for this reason, tort law concepts of willful acts necessarily applied. This Court granted plaintiff permission to appeal from the Appellate Division’s ruling.
Plaintiffs primary argument for reversal is that the Appellate Division erred in refusing to attribute the common, ordinary meaning of willful acts as merely deliberate or
Several factors strongly weigh against narrowly applying the limitation on defendant’s liability to inadvertent malperformance or nonperformance, as plaintiff’s interpretation of the willful acts exception to the limitation of liability provision would dictate.
Generally in the law of contract damages, as contrasted with damages in tort, whether the breaching party deliberately rather than inadvertently failed to perform contractual obligations should not affect the measure of damages. As was stated by then-Justice Bergan in Briefstein v Rotondo Constr. Co. ( 8 AD2d 349 ):
"An intention not to perform [a contract] does not bring on heavier damages than actual nonperformance. The policy which runs through the fabric of the law of contracts is to bind a party by what he agrees to do whether or not he intends to do what he agrees” (id., at 351 [emphasis supplied]; see also, Globe Ref. Co. v Landa Cotton Oil Co., 190 US 540 , 544 [Holmes, J.]; 5A Corbin, Contracts § 1123; 3 Farnsworth, Contracts § 12.17a [2d ed]).
Plaintiff has not advanced any reason why the parties would have drawn such a distinction between inadvertent and intentional nonperformance with respect to the damages limitation clause in their Agreement.
"[W]ith certain exceptions, the courts see no harm in express agreements limiting the damages to be recovered for breach of contract![1] 1 Public policy may forbid the enforcement of penalties against a defendant; but it does not forbid the enforcement of a limitation in his favor. Parties sometimes make agreements and expressly provide that they shall not be enforceable at all, by any remedy legal or equitable. They may later regret their assumption of the risks of non-performance in this manner; but the courts let them lie on the bed they made. Where a contract provides that damages for breach shall not be recoverable beyond a specified sum, it is obvious that the risk of loss beyond that sum is being assumed by the promisee. If the law allows him to assume the whole risk, with no remedy whatever, it is obvious that it will allow him to assume a part less than the whole.” (5 Corbin, Contracts, § 1068, at 386; see also, Patrick Petroleum Corp. v Callón Petroleum Co., 531 F2d 1312 , 1315-1318.)
Repeatedly throughout their Agreement here, the parties agreed to shift to plaintiff the risk of a substantial portion of any economic loss caused by defendant’s nonperformance by excluding plaintiff’s right of recovery of consequential damages such as those it now claims. Thus, section 10 of the Agreement provided that in the event that the ACES system failed to perform in accordance with the specifications within the first year after acceptance, plaintiff had the right to "terminate this Agreement and receive a full refund of all monies paid hereunder” (Agreement § 10 [b] [i] [emphasis supplied]). The same section likewise limited plaintiff’s remedies in the event that defendant "commits any material breach * * * and fails to remedy such breach within thirty (30) days after written notice” (Agreement § 10 [b] [ii]). Section
* The exceptions Professor Corbin notes are contracts of adhesion (5 Corbin, Contracts § 1068, at 386, n 84.5), or when the breach is also tortious (id., at 389).
Plaintiff’s construction of the general limitation on liability section, essentially restricting it to inadvertent breaches in the course of defendant’s performance of the contract, clearly is inconsistent with sections 1 (k), 10 and 12 of the Agreement in which plaintiff agreed to limit its remedies for defendant’s nonperformance of the most vital of its obligations under the Agreement, even when such nonperformance persists after notice. Plaintiff’s construction of the willful acts exception to the general limitation on liability section of the Agreement thus violates one of the primary canons of contract construction.
"A cardinal principle governing the construction of contracts is that the entire contract must be considered and, as between possible interpretations of an ambiguous term, that will be chosen which best accords with the sense of the remainder of the contract” (Rentways, Inc. v O’Neill Milk & Cream Co., 308 NY 342 , 347).
Moreover, plaintiff’s construction of the willful acts exception to defendant’s immunity from consequential damages in section 7 of the Agreement would eliminate any semblance of reciprocity between plaintiff and defendant as to their exposure to liability for heavy consequential damages, in a dispute between the parties over contract performance. Under plaintiff’s narrow interpretation of the protection afforded defen
In excepting willful acts from defendant’s general immunity from liability for consequential damages under section 7 of the Agreement, we think the parties intended to narrowly exclude from protection truly culpable, harmful conduct, not merely intentional nonperformance of the Agreement motivated by financial self-interest. Under the interpretation tool of ejusdem generis applicable to contracts as well as statutes, the phrase "willful acts” should be interpreted here as referring to conduct similar in nature to the "intentional misrepresentation” and "gross negligence” with which it was joined as exceptions to defendant’s general immunity from liability for consequential damages (see, Bers v Erie R. R. Co., 225 NY 543 , 546; Krulewitch v National Importing & Trading Co., 195 App Div 544 , 546). We, therefore, conclude that the term willful acts as used in this contract was intended by the parties to subsume conduct which is tortious in nature, i.e., wrongful conduct in which defendant willfully intends to inflict harm on plaintiff at least in part through the means of breaching the contract between the parties.
