Majority
OPINION OF THE COURT
This case presents the puzzle of when the one-year limitations period for suing a surety on a public improvement construction bond begins to run, within the meaning of State Finance Law • § 137 (4) (b). Also implicated is whether contractual provisions in a subcontract can effectively toll the statutory time period.
We conclude that the one-year period starts to be counted as of the time when a subcontractor has demanded final payment from the general contractor with whom it contracted, and 90 days have passed since the subcontractor ceased work on the project. This time frame may not be extended or overridden by any provisions of the subcontract.
I.
This controversy arises out of a public improvement contract for the construction of a health care facility at Green Haven
Defendant General Accident provided the statutory payment bond for the project. The document stated that it was a Comptroller’s Form Bond issued pursuant to State Finance Law § 137 and that “all rights and remedies on this bond * * * shall be determined in accordance with the provisions, conditions and limitations of said Section.”
Windsor started its work on the project on April 12, 1994. The State terminated its prime contract with Eberhard on March 28, 1995. This resulted in the termination of the subcontract with Windsor and in Windsor’s cessation of work on the project. Windsor’s president later asserted in an affidavit:
“Prior to the termination, Eberhard had already fallen behind in payments to Windsor. Following the termination, I contacted Eberhard on several occasions in an attempt to secure final payment, all to no avail.”
On March 31, 1995, three days after the State terminated the contract with Eberhard, Windsor wrote to General Accident, stating:
“As of this date we are owed the amount of $211,192.00. Plus, we are awaiting charges from our erector for changing opening and delays.
“For you [sic] convenience we have hereby attached a copy of our request for payment sent to Eberhard Construction.
“Please regard this as a notice for payment. Please be kind enough to inform us as to when we can expect the monies due to us.”
At all relevant times, Eberhard and General Accident denied owing Windsor additional compensation and rejected Windsor’s payment demands. Indeed, Eberhard took the position that Windsor’s failure to fulfill its obligations under the subcontract caused the State to terminate the prime contract with Eberhard.
On April 19, 1995, Windsor filed a notice of mechanics’ lien in the amount of $214,036.36, which Windsor indicated was
II
On April 19, 1995, Windsor also filed a demand for arbitration against Eberhard, seeking the $214,036.36. Windsor immediately notified General Accident of the arbitration, and General Accident participated in the proceedings to the extent that it joined Eberhard in the attempt to prove Windsor had breached its subcontract; General Accident also asserted that Windsor was responsible for General Accident’s own losses incurred as a result of its having to arrange to complete the project following the termination of Eberhard, its principal.
Windsor won an arbitration award against only Eberhard on April 2, 1996 in the sum of $231,678.20. Supreme Court confirmed the award and, on December 24, 1996, entered a $255,130.22 judgment against Eberhard. Unfortunately for Windsor, Eberhard was apparently insolvent by this time. Windsor, thus turned its recovery effort toward General Accident, which denied its demand for payment.
In early 1997, Windsor sued General Accident, seeking $255,130.22, the amount of the judgment entered against Eberhard. General Accident raised the Statute of Limitations as an affirmative defense (State Finance Law § 137 [4] [b]), and Supreme Court granted summary judgment to General Accident on this ground.
The Appellate Division disagreed. It relied on specific provisions of Windsor’s subcontract and found that none of the “final payment” provisions in the subcontract could operate to raise a time bar. As pertinent to this appeal, the Appellate Division unanimously reversed and granted that part of Windsor’s motion seeking summary judgment on its first cause of action pursuant to the payment bond.
This Court granted General Accident leave to appeal. We now reverse, reinstate the Supreme Court ruling, and dismiss Windsor’s complaint.
State Finance Law § 137 (4) (b) states:
“No action on a payment bond furnished pursuant to this section shall be commenced after the expiration of one year from the date on which final payment under the claimant’s subcontract became due” (emphasis added).
Together, subdivisions (3) and (4) set the beginning and endpoint measurements for a lawsuit against a surety in these circumstances. They establish a date upon which the claim against a surety becomes ripe (State Finance Law § 137 [3]) and a date after which time has run out for an action on the claim (State Finance Law § 137 [4] [b]). The pinpointing of this latter date is the operative question in this case; it hinges on the definition of “the date on which final payment under the claimant’s subcontract became due” (State Finance Law § 137 [4] [b]).
This date is critical because the lawsuit must be started within one year from that fixed point. In this case, Windsor proffers as the date upon which this one-year period begins the date of the favorable arbitration determination. To so calculate this date, it relies on a combination of the final payment provision (“when the Subcontractor’s work is fully performed in accordance with the requirements of the Contract Documents, the Architect has issued a Certificate for Payment covering the Subcontractor’s completed Work and the Contractor has received payment from the Owner”) and the arbitration clause (“[a]ny controversy or claim between the Contractor and the Subcontractor arising out of or related to this Subcontract, or the breach thereof, shall be settled by arbitration”). We reject Windsor’s contract-based calculation of the measuring date.
Our holding focuses principally on when the one-year limitations period begins to run, within the meaning of State Finance Law § 137 (4) (b). We conclude that it starts at a point when a subcontractor who has directly contracted with the general contractor has submitted an invoice for final payment (or given the functional equivalent thereof) and 90 days have passed since the subcontractor has ceased to work on the project. Contractual provisions between the subcontractor and general contractor cannot modify this starting-point date. The necessity to incorporate and satisfy all these considerations is supported by the statute, as well as precedent of this Court.
A.
The language — “date on which final payment under the claimant’s subcontract became due” — stems from a bill recom
In 1963, a new bill was recommended by the Commission. Like the original bill, it included a provision regarding suit against a surety “like that of the [Federal] Miller Act * * * It adds an exception, however, under which, if the claimant is a subcontractor, the one year period runs from the date on which final payment under the subcontract became due” (1963 Report of NY Law Rev Commn, at 105). In 1964, the 1963 recommendations of the Commission were adopted in substantially unchanged form and State Finance Law § 137 (4) (b) was enacted to provide:
“No action on a payment bond furnished pursuant, to this section shall be commenced after the expiration of one year from the date on which the claimant performed the last of the labor or furnished the last of the material for which such action is brought, except that if the claimant is a subcontractor of the contractor, no such action shall be commenced after the expiration of one year from the date on which final payment under the subcontract became due.”
Legislative history indicates that in 1980, this subdivision was amended into its current version, specifically to render the original “exception” for subcontractors universally applicable to all claimants (see, Mem of Assembly Member Goldstein, Bill Jacket, L 1980, ch 360). This change enabled secondary subcontractors (sub-subcontractors) to pursue an action based on a claim within one year after final payment is due, rather than within one year after they have completed their work, because the one-year period from completion of work was seen as too stringent a limitation on them (see, id.). “Frequently these [secondary sub-] contractors finish their work more than a year before payment is due them and thus when payment is received they have no recourse should such payment not be to their satisfaction” (id.).
For example, if the claim cannot mature until 90 days after the date of last work performed, but final payment was demanded as due before this date of last work performed, then a claimant may lose at least 90 days of its statutory one-year limitation. This diminishment conflicts with the intent of the 1980 amendments, which, although they addressed a variation on this diminishment of time in which to sue, essentially sought to insure that all levels of subcontractors would have a full year in which they could sue on the bond.
Here, because the project was terminated by the State, Windsor’s demand for final payment occurred virtually simultaneously with its date of final performance. Yet, its ability to sue the surety did not accrue until 90 days after its date of final performance. This case provides a prime reason for holding that both subdivisions (3) and (4) of State Finance Law § 137, are implicated in tandem.
B.
Legnetto ( 92 NY2d 275 , supra) provides helpful guidance with respect to the Statute of Limitations issue presented here. In that case, the parties disputed whether the subcontractor had adequately performed its work under the contract, and it was undisputed that the contractor had failed to pay the subcontractor the full amount due under the subcontract. Thus, the question whether the contractor would actually pay the subcontractor did not change the fact that final payment to the subcontractor had legally become due. At that point and circumstance, the statutory formula takes over and controls (see, Sehuler-Haas Elec. Co. v Aetna Cas. & Sur. Co., 40 NY2d 883 , 885; see also, Sturdy Concrete Corp. v NAB Constr. Corp., 65 AD2d 262 , 271, appeal dismissed 46 NY2d 938 ),
Here, Windsor’s president asserted that Windsor considered final payment due as of at least March 31, 1995, yet Windsor
Windsor’s strategic actions belie the legal merit of its current position. Windsor itself was asserting that final payment was due, despite the fact that the final payment events delineated in the subcontract had not occurred and the project had been terminated. Windsor’s “new logic” falters over the premise that payment may become legally due to the subcontractor before it must be actually paid to the subcontractor. Additionally, the subcontract here provides that the arbitration provision “shall not be deemed a limitation of rights or remedies which the Subcontractor may have under * * * applicable labor or material payment bonds.” Thus, if courts are to look at the contract at all, that examination here further supports General Accident’s assertion that the date when final payment becomes due is not determined by the date the arbitration is resolved. Indeed, the triggering date for the limitations period should not be pegged to so uncertain an event with its usual confirmation steps and review potentialities.