As thus defined, limiting defendant’s liability for consequential damages to injuries to plaintiff caused by intentional misrepresentations, willful acts and gross negligence does not offend public policy. As we said in Sommer v Federal Signal Corp. ( 79 NY2d 540 ) the conduct necessary "to pierce an
Finally, we conclude that plaintiffs proof was insufficient as a matter of law to establish that defendant willfully intended to inflict harm on plaintiff through its abandonment of the contract. Apart from evidence of alleged misconduct by defendant during the course of its performance of the contract, totally irrelevant to the subsequent withdrawal from the project, the proof, as plaintiff has indeed stressed, was that defendant’s repudiation of the Agreement was motivated exclusively by its own economic self-interest in divesting itself of a highly unprofitable business undertaking in order to promote the sale of its computer software division to a competitor company. Consequential damages resulting from that kind of contract nonperformance constitute a risk which plaintiff assumed under section 7 of the parties’ Agreement.
Accordingly, the order of the Appellate Division should be affirmed, with costs.
Chief Judge Kaye and Judges Simons, Titone, Bellacosa, Smith and Ciparick concur.
Order affirmed, with costs.
Cases cited
- Kalisch-Jarcho, Inc. v. City of New York 58 NY2d 377 at 385 p. 431, p. 432, p. 439
- Weiss v. Weiss 52 NY2d 170 p. 431
- Graphic Scanning Corp. v. Citibank N. A. 116 AD2d 22 p. 431
- Messina v. Lufthansa German Airlines 47 NY2d 111 p. 431
- Procopio v. Fisher 83 AD2d 757 p. 431
- Anderson v. How 116 NY 336 p. 431
- American Transit Insurance v. Corcoran 76 NY2d 977 p. 431
- Old Republic Life Insurance v. Thacher 12 NY2d 48 p. 431
- People v. Broady 5 NY2d 500 p. 432
- Broady v. New York 361 US 8 p. 432
- Insurance of Pennsylvania v. Corcoran 160 AD2d 304 p. 432
- Martin v. City of Cohoes 37 NY2d 162 p. 432
- Fioranelli v. News Building Corp. 102 Misc 2d 825 p. 432
- McCummings v. New York City Transit Authority 81 NY2d 923 p. 432
- Sagorsky v. Malyon 307 NY 584 p. 432
- S. Kornblum Metals Co. v. Intsel Corp. 38 NY2d 376 p. 432
- Van Valkenburgh, Nooger & Neville, Inc. v. Hayden Publishing Co. 30 NY2d 34 p. 432
- Lewis v. Weiner 191 AD2d 172 p. 432
- Held v. New York Telephone Co. 73 Misc 2d 582 p. 432
- Dobess Realty Corp. v. City of New York 79 AD2d 348 p. 432
- Dobess Realty Corp v. City of New York 53 NY2d 1054 p. 432
- Eighth Avenue Coach Corp. v. City of New York 286 NY 84 p. 432
- Sunnybrook Realty Co. v. State 15 Misc 2d 739 p. 432
- Sunnybrook Realty Co. v. State 9 NY2d 960 p. 432
- Corhill Corp. v. S. D. Plants, Inc. 9 NY2d 595 p. 432
- Dady v. O'Rourke 172 NY 447 p. 432
- Spaulding v. Benenati 57 NY2d 418 p. 432
- Laba v. Carey 29 NY2d 302 p. 432
- Muzak Corp. v. Hotel Taft Corp. 1 NY2d 42 p. 432
- Briefstein v. P. J. Rotondo Construction Co. 8 AD2d 349 p. 432, p. 435
- Tesoro Petroleum Corp. v. Holborn Oil Co. 108 AD2d 607 p. 432
- Zook v. Accident & Indemnity Co. 64 AD2d 701 p. 432
- Metropolitan Life Insurance v. Noble Lowndes International, Inc. 192 AD2d 83 p. 432, p. 434
- Manshul Construction Corp. v. City of New York 143 AD2d 333 p. 432
- Green Bus Lines, Inc. v. General Motors Corp. 169 AD2d 758 p. 432
- Murphy v. American Home Products Corp. 58 NY2d 293 p. 432
- Globe Refining Co. v. Landa Cotton Oil Co. 190 US 540 at 544 p. 435
- Rentways, Inc. v. O'Neill Milk & Cream Co. 308 NY 342 at 347 p. 437
- Fleischman v. Furgueson 223 NY 235 at 241 p. 438
- Tibbetts Contracting Corp. v. O & E Contracting Co. 15 NY2d 324 at 337 p. 438
- Schoellkopf v. Coatsworth 166 NY 77 at 84 p. 438
- Gillet v. Bank of America 160 NY 549 at 557-558 p. 438
- Bers v. Erie Railroad 225 NY 543 at 546 p. 438
- Sommer v. Federal Signal Corp. 79 NY2d 540 p. 438