Instructively, in Legnetto, this Court refused to turn to the terms of the contract to determine whether the bond could be interpreted as having a Statute of Limitations greater than one year. The bond was silent as to its Statute of Limitations and because the bond itself did not contain provisions more ample than the statute, the specific limitations period provided by the statute was given full effect.
That is so here, too. The bond provided by General Accident clearly incorporates the one-year limitations period from the statute; the statute is also specifically referenced on the face of the bond. According to Legnetto, and contrary to the theory Windsor proposes and the rationale that the Appellate Division adopted, we must refuse to look beyond the face and terms of the bond to the contract provisions. To recalculate the Statute of Limitations’ starting point and duration on that basis, as applied to this controversy, is not supportable.
We observe that this case yields the ironic result of a subcontractor being shut out from a timely lawsuit by the very
There are also strong policy reasons for not reading contract clauses to interject an open durational set of events into this statute. That practice would undermine the essential purpose of the limitations period and would effectively circumvent the intent of the Legislature in this respect (see generally, Bill Jacket, L 1964, ch 700; Bill Jacket, L 1980, ch 360). We cannot, by adroit construction of the statute that sidesteps its purpose, as well as our guiding precedents, countenance a sympathetic escape hatch for a particular subcontractor’s claim under these circumstances. That would unjustifiably damage the desirable definiteness fabric and principle of this statutory formulation. The adverse impact on the construction industry in forestalling prompt, fair resolution of disputes growing out of this vast, complicated commercial enterprise contraindicates the theory advanced by Windsor, and adopted by the Appellate Division.
Accordingly, the order of the Appellate Division should be reversed, with costs, and the complaint should be dismissed.
Chief Judge Kaye and Judges Smith, Levine, Ciparick, Wesley and Rosenblatt concur.
Order reversed, with costs, plaintiff’s motion for summary judgment denied and defendant’s cross motion for summary judgment dismissing the complaint granted.
Cases cited
- A.C. Legnetto Construction, Inc. v. Hartford Fire Insurance 92 NY2d 275 p. 125, p. 126, p. 127, p. 133
- Jess F. Howes, Inc. v. Hudson Valley District Council of Carpenters 146 AD2d 163 p. 125, p. 126, p. 127
- Construction Pace Setters, Inc. v. United States Fidelity & Guaranty Co. 225 AD2d 1090 p. 125, p. 126, p. 127
- William H. Lane, Inc. v. American Druggists' Insurance 111 AD2d 970 p. 125, p. 126
- Scaccia Concrete Corp. v. Hartford Fire Insurance 212 AD2d 225 p. 125, p. 126
- Bello v. Aetna Casualty & Surety Co. 144 AD2d 513 p. 125, p. 126, p. 127
- Cortland Paving Co. v. Capitol District Contractors, Ltd. 111 AD2d 955 p. 125
- Concrete Construction Corp. v. Commercial Union Insurance 68 AD2d 866 p. 125
- Cabrini Medical Center v. Desina 64 NY2d 1059 p. 125, p. 127
- Phillips Construction Co. v. City of New York 61 NY2d 949 p. 125, p. 127
- West-Fair Electric Contractors v. Aetna Casualty & Surety Co. 87 NY2d 148 p. 125
- Huber Lathing Corp. v. Aetna Casualty & Surety Co. 132 AD2d 597 p. 125
- Palcon Industries, Inc. v. Travelers Indemnity Co. 114 AD2d 667 p. 125
- Conesco Industries, Ltd. v. St. Paul Fire & Marine Insurance 184 AD2d 956 p. 126
- Conesco Industries, Ltd. v. St. Paul Fire & Marine Insurance 210 AD2d 596 p. 126
- Duffy v. Horton Memorial Hospital 66 NY2d 473 p. 126
- Vastola v. Maer 48 AD2d 561 p. 126
- Vastola v. Maer 39 NY2d 1019 p. 126
- Pearlman v. Reliance Insurance 371 US 132 p. 126
- Fidelity & Deposit Co. v. Parsons & Whittemore Contractors Corp. 48 NY2d 127 p. 126
- Sturdy Concrete Corp. v. NAB Construction Corp. 65 AD2d 262 at 271 p. 126, p. 133
- Ardsley Construction Co. v. Port Authority of New York & New Jersey 54 NY2d 876 p. 126
- Tufano Contracting Corp. v. Port of New York Authority 13 NY2d 848 p. 126
- Arnell Construction Corp. v. Board of Education 193 AD2d 640 p. 126
- General Railway Signal Corp. v. L.K. Comstock & Co. 254 AD2d 759 p. 126
- Yonkers Contracting Co. v. Port Authority Trans-Hudson Corp. 208 AD2d 63 p. 126
- Yonkers Contracting Co. v. Port Authority Trans-Hudson Corp. 87 NY2d 927 p. 126
- Schuler-Haas Electric Corp. v. Aetna Casualty & Surety Co. 49 AD2d 60 p. 126
- Schuler-Haas Electric Co. v. Aetna Casualty & Surety Co. 40 NY2d 883 at 885 p. 126, p. 133
- Grossman Steel & Aluminum Corp. v. Samson Window Corp. 54 NY2d 653 p. 126
- Action Interiors, Inc. v. Component Assembly Systems Inc. 144 AD2d 606 p. 126
- Carl A. Morse, Inc. v. Rentar Industrial Development Corp. 85 Misc 2d 304 p. 127
- Carl A. Morse, Inc. v. Rentar Industrial Development Corp. 56 AD2d 30 p. 127
- Carl A. Morse, Inc. v. Rentar Industrial Development Corp. 43 NY2d 952 p. 127
- Sommer v. Anthony J. Quarant Contracting, Inc. 40 AD2d 95 p. 127
- Davidson Pipe Supply Co. v. Wyoming County Industrial Development Agency 85 NY2d 281 p. 127
- Chittenden Lumber Co. v. Silberblatt & Lasker, Inc. 288 NY 396 p. 127
- Dutchess Quarry & Supply Co. v. Firemen's Insurance Co. of Newark 190 AD2d 36 p. 127, p. 128
- In re the Arbitration between Weinrott & Carp 32 NY2d 190 p. 127
- Rembrandt Industries, Inc. v. Hodges International, Inc. 38 NY2d 502 p. 127
- In re the Arbitration between S & W Fine Foods, Inc. & Office Employees International Union, Local 153 8 AD2d 130 p. 127
- In re the Arbitration between S & W Fine Foods, Inc. & Office Employees International Union, Local 153 7 NY2d 1018 p. 127
- Kilduff v. Donna Oil Corp. 74 AD2d 562 p. 127
- Dimacopoulos v. Consort Development Corp. 158 AD2d 658 p. 127
- Brescia Construction Co. v. Walart Construction Co. 264 NY 260 p. 127
- Zacher v. Oakdale Islandia Ltd. Partnership 211 AD2d 712 p. 127
- County of Rockland v. Aetna Casualty & Surety Co. 129 AD2d 606 p. 127
- Arnell Construction Corp. v. Village of North Tarrytown 64 NY2d 916 p. 127
- Blanco v. American Telephone & Telegraph Co. 90 NY2d 757 p. 128
- MRI Broadway Rental, Inc. v. United States Mineral Products Co. 92 NY2d 421 p. 128
- Ely-Cruikshank Co. v. Bank of Montreal 81 NY2d 399 p. 128
- People v. Standard Accident Insurance 17 AD2d 1 p. 128
- People v. Standard Accident Insurance 13 NY2d 751 p. 128
- Bayridge Air Rights, Inc. v. Blitman Construction Corp. 80 NY2d 777 p. 128
- Florio v. Cook 48 NY2d 792 p. 128